AGENDA
OPEN PORTION OF THE Council Meeting

Monday, 23 October 2017

AT 5.00 pm


 


 

Agenda (Open Portion)

Council Meeting

Page 3

 

23/10/2017

 

 

ORDER OF BUSINESS

 

APOLOGIES AND LEAVE OF ABSENCE

1.        Confirmation of Minutes. 7

2.        Transfer of Agenda Items. 7

3.        Communication from the Chairman. 7

4.        Notification of Council WorKshops. 8

5.        Public Question Time. 8

6.        Petitions. 8

7.        Consideration of Supplementary Items. 8

8.        Indications of Pecuniary and Conflicts Of Interest. 8

Reports of Committees. 9

City Planning Committee

9.        Council Acting as Planning Authority. 9

9.1     16-20 Davey Street and 3 Argyle Street, Hobart - Hydraulic Infrastructure  9

9.2     1-3 Elizabeth Street, Hobart - Public Art (Installation) 12

9.3     29 Morrison Street, Hobart  Outdoor Dining - PLN-17-614. 14

9.4     10 David Avenue, Sandy Bay - Partial Demolition and Front Fencing. 14

9.5     43 Runnymede Street, Battery Point - Change of Use to Visitor Accommodation  15

9.6     162 Macquarie Street, Hobart and Adjacent Road Reserve - Alterations and Signage. 17

9.7     15-17 Liverpool Street, 61 Brooker Avenue, 71 Brooker Avenue, CT 160498/2, Brooker Avenue Road Reservation, Bathurst Street Road Reservation, Hobart - Shared Use Bicycle and Pedestrian Bridge. 20

9.8     260 Sandy Bay Road, Sandy Bay and Adjacent Road Reserve - Signage and Alterations to Car Park Access and Layout 30

10.     Building Height Standards Review - Hobart Interim Planning Scheme 2015 - Sullivans Cove Planning Scheme 1997 - Project Brief 31

Community, Culture and Events Committee

11.     2017-18 Fees and Charges - Salamanca Market 32

12.     Five Year Review of Salamanca Market Stallholder Licence Agreement 32

13.     Urban Art Walls: Iteration 4 - Bidencopes Lane. 32

14.     Australia Day. 32

15.     Late Night Toilet Provision - Salamanca/Waterfront Precinct 32

16.     Community Development Grants Program - Recommendations - Round Two 2017 Round. 33

17.     Musica Viva Tasmania - Extension of Partnership Arrangement 33

18.     2017 The Taste of Tasmania - New Year's Eve, Ticket Pricing and Retail Recommendations. 33

Economic Development & Communications Committee

19.     Community Development Grants Program - Recommendations Marketing Grants 2017. 34

Finance Committee

20.     2016-17 Financial Statements. 35

Governance Committee

21.     City of Hobart - Draft Customer Service Charter 36

22.     Proposed 2018 Council and Committee Meeting Schedule and Temporary City Planning Committee Delegation. 36

Parks and Recreation Committee

23.     Naming - Pedestrian Bridge Across Tasman Highway from the Cenotaph to the Domain. 38

24.     Request for Easement - Queens Domain. 38

25.     Request for Lease - Sandown Park - Optus. 38

26.     Response to Petition - Girrabong Park (Corner of Firth and Girrabong Roads), Lenah Valley. 38

Special Report – General Manager

27.     Public Meeting in Response to Building Height Petition. 39

28.     Closed Portion Of The Meeting.. 75

 


 

Agenda (Open Portion)

Council Meeting

Page 6

 

23/10/2017

 

 

A meeting of the Open Portion of the Council will be held in the Council Chamber, Town Hall on Monday, 23 October 2017 at 5.00 pm.

 

N D Heath

General Manager

ALDERMEN:

Lord Mayor S L Hickey

Deputy Lord Mayor R G Christie

Alderman M Zucco

Alderman J R Briscoe

Alderman E R Ruzicka

Alderman P T Sexton

Alderman H C Burnet

Alderman P S Cocker

Alderman D C Thomas

Alderman A M Reynolds

Alderman T M Denison

Alderman W F Harvey

APOLOGIES: Nil

 

 

LEAVE OF ABSENCE:

Alderman D C Thomas

 

1.       Confirmation of Minutes

 

The Chairman reports that she has perused the minutes of the meeting of the Open Portion of the Council meeting held on Monday, 2 October 2017, finds them to be a true record and recommends that they be taken as read and signed as a correct record.

 

 

 

 

2.       Transfer of Agenda Items

 

Are there any items, which the meeting believes, should be transferred from this agenda to the closed agenda or from the closed agenda to the open agenda, in accordance with the procedures allowed under Section 15 of the Local Government (Meeting Procedures) Regulations 2015?

 

 

 

3.       Communication from the Chairman

 

4.       Notification of Council WorKshops

 

In accordance with the requirements of the Local Government (Meeting Procedures) Regulations 2015, the General Manager reports that no Council workshops have been conducted since the last ordinary meeting of the Council.

 

5.       Public Question Time

 

 

 

 

6.       Petitions

 

 

 

 

7.       Consideration of Supplementary Items

Ref: Part 2, Regulation 8(6) of the Local Government (Meeting Procedures) Regulations 2015.

RECOMMENDATION

 

That the Council resolve to deal with any supplementary items not appearing on the agenda, as reported by the General Manager in accordance with the provisions of the Local Government (Meeting Procedures) Regulations 2015.

 

 

 

 

8.       Indications of Pecuniary and Conflicts Of Interest

Ref: Part 2, Regulation 8(7) of the Local Government (Meeting Procedures) Regulations 2015.

 

Aldermen are requested to indicate where they may have any pecuniary or conflict of interest in respect to any matter appearing on the agenda, or any supplementary item to the agenda, which the committee has resolved to deal with.


 

Agenda (Open Portion)

Council Meeting

Page 8

 

23/10/2017

 

 

Reports of Committees

 

City Planning Committee

 

9.       Council Acting as Planning Authority

 

In accordance with the provisions of Part 2 Regulation 25 of the Local Government (Meeting Procedures) Regulations 2015, the intention of the Council to act as a planning authority pursuant to the Land Use Planning and Approvals Act 1993 is to be noted.

 

In accordance with Regulation 25, the Council will act as a planning authority in respect to those matters appearing under this heading on the agenda, inclusive of any supplementary items.

 

The Council is reminded that in order to comply with Regulation 25(2), the General Manager is to ensure that the reasons for a decision by a Council or Council Committee acting as a planning authority are recorded in the minutes.

 

9.1      16-20 Davey Street and 3 Argyle Street, Hobart - Hydraulic Infrastructure

            pln-17-615 - File Ref: F17/135844

Ref:    Open CP 7.1.1, 9/10/2017

Application Expiry Date: 15 November 2017

Extension of Time: Not applicable

 

Pursuant to the Sullivans Cove Planning Scheme 1997, the Council approve the application for Hydraulic Infrastructure at 16­20 Davey Street and 3 Argyle Street HOBART for the reasons outlined in the officer’s report attached to item 7.1.1 of the Open City Planning Committee agenda of 9 October 2017 and a permit containing the following conditions be issued:

GEN

 

The use and/or development must be substantially in accordance with the documents and drawings that comprise PLN­17­615 ­ 16­20 DAVEY STREET AND 3 ARGYLE STREET HOBART TAS 7000 ­ Final Planning Documents except where modified below.

 

Reason for condition

 

To clarify the scope of the permit.

 

TW

 

The use and/or development must comply with the requirements of TasWater as detailed in the form Submission to Planning Authority Notice, Reference No. TWDA 2017/01348­HCC dated 29 August 2017 as attached to the permit.

 

Reason for condition

 

To clarify the scope of the permit.

 

THC

 

The use and/or development must comply with the requirements of the Tasmanian Heritage Council as detailed in the Notice of Heritage Decision, THC Application No. 5401 dated 22 September 2017 as attached to the permit.

 

Reason for condition

 

To clarify the scope of the permit.

 

HER 6

 

All onsite excavation and disturbance must be monitored. If any features or deposits of an archaeological nature are discovered on the site during excavation or disturbance:

 

 

1.       All excavation and/or disturbance must stop immediately; and

 

2.       A qualified archaeologist must be engaged to attend the site and provide advice and assessment of the features and/or deposits discovered and make recommendations on further excavation and/or disturbance; and

 

3.       All and any recommendations made by the archaeologist engaged in accordance with (2) above must be complied with in full; and

 

4.       All features and/or deposits discovered must be reported to the Council with one (1) days of the discovery; and

 

5.       A copy of the archaeologists advice, assessment and recommendations obtained in accordance with (2) above must be provided to Council within three (3) days of receipt of the advice, assessment and recommendations.

 

Excavation and/or disturbance must not recommence unless and until approval is granted from the Council.

 

Reason for condition

 

To ensure that work is planned and implemented in a manner that seeks to understand, retain, protect, preserve and manage significant archaeological evidence as required in the Sullivans Cove Planning Scheme 1997.

 

ADVICE

 

The following advice is provided to you to assist in the implementation of the planning permit that has been issued subject to the conditions above. The advice is not exhaustive and you must inform yourself of any other legislation, by­laws, regulations, codes or standards that will apply to your development under which you may need to obtain an approval. Visit the Council's website for further information.

 

Prior to any commencement of work on the site or commencement of use the following additional permits/approval may be required from the Hobart City Council.

 

OCCUPATION OF THE PUBLIC HIGHWAY

 

Permit for the occupation of the public highway for construction or special event (e.g. placement of skip bin, crane, scissor lift etc). Click here for more information.

 

Permit to Open Up and Temporarily Occupy a Highway (for work in the road reserve). Click here for more information.

 

DIAL BEFORE YOU DIG

Click here for dial before you dig information.

.

 

9.2      1-3 Elizabeth Street, Hobart - Public Art (Installation)

            pln-17-603 - File Ref: F17/135872

Ref:    Open CP 7.1.2, 9/10/2017

Application Expiry Date: 25 October 2017

Extension of Time: Not applicable

 

Pursuant to the Sullivans Cove Planning Scheme 1997, the Council approve the application for Public Art (Installation) at 1­3 Elizabeth Street, Hobart for the reasons outlined in the officer’s report attached to item 7.1.2 of the Open City Planning Committee agenda of 9 October 2017 and a permit containing the following conditions be issued:

GEN

The use and/or development must be substantially in accordance with the documents and drawings that comprise PLN­17­603 ­ 1­3 ELIZABETH STREET HOBART TAS 7000 ­ Final Planning Documents except where modified below.

 

Reason for condition

 

To clarify the scope of the permit.

TW

The use and/or development must comply with the requirements of TasWater as detailed in the form Submission to Planning Authority Notice, Reference No. TWDA 2017/01316­HCC dated 23/08/2017 as attached to the permit.

 

Reason for condition

 

To clarify the scope of the permit.

 

THC

The use and/or development must comply with the requirements of the Tasmanian Heritage Council as detailed in the Notice of Heritage Decision, THC Application No. 5395 dated 13 September 2017, as attached to the permit.

 

Reason for condition

 

To clarify the scope of the permit.

 

PLN s1

The statue is only approved while the Mawson's Hut Replica Museum use is in operation. The statue must be removed within three months of that use ceasing to operate.

Advice:

 

The Mawson's Hut Replica Museum has planning approval until 28 February 2019 pursuant to PLN­16­1065.

 

The intent of this condition is to ensure that the statue is removed at the same time that the Mawson's Hut Replica Museum is removed, when that use ceases to operate.

 

Reason for condition

 

To ensure that the temporary structure is removed at the expiration of the permit and the site restored to its original condition.

ADVICE

The following advice is provided to you to assist in the implementation of the planning permit that has been issued subject to the conditions above. The advice is not exhaustive and you must inform yourself of any other legislation, by­laws, regulations, codes or standards that will apply to your development under which you may need to obtain an approval. Visit the Council's website for further information.

 

Prior to any commencement of work on the site or commencement of use the following additional permits/approval may be required from the Hobart City Council.

BUILDING PERMIT

Building permit in accordance with the Building Act 2016. Click here for more information.

DIAL BEFORE YOU DIG

Click here for dial before you dig information.

 

 


 

 9.3   29 Morrison Street, Hobart - Outdoor Dining - PLN-17-614

            File Ref: F17/135813

Ref:    Open CP 7.1.3, 9/10/2017

 

PART A

That pursuant to the Sullivans Cove Planning Scheme 1997, the Council refuse the application for outdoor dining at 29 Morrison Street Hobart and adjacent road reserve for the following reasons:

1.      The proposal does not meet clause 22.4.5 ‘Discretionary’ 'Building or works' in Schedule 1 – Conservation of Cultural Heritage Values of the Sullivans Cove Planning Scheme 1997 because the location, bulk and appearance of the proposal would dominate the Place of Cultural Significance and fail to complement and contribute to its character and appearance; and would therefore adversely affect the heritage values of the Place of Cultural Significance.

PART B

That the City Infrastructure Committee request an investigation into the possible removal of three car parking spaces located in front of 29 Morrison Street.

 

 

 

9.4      10 David Avenue, Sandy Bay - Partial Demolition and Front Fencing

            PLN-17-142 - File Ref: F17/135841

Ref:    Open CP 7.2.1, 9/10/2017

Application Expiry Date: 31 October 2017

Extension of Time: Not applicable

 

PART A

Pursuant to the Hobart Interim Planning Scheme 2015, the Council refuse the application for Partial Demolition and Front Fencing at 10 David Avenue SANDY BAY for the following reasons:

 

1.       The proposal does not meet the acceptable solution or the performance criterion with respect to clause E.13.8.1 A1 and P1 of the Hobart Interim Planning Scheme 2015 because the partial demolition of the existing front fence results in the loss of fabric or landscape elements that contribute to the historic cultural heritage significance of Heritage Precinct Sandy Bay 9 and the following do not apply: (i) there are environmental, social, economic or safety reasons of greater value to the community than the historic cultural heritage values of the place; (ii) there are no prudent or feasible alternatives and (iii) the replacement fence is more complementary to the heritage values of Heritage Precinct Sandy Bay 9.

 

2.       The proposal does not meet the acceptable solution or the performance criterion with respect to clause E.13.8.2 A4 and P4 of the Hobart Interim Planning Scheme 2015 because the new front fence and gates are not sympathetic in design (including height, form, scale and materials), and setback to the style, period and characteristics of Heritage Precinct Sandy Bay 9.

 

3.       The proposal does not meet the acceptable solution or the performance criterion with respect to clause 10.4.7 A1 and P1 of the Hobart Interim Planning Scheme 2015 because the new front fence and gates do not provide mutual passive surveillance between the road and the dwelling and are not compatible with the height and transparency of fences in the street.

PART B

That the Council significantly promote the risk of building front fences without appropriate Council approval and for this information to be promoted in writing to the architectural community and via suitable media platforms such as City News and social media.

 

 

 

 

9.5      43 Runnymede Street, Battery Point - Change of Use to Visitor Accommodation

            PLN-17-589 - File Ref: F17/135852

Ref:    Open CP 7.2.2, 9/10/2017

Application Expiry Date: 18 November 2017

Extension of Time: Not applicable

 

Pursuant to the Hobart Interim Planning Scheme 2015, the Council approve the application for a partial change of use to visitor accommodation at 43 Runnymede Street, Battery Point for the reasons outlined in the officer’s report attached to item 7.2.2 of the Open City Planning Committee agenda of 9 October 2017 and a permit containing the following conditions be issued:

GEN

The use and/or development must be substantially in accordance with the documents and drawings that comprise PLN­17­589 ­ 43 RUNNYMEDE STREET BATTERY POINT TAS 7004 ­ Final Planning Documents except where modified below.

 

Reason for condition

 

To clarify the scope of the permit.

ADVICE

The following advice is provided to you to assist in the implementation of the planning permit that has been issued subject to the conditions above. The advice is not exhaustive and you must inform yourself of any other legislation, by­laws, regulations, codes or standards that will apply to your development under which you may need to obtain an approval. Visit the Council's website for further information.

 

Prior to any commencement of work on the site or commencement of use the following additional permits/approval may be required from the Hobart City Council.

 

VISITOR ACCOMMODATION

Building approval is required for investment property dwellings or residential premises (which are not occupied by the owner).

 

If building work is required then both planning and building approval may be required.

 

You should consult with your insurance provider to ensure appropriate insurance coverage.

 

More information on visitor accommodation can be found here.

 

PARKING LIMITATIONS:

That the Applicant consider encouraging guests to explore other modes of transport apart from a motor vehicle whilst utilising the visitor accommodation due to the limited public parking spaces within the vicinity.

 

 

 


 

9.6      162 Macquarie Street, Hobart and Adjacent Road Reserve - Alterations and Signage

            pln-17-661 - File Ref: F17/135848

Ref:    Open CP 7.2.3, 9/10/2017

Application Expiry Date: 24 October 2017

Extension of Time: Not applicable

 

Pursuant to the Hobart Interim Planning Scheme 2015, the Council approve the application for alterations and signage at 162 Macquarie Street, Hobart and Adjacent Road Reserve for the reasons outlined in the officer’s report attached to item 7.2.3 of the Open City Planning Committee agenda of 9 October 2017 and a permit containing the following conditions be issued:

 

 

GEN

 

 

The use and/or development must be substantially in accordance with the documents and drawings that comprise PLN­17­661 ­ 162 MACQUARIE STREET HOBART TAS 7000 ­ Final Planning Documents except where modified below.

 

 

Reason for condition

 

 

To clarify the scope of the permit.

 

 

HER 5

 

 

The illuminated wall sign at fourth floor level to the Macquarie Street elevation is not approved.

 

 

Prior to the commencement of works, amended drawings must be submitted and approved, which do not show the illuminated wall sign at fourth floor level to the Macquarie Street elevation to satisfy the above requirement.

 

 

All work required by this condition must be undertaken in accordance with the amended drawings.

 

 

Advice:

 

 

Once the amended drawings have been approved, the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement).

 

 

Where building approval is also required, it is recommended that documentation for condition endorsement be submitted well before submitting documentation for building approval. Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.

 

 

Reason for condition

 

To ensure the size, design and siting of signs complements and does not impact on the cultural heritage significance of the City Centre Heritage Precinct as listed in the Historic Heritage code.

 

 

ADVICE

 

 

The following advice is provided to you to assist in the implementation of the planning permit that has been issued subject to the conditions above. The advice is not exhaustive and you must inform yourself of any other legislation, by­laws, regulations, codes or standards that will apply to your development under which you may need to obtain an approval. Visit the Council's website for further information.

 

 

Prior to any commencement of work on the site or commencement of use the following additional permits/approval may be required from the Hobart City Council.

 

 

CONDITION ENDORSEMENT

 

 

If a condition endorsement is required by a planning condition above, you will need to submit the relevant documentation to satisfy the condition via the Condition Endorsement Submission on Council's online services e­planning

 

 

Where building approval is also required, it is recommended that documentation for condition endorsement be submitted well before submitting documentation for building approval. Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.

 

 

Once approved, the Council will respond to you via email that the condition has been endorsed (satisfied). Detailed instructions can be found here.

 

 

BUILDING PERMIT

 

 

Building permit in accordance with the Building Act 2016. Click here for more information.

 

 

OCCUPATION OF THE PUBLIC HIGHWAY

 

 

Permit for the occupation of the public highway for construction or special event (e.g. placement of skip bin, crane, scissor lift etc). Click here for more information.

 

 

Occupational license for structures in the Hobart City Council highway reservation, in accordance with conditions to be established by the Council. Click here for more information.

 

Road closure permits for construction or special event. Click here for more information.

 

 

Permit to Open Up and Temporarily Occupy a Highway (for work in the road reserve). Click here for more information.

 

 

GENERAL EXEMPTION (TEMPORARY) PARKING PERMITS

 

 

General Exemption permits for construction vehicles i.e. residential or meter parking/loading zones. Click here for more information.

 

 

WORK WITHIN THE HIGHWAY RESERVATION

 

 

Please note development must be in accordance with the Hobart City Council’s Highways By law. Click here for more information.

 

 

WASTE DISPOSAL

 

 

It is recommended that the developer liaise with the Council’s Cleansing and Solid Waste Unit regarding reducing, reusing and recycling materials associated with demolition on the site to minimise solid waste being directed to landfill.

 

 

Further information regarding waste disposal can also be found on the Council’s website.

 

 


 

9.7      15-17 Liverpool Street, 61 Brooker Avenue, 71 Brooker Avenue, CT 160498/2, Brooker Avenue Road Reservation, Bathurst Street Road Reservation, Hobart - Shared Use Bicycle and Pedestrian Bridge

            pam-17-183 - File Ref: F17/137714

Ref:    Open CP 12, 9/10/2017

Application Expiry Date: Not applicable

Extension of Time: Not applicable

 

That pursuant to the Hobart Interim Planning Scheme 2015, the Council approve the

application for a shared use bicycle and pedestrian bridge at 15-17 Liverpool Street, 61 Brooker Avenue, 71 Brooker Avenue, CT 160498/2, Brooker Avenue Road Reservation, Bathurst Street Road Reservation, Hobart for the reasons outlined in the officer’s report attached to the supplementary item 6.1.4 of the Open City Planning Committee agenda of 4 July 2016 and a permit containing the following conditions be issued:

 

GENERAL

 

GEN 

 

The use and/or development must be substantially in accordance with the documents and drawings that comprise PLN-16-00386-01 - 15-17 Liverpool Street - 61 Brooker Avenue - 71 Brooker Avenue - CT 160498-2 - Brooker Avenue Road Reservation - Amended (s56) Planning Documents except where modified below.

 

Reason for condition

 

To clarify the scope of the permit.

 

Note: Condition 1 amended pursuant to section 56 of the Land Use Planning and Approvals Act 1993 and approved by the Council on 23 October 2017.

 

TASWATER

 

TW 

 

The use and/or development must comply with the requirements of TasWater

as detailed in the form Submission to Planning Authority Notice, Reference

No. TWDA 2016/00479-HCC dated 26/04/2016 as attached to the permit.

 

Reason for condition

 

To clarify the scope of the permit.

 

HERITAGE

 

HERs1 

 

The recommendations detailed in Section 9 of the Kostoglou/Watton

Statement of Historical Archaeological Significance (submitted as part of the application documentation) must be implemented throughout the construction works.  

 

A report on the findings of those archaeological works must be submitted to the planning authority within six months of the completion of works.

 

Reason for condition 

 

To protect the heritage values of the area.

 

HERs2 

 

The recommendations of the Arborist Impact Assessment (Romanski

27/11/15 as submitted with the application) for trees 1 and 2 as identified in that document must be implemented throughout the construction works.

 

Reason for condition

 

To protect the heritage values of the area.

 

ENVIRONMENTAL

 

ENV1 

 

Sediment and erosion control measures sufficient to prevent sediment from leaving the site must be installed prior to any disturbance of the site.

Sediment controls must be maintained until all areas of disturbance have been stabilized or revegetated.

 

Advice:

  

For further guidance in preparing Soil and Water Management Plans in accordance with Fact Sheet 3 Derwent Estuary Program go to www.hobartcity.com.au development engineering standards and guidelines.

 

Reason for condition

 

To avoid the sedimentation of roads, drains, natural watercourses, Council land that could be caused by erosion and runoff from the development, and to comply with relevant State Legislation.

 

ENV2

 

The landslide risk mitigation measures recommended in the letter from

Terroir Pty Ltd dated 16 May 2016 must be implemented during the works.

 

Reason for condition

 

To reduce the risk to life and property, and the cost to the community,

caused by landslides.

 

ENGINEERING

 

ENG1 

 

The cost of repair of any damage to the Council’s infrastructure resulting from the implementation of this permit, must be met by the owners within 30 days of the completion of the development. 

 

A photographic record of the Council’s infrastructure adjacent to the subject site must be provided to the Council prior to any commencement of works.

 

A photographic record of the Council’s infrastructure (e.g. existing property service connection points, roads, buildings, stormwater, footpaths, driveway crossovers and nature strip, including if any, pre-existing damage) will be relied upon to establish the extent of  damage caused to the Council’s infrastructure during construction.

 

In the event that the owner/developer fails to provide to the Council a photographic record of the Council’s infrastructure, then any damage to the Council’s infrastructure found on completion of works will be deemed to be the responsibility of the owner.

 

Reason for condition

 

To ensure that any of the Council’s infrastructure and/or site-related service connections affected by the proposal will be altered and/or reinstated at the owner’s full cost.

 

ENGsw

 

The cost of any alterations to the Council’s or third-party infrastructure incurred as a result of the proposed development works must be met by the owner.

 

Reason for condition

 

To ensure that any of the Council’s infrastructure and/or site-related service connections affected by the proposal will be altered and/or reinstated at the owner’s full cost.

 

ENGsw1

 

The Council’s stormwater infrastructure within five metres of the proposed works must be protected from damage during the construction of the development.

 

Reason for condition

 

To ensure that any of the Council’s infrastructure and/or site-related service connections affected by the proposal will be altered and/or reinstated at the owner’s full cost.

 

 

ENGsw3

 

The proposed works (including footings and overhangs) must be designed to ensure the long term protection of and access to the Council’s stormwater infrastructure.

 

A detailed design certified by a suitably qualified engineer must be submitted and approved prior to issue of any consent under the Building Act 2000. The detailed design must:

 

•        Demonstrate that no additional loads are imposed on the stormwater main;

•        Demonstrate that the structure is entirely independent of the main and its trenching;

•        Demonstrate how adequate access to the main is maintained for both maintenance and future capacity upgrade works;

•        Include cross-sections which clearly state minimum separation; and

•        Include certification by a suitably qualified engineer that the works do not impose any loads on the stormwater main and the structure is entirely independent of the main and its trenching.

 

Prior to issue of any Certificate of Completion a suitably qualified engineer must confirm the installation of the works within five metres of Council’s stormwater main is in accordance with the approved drawings and complies with this condition. Should any remediation works be required, these must be carried out at the developer’s cost.

 

All work required by this condition must be undertaken in accordance with the approved design.

 

Advice: 

 

Once the detailed design drawings has been approved the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement).

 

In this case, Council will accept a minimum separation of 3m from footings on the western side of Park Street Rivulet, with any works within this zone to be demountable.

 

Reason for condition

 

To ensure the protection of the Council’s hydraulic infrastructure.

 

ENGsw4 

 

Council stormwater infrastructure must be carefully and accurately located onsite, and marked on the ground. 

 

Prior to construction of the footings, the stormwater pipe and clearance must be inspected and confirmed by the Council's Project and Development

Inspector to ensure the minimum separation is achieved.

 

Reason for condition

 

To ensure the protection of the Council’s hydraulic infrastructure.

 

ENGsw5 

 

Construction of the works must not adversely impact Park Street Rivulet.

 

A Construction Management Infrastructure Protection Report must be submitted and approved prior to commencement of works. The report must:

 

•        Be prepared by a suitably qualified and experienced engineer;

•        Detail the proposed construction methodology and identify all potential risks to the Rivulet during construction including but not limited to construction loading, excavation works, footing construction, vibrations, undermining, flood, and environmental harm;

•        Provide treatment measures to eliminate or otherwise mitigate to as low as reasonably practicable all identified risks; and 

•        Include a monitoring regime.

 

All work required by this condition must be undertaken in accordance with the approved report.

 

Reason for condition

 

To ensure the protection of the Council’s hydraulic infrastructure.

 

ENGsw7/8

 

The development must be drained to Council infrastructure. Any new public stormwater infrastructure required, including connections, must be constructed prior to issue of a Certificate of Completion.

 

Detailed design drawings showing both existing and proposed services must be submitted and approved, prior to issue of any consent under the Building

Act 2000.

 

The detailed design drawings must include:

 

•        The title boundaries, with each Lot serviced separately by Council infrastructure and all private plumbing contained within each Lot;

•        The location, size and design of the connection(s);

•        Long-sections of the proposed infrastructure clearly showing any nearby services, cover, size, material, access points (including safe working space); gradients;

•        The public piped stormwater infrastructure must be sized to accommodate at least the 5% AEP flows from the catchment;

•        Clearly distinguish between public and private infrastructure, and the ownership of any private plumbing; and

•        Be checked and certified by a qualified and experienced engineer.

 

All work required by this condition must be undertaken in accordance with the approved detailed design drawings.

 

Advice:  

 

Once the detailed design drawings have been approved the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement). Please note that once the condition endorsement has been issued you will need to contact Council’s City Infrastructure Division to initiate an application for service connection.

 

The construction of public infrastructure will require a Permit to Construct

Public Infrastructure.

 

Reason for condition

 

To ensure the site is drained adequately.

 

ENGtr1 

 

The proposed bridge and associated infrastructure within the highway reservation must not undermine the stability and integrity of the highway reservation and its infrastructure.

 

Detailed design drawings and structural certificates of the bridge and associated infrastructure within the Brooker Avenue and Bathurst Street highway reservation must be submitted and approved, prior to the commencement of work and must:

 

•        Be prepared and certified by a suitable qualified person and experienced engineer;

•        Demonstrate that the bridge will not undermine the stability of the highway reservation;

•        Take into account and reference accordingly any geotechnical findings;

•        Show the location of existing and proposed services and infrastructure;

•        Include a lighting design in accordance with AS 1158 standards;

•        Show any changes to traffic lanes and parking in detail;

•        Show the construction of any new footpath in accordance with the (IPWEA) LGAT –Tasmanian Standard Drawings;

•        Include design and certification of any pedestrian and vehicle barriers in accordance with the Department of State Growth Specifications Guidelines and procedures, Australian/New Zealand Standard AS / NZS 1170.1 and/or the (IPWEA) LGAT – Tasmanian Standard Drawings;

•        Be in accordance with the Department of State Growth Specifications and all other relevant Standards, Guidelines and procedures; and

•        Include a safe design of structures assessment in accordance with the Safe Design of Structures Code of Practice (as adopted under section 274 of the Work Health and Safety Act 2012) and supply to the Council any documentation from the norm for the ongoing maintenance and replacement of any structures within the Highway Reservation.

 

All work required by this condition must be undertaken in accordance with the approved design drawing and structural certificates.

 

Once the works have been completed, the as constructed drawings must be submitted to the Council.

 

Advice: 

 

Once the design drawing has been approved the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement).

 

Reason for condition

 

To ensure that the stability and integrity of the Council’s highway reservation is not compromised by the development.

 

ENGtr2 

A construction traffic and parking management plan must be implemented prior to the commencement of work on the site (including demolition).

 

The construction traffic (including cars, public transport vehicles, service vehicles, pedestrians and cyclists) and parking management plan must be submitted and approved, prior to commencement work. The construction traffic and parking management plan must:

 

(a)     Be prepared by a suitably qualified person, by the Council;

(b)     Develop a communications plan to advise the wider community of the traffic and parking impacts during construction;

(c)     Include a start date and finish dates of various stages of works;

(d)     Include times that trucks and other traffic associated with the works will be allowed to operate;

(e)     Nominate a superintendant or like to advise the Council of the progress of works in relation to the traffic and parking management with regular meetings during the works.

 

All work required by this condition must be undertaken in accordance with the approved construction traffic and parking management plan.

 

Advice: 

 

Once the construction traffic and parking management plan has been approved Council will issue a condition endorsement (see general advice on how to obtain condition endorsement).

 

Reason for condition

 

To ensure the safety of vehicles entering and leaving the development and the safety and access around the development site for the general public and adjacent businesses.

 


ADVICE: 

 

The following advice is provided to you to assist in the implementation of the planning permit that has been issued subject to the conditions above. The advice is not exhaustive and you must inform yourself of any other legislation, by-laws, regulations, codes or standards that will apply to your development under which you may need to obtain an approval.  Visit www.hobartcity.com.au for further information.  

 

Prior to any commencement of work on the site or commencement of use the following additional permits/approval may be required from the Hobart City

Council.

 

If a condition endorsement is required by a planning condition above, please forward documentation required to satisfy the condition to rfiinformation@hobartcity.com.au, clearly identifying the planning permit number, address and the condition to which the documentation relates.

 

Once approved, the Council will respond to you via email that the condition/s has been endorsed (satisfied). Detailed instructions can be found at

www.hobartcity.com.au/Development/Planning/How_to_obtain_a_condition_endorsement.

 

•        Building permit in accordance with the Building Act 2000; www.hobartcity.com.au/Development/Building

 

•        Plumbing permit under the Tasmanian Plumbing Regulations 2014; www.hobartcity.com.au/Development/Plumbing..

 

•        Permit for the occupation of the public highway for construction e.g. placement of crane, scissor lift etc) http://www.hobartcity.com.au/Transport/Permits/Construction_Activities_Special_Events_in_the_Road_Reservation

 

•        Permit to Open Up and Temporarily Occupy a Highway (for work in the road reserve) http://www.hobartcity.com.au/Transport/Lighting_Roads_Footpaths_and_Street_Cleaning/Roads_and_Footpaths

 

•        Temporary parking permits for construction vehicles i.e. residential or meter parking/loading zones. http://www.hobartcity.com.au/Transport/Permits/Parking_Permits.

 

•        Any damage to council’s infrastructure must be reported to Council’s compliance area. Please note the developer is liable for any damage to property or person due to unsafe and/or damaged infrastructure within or supporting the highway reservation and the developer should review their insurance.

 

•        Please note development must be in accordance with the Council’s Highways By –law http://www.hobartcity.com.au/Council/Legislation.

•        Fees and charges http://www.hobartcity.com.au/Council/Fees_and_Charges

 

•        Dial before you dig www.dialbeforeyoudig.com.au.

 

•        If you do not have access to the Council’s electronic webpage, please phone the Council (City Planning) on 6238 2715 for assistance.

 

•        The date that this planning permit took effect was 11 July 2017 and you have two years from this date to substantially commence the development/use, before the permit lapses, pursuant to section 53(5) of the Land Use Planning and Approvals Act 1993. The Council may grant extensions to this period if requested in writing at any time before the end of the period of six months from the day on which the permit has lapsed.

Note: Advice added pursuant to section 56 of the Land Use Planning and Approvals Act 1993 and approved by Council on 23 October 2017. 

 

 

 

 

 

 

9.8      260 Sandy Bay Road, Sandy Bay and Adjacent Road Reserve - Signage and Alterations to Car Park Access and Layout

            PLN-17-637 - File Ref: F17/141521

Ref:    Open Special CP 2.1.1, 23/10/2017

Application Expiry Date: 18 October 2017

Extension of Time: Not applicable

 

A recommendation will be submitted to the meeting.

 

 

 


 

10.      Building Height Standards Review - Hobart Interim Planning Scheme 2015 - Sullivans Cove Planning Scheme 1997 - Project Brief

            File Ref: F17/126151; 17/167

Ref:    Open CP 8.1, 9/10/2017

 

That the Council endorse the project brief provided marked as Attachment A to item 8.1 of the Open City Planning Committee agenda of 9 October 2017 and invite Leigh Woolley – Architect and Urban Design Consultant to submit a quotation to undertake the project.

 

 

   


 

Agenda (Open Portion)

Council Meeting

Page 31

 

23/10/2017

 

 

Community, Culture and Events Committee

 

11.      2017-18 Fees and Charges - Salamanca Market

            File Ref: F17/134504; 17/41

Ref:    Open CCE 6.1, 18/10/2017

 

A recommendation will be provided under separate cover.

 

 

 

12.      Five Year Review of Salamanca Market Stallholder Licence Agreement

            File Ref: F17/111631; 15/153-53

Ref:    Open CCE 6.2, 18/10/2017

 

A recommendation will be provided under separate cover.

 

 

 

13.      Urban Art Walls: Iteration 4 - Bidencopes Lane

            File Ref: F17/111421; S30-001-13/08-002-001

Ref:    Open CCE 6.3, 18/10/2017

 

A recommendation will be provided under separate cover.

 

 

 

14.      Australia Day

            File Ref: F17/137949; 2017-0063

Ref:    Open CCE 6.4, 18/10/2017

 

A recommendation will be provided under separate cover.

 

 

 

15.      Late Night Toilet Provision - Salamanca/Waterfront Precinct

            File Ref: F17/136150;  RFS14-0100

Ref:    Open CCE 6.5, 18/10/2017

 

A recommendation will be provided under separate cover.

 

 

 

16.      Community Development Grants Program - Recommendations - Round Two 2017 Round

            File Ref: F17/138582; 17/213

Ref:    Open CCE 6.6, 18/10/2017

 

A recommendation will be provided under separate cover.

 

 

 

17.      Musica Viva Tasmania - Extension of Partnership Arrangement

            File Ref: F17/139256; 17/215-001

Ref:    Open CCE 6.8, 18/10/2017

 

A recommendation will be provided under separate cover.

 

 

 

18.      2017 The Taste of Tasmania - New Year's Eve, Ticket Pricing and Retail Recommendations

            File Ref: F17/140288; S13-046-01/39

Ref:    Open Special CCE 6, 23/10/2017

 

A recommendation will be submitted to the meeting.

 

 

 


 

Agenda (Open Portion)

Council Meeting

Page 33

 

23/10/2017

 

 

Economic Development & Communications Committee

 

19.      Community Development Grants Program - Recommendations Marketing Grants 2017

            File Ref: F17/138216; 16/194

Ref:    Open Special EDC 4.1, 23/10/2017

 

A recommendation will be submitted to the meeting.

 

 

 


 

Agenda (Open Portion)

Council Meeting

Page 34

 

23/10/2017

 

 

Finance Committee

 

20.      2016-17 Financial Statements

            File Ref: F17/134786

Ref:    Open FC 6.2, 17/10/2017

 

That the Council formally adopt the financial statements for the year ended 30 June 2017 marked as Attachment A to item 6.2 of the Open Finance Committee agenda of 17 October 2017.

 

 

 


 

Agenda (Open Portion)

Council Meeting

Page 35

 

23/10/2017

 

 

Governance Committee

 

21.      City of Hobart - Draft Customer Service Charter

            File Ref: F17/125280

Ref:    Open GC 6.1, 10/10/2017

 

That:   1.    The text for a revised draft customer service charter, shown as Attachment A to item 6.1 of the Open Governance Committee agenda of 10 October 2017t, be approved for release for public comment for a four week period.

2.    Following the comment period, a further report be provided presenting the results of consultation and a final draft charter for endorsement.

3.    The Charter be further reviewed to coincide with the implementation of the Council’s customer request management system in the first half of next year, so as to capture the increased functionality available from that system to enhance customer relationship management.

 

 

 

 

 

 

 

22.    Proposed 2018 Council and Committee Meeting Schedule and Temporary City Planning Committee Delegation

            File Ref: F17/125692

Ref:    Open GC 6.2, 10/10/2017

 

That:   1.    The proposed 2018 Council and Council Committee meeting schedule, marked as Attachment A to item 6.2 of the Open Governance Committee agenda of 10 October 2017, be adopted.

2.    In the event that any urgent matters arise which cannot be accommodated within the 2018 meeting schedule, special meetings be convened as required.

3.    The City Planning Committee be provided with the following delegation in order to facilitate the processing of planning permit applications during the Christmas period:

(i)      To determine all planning permit applications which would otherwise be determined by the Council, between 12 December 2017 and the first ordinary scheduled Council meeting in January 2018, in circumstances where it would not otherwise be possible to determine the application within the statutory time period required under Sections 57(6), 57(6A), 58(2) or 58(2A) of the Land Use Planning and Approvals Act 1993, and an extension of time cannot be obtained, unless an Alderman has requested the convening of a special meeting or meetings to determine the application.

 

 


 

Agenda (Open Portion)

Council Meeting

Page 37

 

23/10/2017

 

 

Parks and Recreation Committee

 

23.      Naming - Pedestrian Bridge Across Tasman Highway from the Cenotaph to the Domain

            File Ref: F17/114212; F17/8678

Ref:    Open PR 6.1, 19/10/2017

 

A recommendation will be provided under separate cover.

 

 

 

24.      Request for Easement - Queens Domain

            File Ref: F17/96881; 72-25-17

Ref:    Open PR 6.2, 19/10/2017

 

A recommendation will be provided under separate cover.

 

 

 

25.      Request for Lease - Sandown Park - Optus

            File Ref: F17/138083

Ref:    Open PR 6.3, 19/10/2017

 

A recommendation will be provided under separate cover.

 

 

 

26.      Response to Petition - Girrabong Park (Corner of Firth and Girrabong Roads), Lenah Valley

            File Ref: F17/137747

Ref:    Open PR 6.4, 19/10/2017

 

A recommendation will be provided under separate cover.

 

 

   


Item No. 27

Agenda (Open Portion)

Council Meeting

Page 38

 

23/10/2017

 

 

Special Report – General Manager

 

27.      Public Meeting in Response to Building Height Petition

            File Ref: F17/141445; 15/10-001-001

Report of the General Manager of 18 October 2017 and attachments.

Delegation:                 Council


Item No. 27

Agenda (Open Portion)

Council Meeting

Page 39

 

23/10/2017

 

 

 

 

 

 

Memorandum: Council

 

Public Meeting in Response to Building Height Petition

 

The Council convened a public meeting at the Hotel Grand Chancellor on Monday 16 October 2017 at 6.00pm as the result of being petitioned in accordance with s 59 2 of the Local Government Act 1993 (the Act).

 

The petition was lodged by Hobart Not Highrise and was initially presented to the Council at its meeting held on 7 August 2017.

 

The petition raised concerns with oversized buildings breaching height limits and sought actions from the Council including the conduct of a public meeting.  

 

The Council formally considered the petition at its meeting of 18 September 2017 whereat it noted that the number of signatories met the criteria required under S 59 2 of the Act to require the Council to hold a public meeting, and therefore resolved to do so.

 

Notice of the meeting was published in The Mercury newspaper on Wednesday 20 and Saturday 30 September and written submissions were received until midnight on Wednesday 11 October 2017.  Seventeen written submissions were received and a summary of those submissions was available at the public meeting.

 

Section 60A(5) of the Act states that the minutes of the next ordinary meeting of the council following the public meeting are to record:

a)   A summary of any submission received under this section; and

b)   Any decision made at a public meeting held under this section.

 

Attachment A to this memorandum are minutes from the public meeting capturing the information required under section 60A(5).

 


 

 

REcommendation

That the information be received and noted.

 

 

As signatory to this report, I certify that, pursuant to Section 55(1) of the Local Government Act 1993, I hold no interest, as referred to in Section 49 of the Local Government Act 1993, in matters contained in this report.

 

N.D Heath

General Manager

 

 

Date:                            18 October 2017

File Reference:          F17/141445; 15/10-001-001

 

 

Attachment a:             Minutes from the Public Meeting held on 16 October 2017   


Item No. 27

Agenda (Open Portion)

Council Meeting - 23/10/2017

Page 41

ATTACHMENT a

 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator

     


 

Agenda (Open Portion)

Council Meeting

Page 74

 

23/10/2017

 

 

28.     Closed Portion Of The Meeting

 

The following items were discussed:-

 

Item No. 1          Minutes of the last meeting of the Closed Portion of the Council Meeting

Item No. 2          Communication from the Chairman

Item No. 3          Leave of Absence

Item No. 4          Consideration of supplementary items to the agenda

Item No. 5          Indications of pecuniary and conflicts of interest 

Item No. 6.1       186 Bathurst Street, Hobart
Planning Appeal - Mediation - PLN-16-701

LG(MP)R 15(4)(a)

Item No. 7          Application for Remission of Rates - 110 Burnett Street, North Hobart

LG(MP)R 15(2)(j)

Item No. 8          Battery Point Slipyards Master Plan Options Paper

LG(MP)R 15(2)(c)(i)