City
of hobart
AGENDA
City Planning Committee Meeting
Open Portion
Monday, 15 June 2020
at 5:00 pm
SUPPLEMENTARY ITEMS
ORDER OF BUSINESS
Committee Acting as Planning Authority
Applications under the Hobart Interim Planning Scheme 2015
12 283-287 Liverpool Street, Hobart - Demolition and New Building for 25 Multiple Dwellings
13 29 Aberdeen Street, Glebe, 2 Davies Avenue, Hobart - Change of Use to Visitor Accommodation
|
Supplementary Agenda (Open Portion) City Planning Committee Meeting |
Page 2 |
|
15/6/2020 |
|
This meeting of the City Planning Committee is held in accordance with a Notice issued by the Premier on 3 April 2020 under section 18 of the COVID-19 Disease Emergency (Miscellaneous Provisions) Act 2020.
The General Manager reports:
“That in accordance with the provisions of Part 2 Regulation 8(6) of the Local Government (Meeting Procedures) Regulations 2015, these supplementary matters are submitted for the consideration of the Committee.
Pursuant to Regulation 8(6), I report that:
(a) information in relation to the matter was provided subsequent to the distribution of the agenda;
(b) the matter is regarded as urgent; and
(c) advice is provided pursuant to Section 65 of the Act.”
|
Supplementary Agenda (Open Portion) City Planning Committee Meeting |
Page 3 |
|
15/6/2020 |
|
In accordance with the provisions of Part 2 Regulation 25 of the Local Government (Meeting Procedures) Regulations 2015, the intention of the Committee to act as a planning authority pursuant to the Land Use Planning and Approvals Act 1993 is to be noted.
In accordance with Regulation 25, the Committee will act as a planning authority in respect to those matters appearing under this heading on the agenda, inclusive of any supplementary items.
The Committee is reminded that in order to comply with Regulation 25(2), the General Manager is to ensure that the reasons for a decision by a Council or Council Committee acting as a planning authority are recorded in the minutes.
Item No. 12 |
Supplementary Agenda (Open Portion) City Planning Committee Meeting |
Page 4 |
|
15/6/2020 |
|
12 283-287 Liverpool Street, Hobart - Demolition and New Building for 25 Multiple Dwellings
Address: 283-287 Liverpool Street, Hobart
Proposal: Demolition and New Building for 25 Multiple Dwellings
Expiry Date: 23 June 2020
Extension of Time: Not applicable
Author: Helen Ayers
That pursuant to the Hobart Interim Planning Scheme 2015, the Council approve the application for demolition and new building for 25 multiple dwellings at 283287 Liverpool Street, Hobart for the reasons outlined in the officer’s report and a permit containing the following conditions be issued:
GEN
The use and/or development must be substantially in accordance with the documents and drawings that comprise PLN20191 283287 LIVERPOOL STREET HOBART TAS 7000 Final Planning Documents, except where modified below.
Reason for condition
To clarify the scope of the permit.
TW
The use and/or development must comply with the requirements of TasWater as detailed in the form Submission to Planning Authority Notice, Reference No. TWDA 2020/00418HCC dated 16/04/2020 as attached to the permit.
Reason for condition
To clarify the scope of the permit.
PLN 15
A demolition waste management plan must be implemented throughout demolition.
A demolition waste management plan must be submitted and approved, prior to commencement of work on the site. The demolition waste management plan must include provisions for the handling, transport and disposal of demolition material, including any contaminated waste and recycling opportunities, to satisfy the above requirement.
All work required by this condition must be undertaken in accordance with the approved demolition waste management plan.
Advice:
Once the demolition waste management plan has been approved, the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement).
Where building approval is also required, it is recommended that documentation for condition endorsement be submitted well before submitting documentation for building approval. Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.
It is recommended that the developer liaise with the Council’s Cleansing and Solid Waste Unit regarding reducing, reusing and recycling materials associated with demolition on the site to minimise solid waste being directed to landfill. Further information can also be found on the Council’s website.
Reason for condition
To ensure that solid waste management from the site meets the Council’s requirements and standards.
PLN 1
All screening as shown on the approved plans must be installed with a uniform transparency between 50% and 25% prior to first occupation. The screening must be maintained.
Reason for condition
To provide reasonable opportunity for privacy for dwellings.
PLN 4
Planter boxes as shown on the approved plans must be retained in the final building design.
Landscaping which is visible above the top of the planter box walls must be installed in the planter boxes prior to first occupation of the dwellings, and maintained for the life of the use of the building.
Prior to the completion of the building, an automated watering system must be installed for all planter boxes and maintained for the life of the use of the building.
All work required by this condition must be undertaken in accordance with the approved revised plans.
Reason for condition
To ensure that the scale of the building is compatible with nearby buildings.
PLN 17
Illumination must be provided to the entry ramp for the carpark such that the entry ramp is not dark when people and vehicles enter it from the street or from the carpark. This illumination should be designed and baffled such that it does not cause a nuisance outside the property, operating in accordance with Australian Standard AS4282 Control of the obtrusive effects of outdoor lighting.
Reason for condition
To ensure that the potential entrapment space created by the carpark ramp and doors is sufficiently illuminated to minimise the risk or antisocial behaviour in the location.
PLN 5
A landscape plan must be prepared for the soft and hard landscaping of the site, by a suitably qualified landscape architect.
Prior to the issue of any approval under the Building Act 2016 (excluding for demolition, excavation and works up to the ground floor slab), a revised landscape plan must be submitted and approved to the satisfaction of the Director City Planning in accordance with the above requirement.
All landscaping features (including any proposed plants and hard landscaping) must be installed in accordance with the approved Landscaping Plan to the satisfaction of the Council's Director City Planning prior to commencement of use.
The landscaping must be maintained, and replacement plants and hard landscaping must be planted in accordance with the approved Landscaping Plan if any is lost.
Confirmation by the person who prepared the landscaping plan that the landscaping has been completed in accordance with the approved landscaping plan must be submitted to the Council to the satisfaction of the
Director City Planning, prior to commencement of use. Once this has been received, and all plants and hard landscaping shown on the approved Landscaping Plan have been planted in accordance with the approved plan to the satisfaction of the Council's Director City Planning, the Council will issue a statement confirming satisfactory planting of all trees and landscaping.
Advice:
Any increase to the area of the 'deep planting zone' at the rear of the property that can be achieved through alterations to the footprint of the ground floor, without compromising the building function and structure, is encouraged to increase the viability of the space for larger plantings.
Protection of the root area of vegetation on adjacent properties is encouraged wherever possible.
Additional landscaping in front of the building in Liverpool Street is encouraged where it does not compromise vehicle and pedestrian safety.
Reason for condition
To preserve the amenity of the space and to ensure that the scale of the building is compatible with nearby buildings, and that the plantings proposed are appropriate to assist with this.
PLN s1
The palette of exterior colours and materials must be provided.
The palette of exterior colours, materials and finishes must reflect the palette of colours, materials and finishes within the local streetscape.
Prior to the issue of any approval under the Building Act 2016 (excluding for demolition, excavation and works up to the ground floor slab), revised plans, and montages and samples where appropriate, must be submitted and approved to the satisfaction of the Director City Planning showing exterior colours and materials in accordance with the above requirement.
All work required by this condition must be undertaken in accordance with the approved revised plans, montages and samples.
Advice:
In keeping with the submitted heritage assessment, it is considered that successful integration of the proposal into the Liverpool Street Streetscape would benefit from a more detailed consideration of the choice of materials, textures and colours together with the manner in which they are integrated and articulated throughout the fenestration.
Consideration should be given to using colours, materials and textures that further ‘soften’ the building’s appearance in order to better reinforce the transition and integration of the development into the surrounding area and not unreasonably detract from the adjacent heritage buildings. A diversity of colours and textures is encouraged and stark white and black colours are to be avoided in favour of softer more muted tones.
Consideration be given to the detailed design of the fence enclosing the courtyard of Unit 0.01 so that it is more in keeping with the residential nature of the development.
Reason for condition
To provide greater integration and compatibility of the building design with the streetscape, townscape and heritage values of the surrounding area.
PLN s4
Prior to the commencement of works (other than demolition), plans demonstrating the removal of the potential entrapment spaces at either side of the Liverpool Street frontage must be submitted to and approved by Council's Director City Planning.
Prior to the issue of any approval under the Building Act 2016, revised plans must be submitted and approved showing:
1. Either a screen wall or fence on the north eastern corner of the building which provides an anchor point for the existing gate at the side of 281 Liverpool Street, to prevent unauthorised access between the two buildings. 2. Relocation of the Fire Door and Stair in the fire escape to the south western side of the building. The door should be moved as close to the street front boundary as is possible, with the stair relocated to inside the Fire Escape Corridor.
All work required by this condition must be undertaken in accordance with the approved revised plans.
Reason for condition
To remove potential entrapment spaces from around the building to improve the safety of the site.
ENG 12
A construction waste management plan must be implemented throughout construction.
A construction waste management plan must be submitted and approved, prior to commencement of work on the site. The construction waste management plan must include:
· Provisions for commercial waste services for the handling, storage, transport and disposal of postconstruction solid waste and recycle bins from the development; and · Provisions for the handling, transport and disposal of demolition material, including any contaminated waste and recycling opportunities, to satisfy the above requirement.
All work required by this condition must be undertaken in accordance with the approved construction waste management plan.
Advice:
Once the construction waste management plan has been approved, the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement).
Where building approval is also required, it is recommended that documentation for condition endorsement be submitted well before submitting documentation for building approval. Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.
It is recommended that the developer liaise with the Council’s Cleansing and Solid Waste Unit regarding reducing, reusing and recycling materials associated with demolition on the site to minimise solid waste being directed to landfill. Further information can also be found on the Council’s website.
Reason for condition
To ensure that solid waste management from the site meets the Council’s requirements and standards.
ENG sw1
All stormwater from the proposed development (including but not limited to: roofed areas, ag drains, retaining wall ag drains and impervious surfaces such as driveways and paved areas) must be drained to the Council’s stormwater infrastructure prior to first occupation or commencement of use (whichever occurs first).
Advice:
Under section 23 of the Urban Drainage Act 2013 it is an offence for a property owner to direct stormwater onto a neighbouring property.
Reason for condition
To ensure that stormwater from the site will be discharged to a suitable Council approved outlet.
ENG sw4
The new stormwater connection must be constructed and existing abandoned connections sealed by the Council at the owner’s expense, prior to the first occupation.
Detailed engineering drawings must be submitted and approved, prior to the issuing of any approval under the Building Act 2016 or commencement of works (which ever occurs first). The detailed engineering drawings must include:
1. The location of the proposed connections and all existing connections; 2. The size and design of the connection such that it is appropriate to safely service the development; 3. Longsections of the proposed connection clearly showing clearances from any nearby services, cover, size, material and delineation of public and private infrastructure. Connections must be freeflowing gravity.
All work required by this condition must be undertaken in accordance with the approved detailed engineering drawings.
Advice:
The applicant is advised to submit detailed design drawings via a Council City Amenity Division application for a new stormwater connection. If detailed design to satisfy this condition is submitted via the planning condition endorsement process there may be fees associated with the assessment, and once approved the applicant will still need to submit an application for a new stormwater connection with Council City Amenity Division.
Where building / plumbing approval is also required, it is recommended that documentation to satisfy this condition is submitted well before submitting documentation for building/plumbing approval. Failure to address planning condition requirements prior to submitting for building/plumbing approval may result in unexpected delays.
Reason for condition
To ensure the site is drained adequately.
ENG sw7
Stormwater pre treatment for stormwater discharges from the development must be installed prior to issue of a Certificate of Completion.
A stormwater management report and design must be submitted and approved, prior to the issuing of any approval under the Building Act 2016 or commencement of works (which ever occurs first). The stormwater management report and design must:
1. be prepared by a suitably qualified engineer; 2. include detailed design of the proposed treatment train, including final estimations of contaminant removal; and 3. include a maintenance plan
All work required by this condition must be undertaken and maintained in accordance with the approved stormwater management report and design.
Advice:
Once the stormwater management report and design has been approved Council will issue a condition endorsement (see general advice on how to obtain condition endorsement).
Where building approval is also required, it is recommended that documentation for condition endorsement be submitted well before submitting documentation for building approval. Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.
Reason for condition
To avoid the possible pollution of drainage systems and natural watercourses, and to comply with relevant State legislation.
ENG tr2
A construction traffic and parking management plan must be implemented prior to the commencement of work on the site (including demolition).
The construction traffic (including cars, public transport vehicles, service vehicles, pedestrians and cyclists) and parking management plan must be submitted and approved, prior to commencement work (including demolition). The construction traffic and parking management plan must:
1. Be prepared by a suitably qualified person. 2. Develop a communications plan to advise the wider community of the traffic and parking impacts during construction. 3. Include a start date and finish dates of various stages of works. 4. Include times that trucks and other traffic associated with the works will be allowed to operate. 5. Nominate a superintendant, or the like, to advise the Council of the progress of works in relation to the traffic and parking management with regular meetings during the works.
All work required by this condition must be undertaken in accordance with the approved construction traffic and parking management plan.
Advice:
Once the construction traffic and parking management plan has been approved, the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement).
Where building approval is also required, it is recommended that documentation for condition endorsement be submitted well before submitting documentation for building approval. Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.
Reason for condition
To ensure the safety of vehicles entering and leaving the development and the safety and access around the development site for the general public and adjacent businesses.
ENG 3a
The access driveway, circulation roadways, ramps and parking module (parking spaces, aisles and manoeuvring area) must be designed and constructed in accordance with Australian Standard AS/NZS2890.1:2004 (including the requirement for vehicle safety barriers where required), or a Council approved alternate design certified by a suitably qualified engineer to provide a safe and efficient access, and enable safe, easy and efficient use.
Reason for condition
To ensure the safety of users of the access and parking module, and compliance with the relevant Australian Standard.
ENG 4
The access driveway and parking module (car parking spaces, aisles and manoeuvring area) approved by this permit must be constructed to a sealed standard (spray seal, asphalt, concrete, pavers or equivalent Council approved) and surface drained to the Council's stormwater infrastructure prior to the commencement of use.
Reason for condition
To ensure the safety of users of the access driveway and parking module, and that it does not detract from the amenity of users, adjoining occupiers or the environment by preventing dust, mud and sediment transport.
ENG 8
The use of the car parking spaces is restricted to User Class 1A (residential, domestic and employee parking) in accordance with Australian Standards AS/NZS2890.1 2004 Table 1.1.
Prior to commencement of use:
· A sign, approved by council, and in accordance with Australian Standards AS/NZS1742.11:2016, must be erected at the entry of the parking access to indicate the parking area is for residents only; and · All parking spaces must be delineated by means of white or yellow lines 80mm to 100mm wide, or white or yellow pavement markers in accordance with Australian Standards AS/NZS 2890.1 2004.
Reason for condition
In the interests of vehicle user safety and the amenity of the development.
ENG 1
Any damage to council infrastructure resulting from the implementation of this permit, must, at the discretion of the Council:
1. Be met by the owner by way of reimbursement (cost of repair and reinstatement to be paid by the owner to the Council); or 2. Be repaired and reinstated by the owner to the satisfaction of the Council.
A photographic record of the Council's infrastructure adjacent to the subject site must be provided to the Council prior to any commencement of works.
A photographic record of the Council’s infrastructure (e.g. existing property service connection points, roads, buildings, stormwater, footpaths, driveway crossovers and nature strips, including if any, preexisting damage) will be relied upon to establish the extent of damage caused to the Council’s infrastructure during construction. In the event that the owner/developer fails to provide to the Council a photographic record of the Council’s infrastructure, then any damage to the Council's infrastructure found on completion of works will be deemed to be the responsibility of the owner.
Reason for condition
To ensure that any of the Council's infrastructure and/or siterelated service connections affected by the proposal will be altered and/or reinstated at the owner’s full cost.
ENG 13
The front fencing and planter along the northeastern boundary must allow adequate sight distance between user vehicles, cyclists and pedestrians in accordance with Australian/NZ Standard, Parking facilities Part 1: Offstreet car parking AS/NZS 2890.1: 2004 Fig 3.3
Reason for condition
To ensure the safety of vehicles entering and leaving the development and of pedestrians and traffic in the vicinity.
ENG r1
The excavation and earthretaining structures within or supporting the highway reservation must not undermine the stability and integrity of the highway reservation and its infrastructure.
Detailed design drawings, structural certificates and associated geotechnical assessments of the retaining wall supporting the highway reservation must be submitted and approved, prior to the commencement of work and must:
1. Be prepared and certified by a suitable qualified person and experienced engineer; 2. Not undermine the stability of the highway reservation 3. Be designed in accordance with AS4678, with a design life in accordance with table 3.1 typical application major public infrastructure works 4. Take into account any additional surcharge loadings as required by relevant Australian Standards. 5. Take into account and reference accordingly any Geotechnical findings 6. Detail any mitigation measures required
The structure certificated and/or drawings should note accordingly the above requirements.
All work required by this condition must be undertaken in accordance with the approved select design drawing and structural certificates.
Advice:
The applicant is required submit detailed design documentation to satisfy this condition via Council's planning condition endorsement process (noting there is a fee associated with condition endorsement approval of engineering drawings [see general advice on how to obtain condition endorsement and for fees and charges]). This is a separate process to any building approval under the Building Act 2016.
Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.
Reason for condition
To ensure that the stability and integrity of the Council’s highway reservation is not compromised by the development.
ENG r3
Prior to the commencement of use, the proposed driveway crossover and removal of redundant crossover must be designed and constructed in accordance with:
· Urban TSDR09v1 – Urban Roads Driveways and TSD R14v1 Type KC vehicular crossing · Kerb TSDR14v1 · Footpath Urban Roads Footpaths TSDR11v1
Design drawings must be submitted and approved prior to any approval under the Building Act 2016. The design drawing must:
1. Show the cross and long section of the driveway crossover within the highway reservation and onto the property 2. Detail any services or infrastructure (ie light poles, pits, awnings) at or near the proposed driveway crossover 3. Be designed for the expected vehicle loadings. A structural certificate to note that driveway is suitable for heavy vehicle loadings. 4. Show swept path templates in accordance with AS/NZS 2890.1 2004(B85 or B99 depending on use, design template) 5. If the design deviates from the requirements of the TSD then the drawings must demonstrate that a B85 vehicle or B99 depending on use (AS/NZS 2890.1 2004, section 2.6.2) can access the driveway from the road pavement into the property without scraping the cars underside 6. Show that the redundant crossover will be removed and reinstated with kerb 7. Be prepared and certified by a suitable qualified person, to satisfy the above requirement.
All work required by this condition must be undertaken in accordance with the approved drawings.
Advice:
The applicant is required submit detailed design documentation to satisfy this condition via Council's planning condition endorsement process (noting there is a fee associated with condition endorsement approval of engineering drawings [see general advice on how to obtain condition endorsement and for fees and charges]). This is a separate process to any building approval under the Building Act 2016.
Please note that your proposal does not include adjustment of footpath levels. Any adjustment to footpath levels necessary to suit the design of proposed floor, parking module or driveway levels will require separate agreement from Council's Road Services Engineer and may require further planning approvals. It is advised to place a note to this affect on construction drawings for the site and/or other relevant engineering drawings to ensure that contractors are made aware of this requirement.
Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.
Reason for condition
To ensure that works will comply with the Council’s standard requirements.
ENV 8
All recommendations in section 6 of the landslide risk assessment report by GeoEnvironmental Solutions P/L dated April 2020 and received by the Planning Authority on 1 May 2020 must be implemented including:
· Protection works for the planned excavations must be installed on the upslope sides of the proposed development prior to carrying out excavation works at the site. · The works must be designed in accordance with the good hillside construction practices as outlined in the Australian Geomechanics Society (AGS) Geoguide LR8. · Further geotechnical testing must be undertaken to define parameters for the design of protection works including soil/rock bearing capacity, lateral earth pressures and friction angles. · The further investigations must also include adequate deep drilling and testing to confirm foundation conditions for the anticipated building loads.
Reason for condition
To reduce the risk to life and property, and the cost to the community, caused by landslides.
ENV 2
Sediment and erosion control measures, in accordance with an approved soil and water management plan (SWMP), must be installed prior to the commencement of work and maintained until such time as all disturbed areas have been stabilised and/or restored or sealed to the Council’s satisfaction.
A SWMP must be submitted prior to the issue of any approval under the Building Act 2016 or the commencement of work, whichever occurs first. The SWMP must be prepared in accordance with the Soil and Water Management on Building and Construction Sites fact sheets (Derwent Estuary Program, 2008), available here.
All work required by this condition must be undertaken in accordance with the approved SWMP.
Advice:
Once the SWMP has been approved, the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement).
Where building approval is also required, it is recommended that documentation for condition endorsement be submitted well before submitting documentation for building approval. Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.
Reason for condition
To avoid the pollution and sedimentation of roads, drains and natural watercourses that could be caused by erosion and runoff from the development.
HER 9
All construction documentation must contain protocols and recommendations for all contractors working in close proximity to the stone wall along the boundary of 281 Liverpool Street (The Pickled Frog) to be familiar with the heritage values of the heritage listed site and for the need to protect the wall at all costs whilst undertaking the proposed works to upgrade infrastructure.
Prior to the commencement of works (including demolition and excavation), all workers and managers must be briefed on the importance of the cultural heritage values of the site as part of a site induction. This must be undertaken by a suitably qualified heritage practitioner.
Documents containing protocols for the protection of the wall must be submitted and approved, prior to the issuing of any approval under the Building Act 2016 or commencement of works (which ever occurs first).
Reason for condition
To ensure that there is no loss or damage to the heritage values or fabric of the site.
HER 6
All onsite excavation and disturbance must be monitored in accordance with the Praxis Environment Report dated January 2020. In addition should any features or deposits of an archaeological nature be discovered on the site during excavation or disturbance:
1. All excavation and/or disturbance must stop immediately; and 2. A qualified archaeologist must be engaged to attend the site and provide advice and assessment of the features and/or deposits discovered and make recommendations on further excavation and/or disturbance; and 3. All and any recommendations made by the archaeologist engaged in accordance with (2) above must be complied with in full; and 4. All features and/or deposits discovered must be reported to the Council with one (1) day of the discovery; and 5. A copy of the archaeologists advice, assessment and recommendations obtained in accordance with (2) above must be provided to the Council within 30 days of receipt of the advice, assessment and recommendations.
Excavation and/or disturbance must not recommence unless and until approval is granted from the Council.
Reason for condition
To ensure that work is planned and implemented in a manner that seeks to understand, retain, protect, preserve and manage significant archaeological evidence.
ENVHE 1
Recommendations in the report Environmental Site Assessment 283287 Liverpool Street, by GES, dated February 2020, must be implemented, for the duration of the development.
Reason for condition
To ensure that the risk to workers and future users of the site remains low and acceptable.
ENVHE 4
A construction management plan must be implemented throughout the construction works.
A construction management plan must be submitted and approved prior to the issuing of any building permit under the Building Act 2016. The plan must include but is not limited to the following:
1. Identification and disposal of any potentially contaminated waste and asbestos; 2. Proposed hours of work (including volume and timing of heavy vehicles entering and leaving the site, and works undertaken on site); 3. Proposed hours of construction; 4. Identification of potentially noisy construction phases, such as operation of rock breakers, explosives or pile drivers, and proposed means to minimise impact on the amenity of neighbouring buildings; 5. Control of dust and emissions during working hours; 6. Proposed screening of the site and vehicular access points during work; and 7. Procedures for washing down vehicles, to prevent soil and debris being carried onto the street.
All work required by this condition must be undertaken in accordance with the approved construction management plan.
Advice:
Once the construction management plan has been approved the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement).
Where building approval is also required, it is recommended that documentation for condition endorsement be submitted well before submitting documentation for building approval. Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.
Reason for condition
To ensure minimal impact on the amenity of adjoining properties and members of the public during the construction period.
ADVICE
The following advice is provided to you to assist in the implementation of the planning permit that has been issued subject to the conditions above. The advice is not exhaustive and you must inform yourself of any other legislation, bylaws, regulations, codes or standards that will apply to your development under which you may need to obtain an approval. Visit the Council's website for further information.
Prior to any commencement of work on the site or commencement of use the following additional permits/approval may be required from the Hobart City Council.
BUILDING PERMIT
You may need building approval in accordance with the Building Act 2016. Click here for more information.
This is a Discretionary Planning Permit issued in accordance with section 57 of the Land Use Planning and Approvals Act 1993.
PLUMBING PERMIT
You may need plumbing approval in accordance with the Building Act 2016, Building Regulations 2016 and the National Construction Code. Click here for more information.
OCCUPATION OF THE PUBLIC HIGHWAY
You may require a permit for the occupation of the public highway for construction or special event (e.g. placement of skip bin, crane, scissor lift etc). Click here for more information.
You may require a road closure permit for construction or special event. Click here for more information.
You may require a Permit to Open Up and Temporarily Occupy a Highway (for work in the road reserve). Click here for more information.
PROTECTION OF PUBLIC INFRASTRUCTURE
You will be required to pay a bond to ensure the protection of public infrastructure during the construction works (please contact the Hobart City Council's City Amenity Division to initiate the process).
NEW SERVICE CONNECTION
Please contact the Hobart City Council's City Amenity Division to initiate the application process for your new stormwater connection.
STORM WATER
Please note that in addition to a building and/or plumbing permit, development must be in accordance with the Hobart City Council’s Infrastructure By law. Click here for more information.
STRUCTURES CLOSE TO COUNCILS' STORMWATER MAIN
The design of structures (including footings) must provide protection for the Council’s infrastructure. For information regarding appropriate designs please contact the Council's City Amenity Division. You may need the General Manager's consent under section 13 of the Urban Drainage Ace 2013 and consent under section 73 or 74 of the Building Act 2016.
WORK WITHIN THE HIGHWAY RESERVATION
Please note development must be in accordance with the Hobart City Council’s Infrastructure By law. Click here for more information.
CBD AND HIGH VOLUME FOOTPATH CLOSURES
Please note that the City of Hobart does not support the extended closure of public footpaths or roads to facilitate construction on adjacent land.
It is the developer's responsibility to ensure that the proposal as designed can be constructed without reliance on such extended closures.
In special cases, where it can be demonstrated that closure of footpaths in the CBD and/or other high volume footpaths can occur for extended periods without unreasonable impact on other businesses or the general public, such closures may only be approved by the full Council.
For more information about this requirement please contact the Council's Traffic Engineering Unit on 6238 2804.
REDUNDANT CROSSOVERS
Redundant crossovers are required to be reinstated under the Hobart City Council’s Infrastructure By law. Click here for more information.
ACCESS
Designed in accordance with LGAT IPWEA – Tasmanian standard drawings. Click here for more information.
CROSS OVER CONSTRUCTION
The construction of the crossover can be undertaken by the Council or by a private contractor, subject to Council approval of the design. Click here for more information.
STORM WATER / ROADS / ACCESS
Services to be designed and constructed in accordance with the (IPWEA) LGAT – standard drawings. Click here for more information.
WORK PLACE HEALTH AND SAFETY
Appropriate occupational health and safety measures must be employed during the works to minimise direct human exposure to potentiallycontaminated soil, water, dust and vapours. Click here for more information.
PROTECTING THE ENVIRONMENT
In accordance with the Environmental Management and Pollution Control Act 1994, local government has an obligation to "use its best endeavours to prevent or control acts or omissions which cause or are capable of causing pollution." Click here for more information.
LEVEL 1 ACTIVITIES
The activity conducted at the property is an environmentally relevant activity and a Level 1 Activity as defined under s.3 of the Environmental Management and Pollution Control Act 1994. For further information on what your responsibilities are, click here.
NOISE REGULATIONS
Click here for information with respect to noise nuisances in residential areas.
WASTE DISPOSAL
It is recommended that the developer liaise with the Council’s Cleansing and Solid Waste Unit regarding reducing, reusing and recycling materials associated with demolition on the site to minimise solid waste being directed to landfill.
Further information regarding waste disposal can also be found on the Council’s website.
FEES AND CHARGES
Click here for information on the Council's fees and charges.
DIAL BEFORE YOU DIG
Click here for dial before you dig information.
|
Attachment a: PLN-20-191
- 283-287 LIVERPOOL STREET HOBART TAS 7000 - Planning Committee or Delegated
Report ⇩
Attachment
b: PLN-20-191
- 283-287 LIVERPOOL STREET HOBART TAS 7000 - CPC Agenda Documents ⇩
Attachment
c: PLN-20-191
- 283-287 LIVERPOOL STREET HOBART TAS 7000 - Planning Referral Officer Cultural
Heritage Report ⇩
Attachment
d: PLN-20-191
- 283-287 LIVERPOOL STREET HOBART TAS 7000 - Urban Design Advisory Panel
Minutes ⇩
Item No. 12 |
Supplementary Agenda (Open Portion) City Planning Committee Meeting - 15/6/2020 |
Page 31 ATTACHMENT a |
Supplementary Agenda (Open Portion) City Planning Committee Meeting - 15/6/2020 |
Page 96 ATTACHMENT b |
Supplementary Agenda (Open Portion) City Planning Committee Meeting - 15/6/2020 |
Page 153 ATTACHMENT c |
Supplementary Agenda (Open Portion) City Planning Committee Meeting - 15/6/2020 |
Page 159 ATTACHMENT d |
Supplementary Agenda (Open Portion) City Planning Committee Meeting |
Page 161 |
|
|
15/6/2020 |
|
13 29 Aberdeen Street, Glebe, 2 Davies Avenue, Hobart - Change of Use to Visitor Accommodation
Address: 29 Aberdeen Street Glebe, 2 Davies Avenue, Hobart
Proposal: Change of Use to Visitor Accommodation
Expiry Date: 25 June 2020
Extension of Time: Not applicable
Author: Helen Ayers
That pursuant to the Hobart Interim Planning Scheme 2015, the Council approve the application for change of use to visitor accommodation at 29 Aberdeen Street, Glebe for the reasons outlined in the officer’s report and a permit containing the following conditions be issued:
GEN
The use and/or development must be substantially in accordance with the documents and drawings that comprise PLN20106 29 ABERDEEN STREET GLEBE TAS 7000 Final Planning Documents, except where modified below.
Reason for condition
To clarify the scope of the permit.
ADVICE
The following advice is provided to you to assist in the implementation of the planning permit that has been issued subject to the conditions above. The advice is not exhaustive and you must inform yourself of any other legislation, bylaws, regulations, codes or standards that will apply to your development under which you may need to obtain an approval. Visit the Council's website for further information.
Prior to any commencement of work on the site or commencement of use the following additional permits/approval may be required from the Hobart City Council.
BUILDING PERMIT
You may need building approval in accordance with the Building Act 2016. Click here for more information.
This is a Discretionary Planning Permit issued in accordance with section 57 of the Land Use Planning and Approvals Act 1993.
NOISE REGULATIONS
Click here for information with respect to noise nuisances in residential areas.
VISITOR ACCOMMODATION
More information on visitor accommodation, including when building approval is required, can be found here.
In all cases, check with your insurance company that you have adequate cover.
If you are in a bushfire prone area there may be a need to create/review the Bushfire Management Hazard Plan for your property.
You are encouraged to have in place a management plan for the operation of the visitor accommodation. The management plan should include measures to limit, manage and mitigate unreasonable impacts upon the amenity of permanent residents, including addressing issues like noise, waste management, customer behaviour, security, and maximum occupancy.
Visitor accommodation is also considered to be a commercial use and also not eligible to residential parking permits. Under the current policy for the issuing of residential parking permits, the proposed change of use to visitor accommodation would not entitle the property to a residential parking permit, or a transferable “bed and breakfast” parking permit.
|
Attachment a: PLN-20-106
- 29 ABERDEEN STREET GLEBE TAS 7000 - Planning Committee or Delegated Report ⇩
Attachment
b: PLN-20-106
- 29 ABERDEEN STREET GLEBE TAS 7000 - CPC Agenda Documents ⇩
Item No. 13 |
Supplementary Agenda (Open Portion) City Planning Committee Meeting - 15/6/2020 |
Page 162 ATTACHMENT a |
Supplementary Agenda (Open Portion) City Planning Committee Meeting - 15/6/2020 |
Page 169 ATTACHMENT b |