City
of hobart
MINUTES
City Planning Committee Meeting
Open Portion
Monday, 15 January 2018 at 5:00pm
|
Minutes (Open Portion) City Planning Committee Meeting |
Page 2 |
|
15/1/2018 |
|
APOLOGIES AND LEAVE OF ABSENCE
1. Co-Option of a Committee Member in the event of a vacancy
3. Consideration of Supplementary Items
4. Indications of Pecuniary and Conflicts of Interest
6. Planning Authority Items - Consideration of Items with Deputations
7. Committee Acting as Planning Authority
7.1 Applications under the Hobart Interim Planning Scheme 2015
7.1.1 3 Lasswade Avenue, Sandy Bay - Partial Demolition, Extension and Front Fencing
7.1.3 Augusta Road, Road Reserve Reservation, Lenah Valley - Signage
7.1.4 2A McRobies Road, South Hobart - Partial Demolition and Alterations to Carpark
7.1.5 19 Lansdowne Crescent, West Hobart - Alterations to Car Park
8.1 Coast to Coast Hobart 2018
8.2 Urban Design Advisory Panel - Terms of Reference Review
8.3 City Planning - Advertising List
8.4 Delegated Decisions Report (Planning)
8.5 Major Projects Legislation - Amendments Following Initial Consultation
9 Committee Action Status Report
9.1 Committee Actions - Status Report
10. Responses to Questions without Notice
|
Minutes (Open Portion) City Planning Committee Meeting |
Page 4 |
|
15/01/2018 |
|
City Planning Committee Meeting (Open Portion) held on Monday, 15 January 2018 at 5:00 pm in the Lady Osborne Room, Town Hall.
COMMITTEE MEMBERS Briscoe (Chairman) Ruzicka Burnet Denison
PRESENT: Alderman J R Briscoe (Chairman), Aldermen E R Ruzicka, H C Burnet, T M Denison and W F Harvey.
APOLOGIES: Nil.
LEAVE OF ABSENCE: Nil.
|
ALDERMEN Lord Mayor Hickey Deputy Lord Mayor Christie Zucco Sexton Cocker Thomas Reynolds Harvey
Alderman Harvey was co-opted to the Committee.
|
BURNET
That Alderman Harvey be co-opted to the Committee.
MOTION CARRIED
VOTING RECORD
AYES |
NOES |
Briscoe |
|
Ruzicka |
|
Burnet |
|
Denison |
|
BURNET |
||||||||||||
The minutes of the Open Portion of the City Planning Committee meeting held on Monday, 11 December 2017, be confirmed as an accurate record.
|
||||||||||||
MOTION CARRIED VOTING RECORD
|
The minutes were signed.
Ref: Part 2, Regulation 8(6) of the Local Government (Meeting Procedures) Regulations 2015.
That the Committee resolve to deal with any supplementary items not appearing on the agenda, as reported by the General Manager.
No supplementary items were received.
|
Ref: Part 2, Regulation 8(7) of the Local Government (Meeting Procedures) Regulations 2015.
Aldermen are requested to indicate where they may have any pecuniary or conflicts of interest in respect to any matter appearing on the agenda, or any supplementary item to the agenda, which the committee has resolved to deal with.
No interest was indicated.
Regulation 15 of the Local Government (Meeting Procedures) Regulations 2015.
A committee may close a part of a meeting to the public where a matter to be discussed falls within 15(2) of the above regulations.
In the event that the committee transfer an item to the closed portion, the reasons for doing so should be stated.
Are there any items which should be transferred from this agenda to the closed portion of the agenda, or from the closed to the open portion of the agenda?
No items were transferred.
In accordance with the requirements of Part 2 Regulation 8(3) of the Local Government (Meeting Procedures) Regulations 2015, the General Manager is to arrange the agenda so that the planning authority items are sequential.
In accordance with Part 2 Regulation 8(4) of the Local Government (Meeting Procedures) Regulations 2015, the Committee by simple majority may change the order of any of the items listed on the agenda, but in the case of planning items they must still be considered sequentially – in other words they still have to be dealt with as a single group on the agenda.
Where deputations are to be received in respect to planning items, past practice has been to move consideration of these items to the beginning of the meeting.
BURNET
That in accordance with Regulation 8(4) of the Local Government (Meeting Procedures) Regulations 2015, the Committee resolve to deal with any items which have deputations by members of the public regarding any planning matter listed on the agenda, to be taken out of sequence in order to deal with deputations at the beginning of the meeting.
MOTION CARRIED
VOTING RECORD
AYES |
NOES |
Briscoe |
|
Ruzicka |
|
Burnet |
|
Denison |
|
Harvey |
|
BURNET
That item 8.5 be taken out of sequence in order to deal with a deputation at the beginning of the meeting.
MOTION CARRIED
VOTING RECORD
AYES |
NOES |
Briscoe |
|
Ruzicka |
|
Burnet |
|
Denison |
|
Harvey |
|
|
Minutes (Open Portion) City Planning Committee Meeting |
Page 8 |
|
15/01/2018 |
|
In accordance with the provisions of Part 2 Regulation 25 of the Local Government (Meeting Procedures) Regulations 2015, the intention of the Committee to act as a planning authority pursuant to the Land Use Planning and Approvals Act 1993 is to be noted.
In accordance with Regulation 25, the Committee will act as a planning authority in respect to those matters appearing under this heading on the agenda, inclusive of any supplementary items.
The Committee is reminded that in order to comply with Regulation 25(2), the General Manager is to ensure that the reasons for a decision by a Council or Council Committee acting as a planning authority are recorded in the minutes.
7.1 Applications under the Hobart Interim Planning Scheme 2015
Ms Christie Denman of David Denman and Associates addressed the Committee in relation to item 7.1.1, on behalf of the Applicant.
7.1.1 3 Lasswade Avenue, Sandy Bay - Partial Demolition, Extension and Front Fencing |
||||||||||||
HARVEY That pursuant to the Hobart Interim Planning Scheme 2015, the Council approve the application for Partial Demolition, Extension and Front Fencing at 3 Lasswade Avenue, SANDY BAY, and a permit containing the following conditions be issued: GEN
The use and/or development must be substantially in
accordance with the documents and drawings that comprise PLN-17-844 - 3
LASSWADE AVENUE SANDY BAY 7005 - Final Planning Documents except where
modified below.
THC
The use and/or development must comply with the
requirements of the Tasmanian Heritage Council as detailed in the Notice of
Heritage Decision, THC Works Ref: 5462 dated 8 January 2018 as
attached to the permit.
PLN s1
The transparency of the
elevations of the building containing the swimming pool must be
maximised.
ENG sw4
The development (including hardstand) must be drained to Council infrastructure. The new stormwater connection must be constructed, and any existing connections made redundant must be abandoned and sealed, at the owner's cost prior to the first occupation. Detailed engineering drawings
must be submitted and approved, prior to commencement of work. The detailed
engineering drawings must include: · the location of the proposed connections and all existing connections; · the size and design of the connection such that it is appropriate to safely service the development; · long-sections of the proposed connection clearly showing required levels, grade, clearances from any nearby services, cover, size, material and delineation of public and private infrastructure. Connections must be free-flowing gravity. ·
no impervious areas capable of reaching
the existing northern-most connection may be directed to the new
connection or existing southern connections
All work required by this
condition must be undertaken in accordance with the approved engineering
drawings.
ENG 1
The cost of repair of any
damage to the Council's infrastructure resulting from the implementation of
this permit, must be met by the owners within 30 days of the completion of
the development or as otherwise determined by the Council. Any damage
must be immediately reported to Council.
ENV 1
Sediment and erosion control measures sufficient to
prevent sediment from leaving the site must be installed prior to any
disturbance of the site. Sediment controls must be maintained until all areas
of disturbance have been stabilized or re-vegetated.
HER 17
The palette of exterior
colours and materials of the extension, the garage and the building
containing the swimming pool must reflect the palette of materials within the
local streetscape and precinct and must be to the satisfaction of the
Director City Planning. ADVICE
The following advice is provided to you to assist in the
implementation of the planning permit that has been issued subject to the
conditions above. The advice is not exhaustive and you must inform yourself
of any other legislation, by-laws, regulations, codes or standards that will
apply to your development under which you may need to obtain an approval.
Visit the Council's website for
further information.
CONDITION ENDORSEMENT If a condition endorsement is
required by a planning condition above, you will need to submit the relevant
documentation to satisfy the condition via the Condition Endorsement
Submission on Council's online services e-planning
BUILDING PERMIT You may need building approval in accordance with the Building Act 2016. Click here for more information. This is a Discretionary Planning Permit issued in accordance with section 57 of the Land Use Planning and Approvals Act 1993.
PLUMBING PERMIT You may need plumbing approval in accordance with the Building Act 2016, Building Regulations 2016 and the National Construction Code. Click here for more information.
OCCUPATION OF THE PUBLIC HIGHWAY You may require a road closure
permit for construction or special event. Click here for more information.
NEW SERVICE CONNECTION Please contact the Hobart City Council's City Infrastructure Division to initiate the application process for your new service connection.
STORM WATER Please note that in addition to a building and/or plumbing permit, development must be in accordance with the Hobart City Council’s Hydraulic Services By law. Click here for more information.
WORK WITHIN THE HIGHWAY RESERVATION Please note development must be in accordance with the Hobart City Council’s Highways By law. Click here for more information.
DRIVEWAY SURFACING OVER HIGHWAY RESERVATION If a coloured or textured surface is used for the driveway access within the Highway Reservation, the Council or other service provider will not match this on any reinstatement of the driveway access within the Highway Reservation required in the future.
REDUNDANT CROSSOVERS Redundant crossovers are required to be reinstated under the Hobart City Council’s Highways By law. Click here for more information.
ACCESS Designed in accordance with LGAT-
IPWEA – Tasmanian standard drawings. Click here for
more information. CROSS OVER CONSTRUCTION
STORM WATER / ROADS / ACCESS Services to be designed and constructed in accordance with the (IPWEA) LGAT – standard drawings. Click here for more information.
WORK PLACE HEALTH AND SAFETY Appropriate occupational health and safety measures must be employed during the works to minimise direct human exposure to potentially-contaminated soil, water, dust and vapours. Click here for more information.
FEES AND CHARGES Click here for information on the Council's fees and charges.
DIAL BEFORE YOU DIG Click here for dial before you dig information.
|
||||||||||||
MOTION CARRIED VOTING RECORD
|
||||||||||||
COMMITTEE RESOLUTION: |
||||||||||||
That pursuant to the Hobart Interim Planning Scheme 2015, the Council approve the application for Partial Demolition, Extension and Front Fencing at 3 Lasswade Avenue, SANDY BAY, and a permit containing the following additional conditions be issued: GEN
The use and/or development must be substantially in
accordance with the documents and drawings that comprise PLN-17-844 - 3
LASSWADE AVENUE SANDY BAY 7005 - Final Planning Documents except where
modified below.
THC
The use and/or development
must comply with the requirements of the Tasmanian Heritage Council as
detailed in the Notice of Heritage Decision, THC Works Ref: 5462 dated 8
January 2018 as attached to the permit.
PLN s1
The elevations of the building
containing the swimming pool must be transparent.
ENG sw4 The development (including hardstand) must be drained to Council infrastructure. The new stormwater connection must be constructed, and any existing connections made redundant must be abandoned and sealed, at the owner's cost prior to the first occupation. Detailed engineering drawings must be submitted and approved, prior to commencement of work. The detailed engineering drawings must include: · the location of the proposed connections and all existing connections; · the size and design of the connection such that it is appropriate to safely service the development; · long-sections of the proposed connection clearly showing required levels, grade, clearances from any nearby services, cover, size, material and delineation of public and private infrastructure. Connections must be free-flowing gravity. ·
no impervious areas capable of reaching
the existing northern-most connection may be directed to the new
connection or existing southern connections. All work required by this
condition must be undertaken in accordance with the approved engineering
drawings.
ENG 1
The cost of repair of any
damage to the Council's infrastructure resulting from the implementation of
this permit, must be met by the owners within 30 days of the completion of
the development or as otherwise determined by the Council. Any damage
must be immediately reported to Council.
ENV 1
Sediment and erosion control measures sufficient to
prevent sediment from leaving the site must be installed prior to any
disturbance of the site. Sediment controls must be maintained until all areas
of disturbance have been stabilized or re-vegetated.
HER 17
The palette of exterior colours and materials of the
extension, the garage and the building containing the swimming pool must
reflect the palette of materials within the local streetscape and precinct.
ADVICE
The following advice is provided to you to assist in the
implementation of the planning permit that has been issued subject to the
conditions above. The advice is not exhaustive and you must inform yourself
of any other legislation, by-laws, regulations, codes or standards that will
apply to your development under which you may need to obtain an approval.
Visit the Council's website for
further information.
CONDITION ENDORSEMENT If a condition endorsement is
required by a planning condition above, you will need to submit the relevant
documentation to satisfy the condition via the Condition Endorsement
Submission on Council's online services e-planning
BUILDING PERMIT You may need building approval in accordance with the Building Act 2016. Click here for more information. This is a Discretionary Planning Permit issued in accordance with section 57 of the Land Use Planning and Approvals Act 1993.
PLUMBING PERMIT You may need plumbing approval in accordance with the Building Act 2016, Building Regulations 2016 and the National Construction Code. Click here for more information.
OCCUPATION OF THE PUBLIC HIGHWAY You may require a road closure
permit for construction or special event. Click here for more information.
NEW SERVICE CONNECTION Please contact the Hobart City Council's City Infrastructure Division to initiate the application process for your new service connection.
STORM WATER Please note that in addition to a building and/or plumbing permit, development must be in accordance with the Hobart City Council’s Hydraulic Services By law. Click here for more information.
WORK WITHIN THE HIGHWAY RESERVATION Please note development must be in accordance with the Hobart City Council’s Highways By law. Click here for more information.
DRIVEWAY SURFACING OVER HIGHWAY RESERVATION If a coloured or textured surface is used for the driveway access within the Highway Reservation, the Council or other service provider will not match this on any reinstatement of the driveway access within the Highway Reservation required in the future.
REDUNDANT CROSSOVERS Redundant crossovers are required to be reinstated under the Hobart City Council’s Highways By law. Click here for more information.
ACCESS Designed in accordance with LGAT-
IPWEA – Tasmanian standard drawings. Click here for
more information. CROSS OVER CONSTRUCTION
STORM WATER / ROADS / ACCESS Services to be designed and constructed in accordance with the (IPWEA) LGAT – standard drawings. Click here for more information.
WORK PLACE HEALTH AND SAFETY Appropriate occupational health and safety measures must be employed during the works to minimise direct human exposure to potentially-contaminated soil, water, dust and vapours. Click here for more information.
FEES AND CHARGES Click here for information on the Council's fees and charges.
DIAL BEFORE YOU DIG Click here for dial before you dig information.
|
Delegation: Council
Mr Michael Gregg (representor) addressed the Committee in relation to item 7.1.2
Delegation: Council
Item 8.5 was then taken.
7.1.3 Augusta Road, Road Reserve Reservation, Lenah Valley - Signage |
||||||||||||
RUZICKA That the recommendation contained in the report of the Development Appraisal Officer and the Senior Statutory Planner of 14 December 2017, be adopted. |
||||||||||||
MOTION CARRIED VOTING RECORD
|
||||||||||||
COMMITTEE RESOLUTION: |
||||||||||||
That pursuant to the Hobart Interim Planning Scheme 2015, the Council approve the application for Signage at Augusta Road, Road Reservation, Lenah Valley for the reasons outlined in the officer’s report and a permit containing the following conditions be issued:
GEN
The use and/or development must be substantially in accordance with the documents and drawings that comprise PLN17852 AUGUSTA ROAD LENAH VALLEY TAS 7008 (ROAD RESERVATION) Final Planning Documents except where modified below.
Reason for condition
To clarify the scope of the permit.
ADVICE
The following advice is provided to you to assist in the implementation of the planning permit that has been issued subject to the conditions above. The advice is not exhaustive and you must inform yourself of any other legislation, bylaws, regulations, codes or standards that will apply to your development under which you may need to obtain an approval. Visit the Council's website for further information.
Prior to any commencement of work on the site or commencement of use the following additional permits/approval may be required from the Hobart City Council.
BUILDING PERMIT
You may need building approval in accordance with the Building Act 2016. Click here for more information.
This is a Discretionary Planning Permit issued in accordance with section 57 of the Land Use Planning and Approvals Act 1993.
OCCUPATION OF THE PUBLIC HIGHWAY
You may require a permit for the occupation of the public highway for construction or special event (e.g. placement of skip bin, crane, scissor lift etc). Click here for more information.
You may require an occupational license for structures in the Hobart City Council highway reservation, in accordance with conditions to be established by the Council. Click here for more information.
You may require a road closure permit for construction or special event. Click here for more information.
You may require a Permit to Open Up and Temporarily Occupy a Highway (for work in the road reserve). Click here for more information.
WORK WITHIN THE HIGHWAY RESERVATION
Please note development must be in accordance with the Hobart City Council’s Highways By law. Click here for more information. |
Delegation: Council
7.1.4 2A McRobies Road, South Hobart - Partial Demolition and Alterations to Carpark |
||||||||||||
RUZICKA That the recommendation contained in the report of the Development Appraisal Officer and the Senior Statutory Planner of 14 December 2017, be adopted. |
||||||||||||
MOTION CARRIED VOTING RECORD
|
||||||||||||
COMMITTEE RESOLUTION: |
||||||||||||
That pursuant to the Hobart Interim Planning Scheme 2015, the Council approve the application for Partial Demolition and Alterations to Car Park at 2A McRobies Road, SOUTH HOBART for the reasons outlined in the officer’s report and a permit containing the following conditions be issued:
GEN
The use and/or development must be substantially in accordance with the documents and drawings that comprise PLN17687 2A MCROBIES ROAD SOUTH HOBART TAS 7004 Final Planning Documents except where modified below.
Reason for condition
To clarify the scope of the permit.
PLN s1
Works shown within the McRobies Road highway reservation (Coach parking, Pavement marking) have not been included in this assessment and are therefore not approved as part of this permit.
Advice: Any changes to the existing onstreet parking/traffic management within the McRobies Road highway reservation adjacent to the subject site must be negotiated and agreed with the Council's Manager Traffic Engineering separate to this planning approval.
Reason for condition
To clarify the scope of the permit.
ENG sw4
Where a new stormwater service connection is required, the new stormwater connection must be constructed at the owner’s expense prior to the commencement of use.
Advice: A stormwater service connection must be approved by Council's City Infrastructure Unit prior to construction of the stormwater service connection. Please contact Council’s City Infrastructure Unit to initiate an application for a stormwater service connection.
Reason for condition
To ensure the site is drained adequately.
ENG 2
Vehicular barriers compliant with the Australian Standard AS 1170.1 must be installed to prevent vehicles running off the edge of a parking module where the drop from the edge of the trafficable area to a lower level is 600mm or greater, and wheel stops must be installed for drops between 150mm and 600mm. Barriers must not limit the width of the driveway access or parking and turning areas approved under the permit. Barriers must be installed prior to commencement of use.
Prior to the commencement of use, the installed vehicular barriers must be inspected by a qualified engineer and certification submitted and accepted confirming that the installed vehicular barriers comply with Australian Standard AS 1170.1.h.
Advice: The Council does not consider a slope greater than 1 in 4 to constitute a lower level as described in AS/NZS 2890.1:2004 Section 2.4.5.3
Once the certification of the installed vehicular barriers has been accepted, Council will issue a condition endorsement (see general advice on how to obtain condition endorsement).
Reason for condition
To ensure that the safety of users of the driveway/parking and compliance with the standard.
ENG 4
The access and parking module approved by this permit must be constructed to a sealed standard and surface drained prior to the commencement of use.
Reason for condition
To ensure safe access is provided for the use.
ENG 1
The cost of repair of any damage to the Council's infrastructure resulting from the implementation of this permit, must be met by the owners within 30 days of the completion of the development or as otherwise determined by the Council.
A photographic record of the Council's infrastructure adjacent to the subject site must be provided to the Council prior to any commencement of works.
A photographic record of the Council’s infrastructure (e.g. existing property service connection points, roads, buildings, stormwater, footpaths, driveway crossovers and nature strips, including if any, preexisting damage) will be relied upon to establish the extent of damage caused to the Council’s infrastructure during construction. In the event that the owner/developer fails to provide to the Council a photographic record of the Council’s infrastructure, then any damage to the Council's infrastructure found on completion of works will be deemed to be the responsibility of the owner.
Reason for condition
To ensure that any of the Council's infrastructure and/or siterelated service connections affected by the proposal will be altered and/or reinstated at the owner’s full cost.
ENV 2
Sediment and erosion control measures, in accordance with an approved soil and water management plan (SWMP), must be installed prior to the commencement of work and maintained until such time as all disturbed areas have been stabilised and/or restored or sealed to the Council’s satisfaction.
A SWMP must be submitted and approved, prior to the commencement of work. The SWMP must be prepared in accordance with the Soil and Water Management on Building and Construction Sites fact sheets (Derwent Estuary Program, 2008), available here.
All work required by this condition must be undertaken in accordance with the approved SWMP.
Advice: Once the SWMP has been approved, the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement).
Where building approval is also required, it is recommended that documentation for condition endorsement be submitted well before submitting documentation for building approval. Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.
Reason for condition
To avoid the pollution and sedimentation of roads, drains and natural watercourses that could be caused by erosion and runoff from the development.
HER 6
Should any features or deposits of an archaeological nature be discovered on the site during excavation or disturbance:
1. All excavation and/or disturbance must stop immediately; and 2. A qualified archaeologist must be engaged to attend the site and provide advice and assessment of the features and/or deposits discovered and make recommendations on further excavation and/or disturbance; and 3. All and any recommendations made by the archaeologist engaged in accordance with (2) above must be complied with in full; and 4. All features and/or deposits discovered must be reported to the Council with one day of the discovery; and 5. A copy of the archaeologists advice, assessment and recommendations obtained in accordance with (2) above must be provided to the Council within seven days of receipt of the advice, assessment and recommendations.
Excavation and/or disturbance must not recommence unless and until approval is granted from the Council.
Reason for condition
To ensure that work is planned and implemented in a manner that seeks to understand, retain, protect, preserve and manage significant archaeological evidence.
ADVICE
The following advice is provided to you to assist in the implementation of the planning permit that has been issued subject to the conditions above. The advice is not exhaustive and you must inform yourself of any other legislation, bylaws, regulations, codes or standards that will apply to your development under which you may need to obtain an approval. Visit the Council's website for further information.
Prior to any commencement of work on the site or commencement of use the following additional permits/approval may be required from the Hobart City Council.
CONDITION ENDORSEMENT
If a condition endorsement is required by a planning condition above, you will need to submit the relevant documentation to satisfy the condition via the Condition Endorsement Submission on Council's online services eplanning
Where building approval is also required, it is recommended that documentation for condition endorsement be submitted well before submitting documentation for building approval. Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.
Once approved, the Council will respond to you via email that the condition has been endorsed (satisfied). Detailed instructions can be found here.
BUILDING PERMIT
You may need building approval in accordance with the Building Act 2016. Click here for more information.
This is a Discretionary Planning Permit issued in accordance with section 57 of the Land Use Planning and Approvals Act 1993.
PLUMBING PERMIT
You may need plumbing approval in accordance with the Building Act 2016, Building Regulations 2016 and the National Construction Code. Click here for more information.
STORM WATER
Please note that in addition to a building and/or plumbing permit, development must be in accordance with the Hobart City Council’s Hydraulic Services By law. Click here for more information.
STORM WATER / ROADS / ACCESS
Services to be designed and constructed in accordance with the (IPWEA) LGAT – standard drawings. Click here for more information.
WEED CONTROL
Effective measures are detailed in the Tasmanian Washdown Guidelines for Weed and Disease Control: Machinery, Vehicles and Equipment (Edition 1, 2004). The guidelines can be obtained from the Department of Primary Industries, Parks, Water and Environment website.
DIAL BEFORE YOU DIG
Click here for dial before you dig information. |
Delegation: Council
7.1.5 19 Lansdowne Crescent, West Hobart - Alterations to Car Park |
||||||||||||
HARVEY That the recommendation contained in the report of the Development Appraisal Planner and the Senior Statutory Planner of 2 January 2018, be adopted. |
||||||||||||
MOTION CARRIED VOTING RECORD
|
||||||||||||
COMMITTEE RESOLUTION: |
||||||||||||
Pursuant to the Hobart Interim Planning Scheme 2015, the Council approve the application for Alterations to Car Park at 19 Lansdowne Crescent, West Hobart for the reasons outlined in the officer’s report and a permit containing the following conditions be issued:
GEN
The use and/or development must be substantially in accordance with the documents and drawings that comprise PLN17686 19 LANSDOWNE CRESCENT TAS 7000 Final Planning Documents except where modified below.
Reason for condition
To clarify the scope of the permit.
ENG sw6
All stormwater from the proposed development (including but not limited to: roofed areas; agdrains; retaining wall agdrains; and impervious surfaces such as driveways and paved areas) must be drained to the Council’s stormwater infrastructure prior to commencement of use.
Reason for condition
To ensure that stormwater from the site will be discharged to a suitable Council approved outlet.
ENG 2a
Vehicular barriers compliant with the Australian Standard AS1170.1 must be installed to prevent vehicles running off the edge of an access driveway or parking module (parking spaces, aisles and manoeuvring area) where the drop from the edge of the trafficable area to a lower level is 600mm or greater, and wheel stops (kerb) must be installed for drops between 150mm and 600mm. Barriers must not limit the width of the driveway access or parking and turning areas approved under the permit.
Advice: Council does not consider a slope greater than 1 in 4 to constitute a lower level as described in AS/NZS 2890.1:2004 Section 2.4.5.3. Slopes greater than 1 in 4 will require a vehicular barrier or wheel stop.
Designers are advised to consult the National Construction Code 2016 to determine if pedestrian handrails or safety barriers compliant with the NCC2016 are also required.
Reason for condition
To ensure the safety of users of the access driveway and parking module and compliance with the standard.
ENG 5
The number of car parking spaces approved on the site for use, is sixteen (16).
All parking spaces must be delineated by means of white or yellow lines 80mm to 100mm wide, or white or yellow pavement markers in accordance with Australian Standards AS2890.1:2004, prior to commencement of use.
Reason for condition
To ensure the provision of parking for the use is safe and efficient.
ENG 9
All car parking spaces for people with disabilities must be delineated to Australian Standards AS2890.6:2009, prior to the commencement of the use.
Reason for condition
In the interests of vehicle user safety and the amenity of the development.
ENG 3
The access driveway and parking module (parking spaces, aisles and manoeuvring area) must be designed and constructed in accordance with Australian Standard AS/NZS2890.1:2004 (including the requirement for vehicle safety barriers where required).
Reason for condition
To ensure safety of users of the access and parking module, and compliance with the relevant Australian Standard.
ENG 1
The cost of repair of any damage to the Council's infrastructure resulting from the implementation of this permit, must be met by the owners within 30 days of the completion of the development or as otherwise determined by the Council.
A photographic record of the Council's infrastructure adjacent to the subject site must be provided to the Council prior to any commencement of works.
A photographic record of the Council’s infrastructure (e.g. existing property service connection points, roads, buildings, stormwater, footpaths, driveway crossovers and nature strips, including if any, preexisting damage) will be relied upon to establish the extent of damage caused to the Council’s infrastructure during construction. In the event that the owner/developer fails to provide to the Council a photographic record of the Council’s infrastructure, then any damage to the Council's infrastructure found on completion of works will be deemed to be the responsibility of the owner.
Reason for condition
To ensure that any of the Council's infrastructure and/or siterelated service connections affected by the proposal will be altered and/or reinstated at the owner’s full cost.
ENV 1
Sediment and erosion control measures sufficient to prevent sediment from leaving the site must be installed prior to any disturbance of the site, and maintained until all areas of disturbance have been stabilized or revegetated.
Advice: For further guidance in preparing a Soil and Water Management Plan – in accordance with Fact sheet 3 Derwent Estuary Program click here.
Reason for condition
To avoid the sedimentation of roads, drains, natural watercourses, Council land that could be caused by erosion and runoff from the development, and to comply with relevant State legislation.
ADVICE
The following advice is provided to you to assist in the implementation of the planning permit that has been issued subject to the conditions above. The advice is not exhaustive and you must inform yourself of any other legislation, bylaws, regulations, codes or standards that will apply to your development under which you may need to obtain an approval. Visit the Council's website for further information.
Prior to any commencement of work on the site or commencement of use the following additional permits/approval may be required from the Hobart City Council.
BUILDING PERMIT
Building permit in accordance with the Building Act 2016. Click here for more information.
This is a Discretionary Planning Permit issued pursuant to section 57 of the Land Use Planning and Approvals Act 1993.
PLUMBING PERMIT
Plumbing permit in accordance with the Building Act 2016, Building Regulations 2016 and the National Construction Code. Click here for more information.
WEED CONTROL
Effective measures are detailed in the Tasmanian Washdown Guidelines for Weed and Disease Control: Machinery, Vehicles and Equipment (Edition 1, 2004). The guidelines can be obtained from the Department of Primary Industries, Parks, Water and Environment website.
NOISE REGULATIONS
Click here for information with respect to noise nuisances in residential areas.
DIAL BEFORE YOU DIG
Click here for dial before you dig information.
|
Delegation: Council
7.1.6 6 Washington Street, South Hobart - Partial Demolition, Alterations, New Building for Public Toilets and Landscaping |
||||||||||||
RUZICKA That the recommendation contained in the report of the Development Appraisal Planner and the Senior Statutory Planner of 9 January 2018, be adopted with the following additional condition and advice added: PLN s1 Advice 1. The applicant is encouraged to give consideration to incorporating an appropriately located water “bubbler” for public use within the proposal.
|
||||||||||||
MOTION CARRIED VOTING RECORD
|
||||||||||||
COMMITTEE RESOLUTION: |
||||||||||||
That pursuant to the Hobart Interim Planning Scheme 2015, the Council approve the application for partial demolition, alterations, new building for public toilets and landscaping at 6 Washington Street, South Hobart for the reasons outlined in the officer’s report and a permit containing the following conditions be issued:
GEN
The use and/or development must be substantially in accordance with the documents and drawings that comprise PLN17928 6 WASHINGTON STREET SOUTH HOBART TAS 7004 Final Planning Documents except where modified below.
Reason for condition
To clarify the scope of the permit.
ENG sw6
All stormwater from the proposed development (including but not limited to: roofed areas; agdrains; retaining wall agdrains; and impervious surfaces such as driveways and paved areas) must be drained to the Council’s stormwater infrastructure prior to commencement of use.
Reason for condition
To ensure that stormwater from the site will be discharged to a suitable Council approved outlet.
ENG 1
The cost of repair of any damage to the Council's infrastructure resulting from the implementation of this permit, must be met by the owners within 30 days of the completion of the development or as otherwise determined by the Council.
A photographic record of the Council's infrastructure adjacent to the subject site must be provided to the Council prior to any commencement of works.
A photographic record of the Council’s infrastructure (e.g. existing property service connection points, roads, buildings, stormwater, footpaths, driveway crossovers and nature strips, including if any, preexisting damage) will be infrastructure during construction. In the event that the owner/developer fails to provide to the Council a photographic record of the Council’s infrastructure, then any damage to the Council's infrastructure found on completion of works will be deemed to be the responsibility of the owner.
Reason for condition
To ensure that any of the Council's infrastructure and/or siterelated service connections affected by the proposal will be altered and/or reinstated at the owner’s full cost.
ENV 1
Sediment and erosion control measures sufficient to prevent sediment from leaving the site must be installed prior to any disturbance of the site, and maintained until all areas of disturbance have been stabilized or revegetated.
Advice: For further guidance in preparing a Soil and Water Management Plan – in accordance with Fact sheet 3 Derwent Estuary Program click here.
Reason for condition
To avoid the sedimentation of roads, drains, natural watercourses, Council land that could be caused by erosion and runoff from the development, and to comply with relevant State legislation.
PLN s1
ADVICE
The following advice is provided to you to assist in the implementation of the planning permit that has been issued subject to the conditions above. The advice is not exhaustive and you must inform yourself of any other legislation, bylaws, regulations, codes or standards that will apply to your development under which you may need to obtain an approval. Visit the Council's website for further information.
Prior to any commencement of work on the site or commencement of use the following additional permits/approval may be required from the Hobart City Council.
BUILDING PERMIT
Building approval in accordance with the Building Act 2016. Click here for more information.
Discretionary Planning Permit issued in accordance with section 57 of the Land Use Planning and Approvals Act 1993.
PLUMBING PERMIT
Plumbing approval in accordance with the Building Act 2016, Building Regulations 2016 and the National Construction Code. Click here for more information.
WORK PLACE HEALTH AND SAFETY
Appropriate occupational health and safety measures must be employed during the works to minimise direct human exposure to potentiallycontaminated soil, water, dust and vapours. Click here for more information.
NOISE REGULATIONS
Click here for information with respect to noise nuisances in residential areas.
WASTE DISPOSAL
It is recommended that the developer liaise with the Council’s Cleansing and Solid Waste Unit regarding reducing, reusing and recycling materials associated with demolition on the site to minimise solid waste being directed to landfill.
Further information regarding waste disposal can also be found on the Council’s website.
FEES AND CHARGES
Click here for information on the Council's fees and charges.
DIAL BEFORE YOU DIG
Click here for dial before you dig information.
|
Delegation: Council
8 Reports
HARVEY That: 1. Aldermen Ruzicka, Burnet and Harvey be nominated to attend the Coast to Coast 2018 Hobart conference, with further nominations to be sought at the Council meeting on 22 January 2018. 2. The Council agree to the lead sponsor position of the coastal hazard management and climate adaptation program at the Coast to Coast 2018 Hobart conference for a maximum amount of $5,500. 3. The Council give further consideration of an additional sponsorship of “Field Excursion in partnership with the Derwent Estuary Program”. 4 The estimated cost of $995 per person be attributed to the general Aldermanic conferences allocation within the City Government function of the 2017-18 Annual Plan.
|
||||||||||||
MOTION CARRIED VOTING RECORD
|
||||||||||||
COMMITTEE RESOLUTION: |
||||||||||||
That: 1. Aldermen Ruzicka, Burnet and Harvey be nominated to attend the Coast to Coast 2018 Hobart conference, with further nominations to be sought at the Council meeting on 22 January 2018. 2. The Council agree to the lead sponsor position of the coastal hazard management and climate adaptation program at the Coast to Coast 2018 Hobart conference for a maximum amount of $5,500. 3. The Council give further consideration of an additional sponsorship of “Field Excursion in partnership with the Derwent Estuary Program”. 4 The estimated cost of $995 per person be attributed to the general Aldermanic conferences allocation within the City Government function of the 2017-18 Annual Plan. |
Delegation: Council
BURNET That: 1. The recommendations of the report, contained in Attachment A to item 8.2 of the Open City Planning Committee agenda of 15 January 2018, be endorsed. 2. The Council refer all major planning applications as defined under the Terms of Reference to the Urban Design Advisory Panel post lodgement of a planning application and if so agree to the terms of reference for the Panel to be further amended to ensure that such advice is strictly limited to the relevant urban design provisions of the planning scheme applicable for the site. 3. An invitation, at an appropriate time, to attend a future City Planning Committee meeting, be forwarded to members of the Urban Design Advisory Panel for the purpose of informing the Committee about the role and function of the Panel. |
||||||||||||
MOTION CARRIED VOTING RECORD
|
||||||||||||
COMMITTEE RESOLUTION: |
||||||||||||
That: 1. The recommendations of the report, contained in Attachment A to item 8.2 of the Open City Planning Committee agenda of 15 January 2018, be endorsed. 2. The Council refer all major planning applications as defined under the Terms of Reference to the Urban Design Advisory Panel post lodgement of a planning application and if so agree to the terms of reference for the Panel to be further amended to ensure that such advice is strictly limited to the relevant urban design provisions of the planning scheme applicable for the site. 3. An invitation at an appropriate time to attend a future City Planning Committee meeting be forwarded to members of the Urban Design Advisory Panel for the purpose of informing the Committee about the role and function of the Panel.
|
Delegation: Council
BURNET That the recommendation contained in the report of the Director City Planning of 9 January 2018, be adopted. |
||||||||||||
MOTION CARRIED VOTING RECORD
|
||||||||||||
COMMITTEE RESOLUTION: |
||||||||||||
That the information contained in the memorandum, titled “City Planning Advertising List”, to item 8.3 of the Open City Planning Committee agenda of 15 January 2018, be received and noted. |
Delegation: Committee
HARVEY That the recommendation contained in the report of the Director City Planning of 4 January 2018, be adopted. |
||||||||||||
MOTION CARRIED VOTING RECORD
|
||||||||||||
COMMITTEE RESOLUTION: |
||||||||||||
That the information contained in the memorandum, titled “Delegated Decisions Report (Planning)”, to item 8.4 of the Open City Planning Committee agenda of 15 January 2018, be received and noted. |
Delegation: Committee
Mr Brian Corr, President of Hobart Not Highrise, addressed the Committee in relation to item 8.5
8.5 Major Projects Legislation - Amendments Following Initial Consultation |
||||||||||
That the recommendation contained in the report of the Manager Planning Policy & Heritage and Director City Planning of 4 January 2018, be adopted. |
||||||||||
MOTION CARRIED VOTING RECORD
|
||||||||||
COMMITTEE RESOLUTION: |
||||||||||
That: 1. The Tasmanian Government be advised that the City of Hobart sees no need for the draft Bill to amend the Land Use Planning and Approvals Act 1993 (LUPAA) and the Environmental Management and Pollution Control Act 1994 to introduce a new major projects assessment process. 2. In the event that the Tasmanian Government proceeds with the Land Use Planning and Approvals Amendment (Major Projects) Bill 2017 that the following comments be considered: (i) The key issue identified with the Bill is in relation to the eligibility criteria for declaration of major projects and the fact that they are open to a wide interpretation based on the opinion of the Minister. (ii) The eligibility criteria uses the term ‘significant’, ‘significance’ or ‘potentially significant’ in relation to 4 of the 5 criteria. The draft Bill does not contain any definition of ‘significant’, leaving these criteria open to wide interpretation. This creates uncertainty around what is likely to be a major project and there would be benefit in making these criteria more specific in order to provide both project proponents and the wider community with greater certainty. (iii) Subsection 60J 2(b) provides that a project warrants declaration as a major project if, in the opinion of the Minister the determination by a planning authority of an application for a permit in relation to the project has been unreasonably delayed. It is not clear why this provision is required given the existing legislative provisions in relation to timeframes for making decisions on permit applications.
|
Delegation: Council
Item 7.1.3 was then taken.
9 Committee Action Status Report
BURNET |
||||||||||||
That the information be received and noted.
|
||||||||||||
MOTION CARRIED VOTING RECORD
|
Delegation: Committee
Regulation 29(3) Local Government
(Meeting Procedures) Regulations 2015.
File Ref: 13-1-10
10.1 Condition Surrounding Sediment and Erosion Control
File Ref: F17/151528; 13-1-10
Report of the Director City Planning of 15 January 2018.
HARVEY
That the information be received and noted.
|
||||||||||||
MOTION CARRIED VOTING RECORD
|
Delegation: Committee
Section 29 of the Local Government (Meeting Procedures) Regulations 2015.
File Ref: 13-1-10
No questions were asked at the meeting.
The following items were discussed:-
Item No. 1 Minutes of the last meeting of the Closed Portion of the Council Meeting Item No. 2 Consideration of supplementary items to the agenda Item No. 3 Indications of pecuniary and conflicts of interest Item No. 4 Planning Authority Items – Consideration of Items with Deputations Item No. 5 City Acting as Planning Authority Item No. 6 Committee Action Status Report Item No. 6.1 Committee Actions - Status Report LG(MP)R 15(2)(d) Item No. 7 Questions without notice – File Ref: 13-1-10
|
||||||||||||
BURNET That the items be noted. |
||||||||||||
MOTION CARRIED VOTING RECORD
|
The Chairman adjourned the meeting at 6:38 pm to conduct the closed portion of the meeting.
The meeting reconvened at 6:40 pm.
Item 12 was then taken.
There being no further business the meeting closed at 6:41pm.
TAKEN AS READ AND SIGNED AS A CORRECT RECORD
THIS
29th DAY OF January 2018.
CHAIRMAN