MINUTES
City Planning Committee Meeting
Open Portion
Monday, 30 November 2020 at 5:00pm
|
Minutes (Open Portion) City Planning Committee Meeting |
Page 2 |
|
30/11/2020 |
|
APOLOGIES AND LEAVE OF ABSENCE
1. Co-Option of a Committee Member in the event of a vacancy
3. Consideration of Supplementary Items
4. Indications of Pecuniary and Conflicts of Interest
6. Planning Authority Items - Consideration of Items with Deputations
7. Committee Acting as Planning Authority
7.1 Applications under the Hobart Interim Planning Scheme 2015
8.1 New Delegations Required Due to Amendments to Planning Legislation
8.2 Delegated Decisions Report (Planning)
8.3 City Planning - Advertising Report
9. Committee Action Status Report
9.1 Committee Actions - Status Report
10. Responses to Questions without Notice
12. Closed Portion of the Meeting
Applications under the Hobart Interim Planning Scheme 2015
13. 32 and 30 Romilly Street, South Hobart and Adjacent Rivulet and Adjacent Road Reserve
|
Minutes (Open Portion) City Planning Committee Meeting |
Page 7 |
|
30/11/2020 |
|
City Planning Committee Meeting (Open Portion) held on Monday, 30 November 2020 at 5:00 pm in the Council Chamber, Town Hall.
COMMITTEE MEMBERS Deputy Lord Mayor Burnet (Chairman) Briscoe Harvey Behrakis Dutta Coats
PRESENT: Councillor H Burnet (Chairman), Alderman J R Briscoe, Councillor W F Harvey, Alderman S Behrakis, Councillors M Dutta and W Coats.
APOLOGIES: Nil.
LEAVE OF ABSENCE: Nil.
|
NON-MEMBERS Lord Mayor Reynolds Zucco Sexton Thomas Ewin Sherlock
The Deputy Lord Mayor declared an interest in item 7.1.5, vacated the Chair and left the meeting at 5.03pm, returning at 5.04pm.
Councillor Harvey declared an interest in item 7.1.5 and left the meeting at 5.03pm, returning at 5.04pm.
Alderman Behrakis Chaired the meeting for item 7.1.5.
Alderman Behrakis left the meeting at 5.37pm, returning at 5.39pm and retired from the meeting at 6.10pm during the discussion of supplementary item 13. Alderman Behrakis was present for items 1 to 7 and item 7.1.5.
Councillor Coats retired from the meeting at 6.53pm after voting on Part A of supplementary item 13. Councillor Coats was present for items 1 to 7 and item 7.1.5.
|
No Elected Members were co-opted to the Committee.
HARVEY
|
||||||||||||||
The minutes of the Open Portion of the City Planning Committee meeting held on Monday, 16 November 2020 and the Special City Planning Committee meeting held on Monday, 23 November 2020, be confirmed as an accurate record. |
||||||||||||||
MOTION CARRIED VOTING RECORD
|
The minutes were signed.
Ref: Part 2, Regulation 8(6) of the Local Government (Meeting Procedures) Regulations 2015.
That the Committee resolve to deal with any supplementary items not appearing on the agenda, as reported by the General Manager. |
||||||||||||||
MOTION CARRIED VOTING RECORD
|
Ref: Part 2, Regulation 8(7) of the Local Government (Meeting Procedures) Regulations 2015.
Members of the Committee are requested to indicate where they may have any pecuniary or conflicts of interest in respect to any matter appearing on the agenda, or any supplementary item to the agenda, which the Committee has resolved to deal with.
The following interest was indicated:
1. Deputy Lord Mayor Burnet - item 7.1.5
2. Councillor Harvey - item 7.1.5
Regulation 15 of the Local Government (Meeting Procedures) Regulations 2015.
A Committee may close a part of a meeting to the public where a matter to be discussed falls within 15(2) of the above regulations.
In the event that the Committee transfer an item to the closed portion, the reasons for doing so should be stated.
Are there any items which should be transferred from this agenda to the closed portion of the agenda, or from the closed to the open portion of the agenda?
BEHRAKIS
That item 7.1.5 be taken first followed by supplementary item 13.
MOTION CARRIED
VOTING RECORD
AYES |
NOES |
Deputy Lord Mayor Burnet |
|
Briscoe |
|
Harvey |
|
Behrakis |
|
Dutta |
|
Coats |
|
In accordance with the requirements of Part 2 Regulation 8(3) of the Local Government (Meeting Procedures) Regulations 2015, the General Manager is to arrange the agenda so that the planning authority items are sequential.
In accordance with Part 2 Regulation 8(4) of the Local Government (Meeting Procedures) Regulations 2015, the Committee by simple majority may change the order of any of the items listed on the agenda, but in the case of planning items they must still be considered sequentially – in other words they still have to be dealt with as a single group on the agenda.
Where deputations are to be received in respect to planning items, past practice has been to move consideration of these items to the beginning of the meeting.
BRISCOE
That in accordance with Regulation 8(4) of the Local Government (Meeting Procedures) Regulations 2015, the Committee resolve to deal with any items which have deputations by members of the public regarding any planning matter listed on the agenda, to be taken out of sequence in order to deal with deputations at the beginning of the meeting.
MOTION CARRIED
VOTING RECORD
AYES |
NOES |
Deputy Lord Mayor Burnet |
|
Briscoe |
|
Harvey |
|
Behrakis |
|
Dutta |
|
Coats |
|
|
Minutes (Open Portion) City Planning Committee Meeting |
Page 78 |
|
30/11/2020 |
|
In accordance with the provisions of Part 2 Regulation 25 of the Local Government (Meeting Procedures) Regulations 2015, the intention of the Committee to act as a planning authority pursuant to the Land Use Planning and Approvals Act 1993 is to be noted.
In accordance with Regulation 25, the Committee will act as a planning authority in respect to those matters appearing under this heading on the agenda, inclusive of any supplementary items.
The Committee is reminded that in order to comply with Regulation 25(2), the General Manager is to ensure that the reasons for a decision by a Council or Council Committee acting as a planning authority are recorded in the minutes.
Item 7.1.5 was then taken.
7.1 Applications under the Hobart Interim Planning Scheme 2015
7.1.1 130 Murray Street, 125 Bathurst Street, Hobart - Partial Demolition and New Building for Seven Multiple Dwellings and Food Services |
||||||||||
DUTTA |
||||||||||
That the recommendation contained in the report of the Development Appraisal Planner and the Senior Statutory Planner of 23 November 2020, be adopted. |
||||||||||
MOTION CARRIED VOTING RECORD
|
||||||||||
COMMITTEE RESOLUTION: |
||||||||||
That pursuant to the Hobart Interim Planning Scheme 2015, the Council approve the application for partial demolition and new building for seven multiple dwellings and food services at 130 Murray Street and 125 Bathurst Street, Hobart for the reasons outlined in the officer’s report attached to item 7.1.1 of the Open City Planning Committee agenda of 30 November 2020 and a permit containing the following conditions be issued:
GEN
The use and/or development must be substantially in accordance with the documents and drawings that comprise PLN20238 130 MURRAY STREET HOBART TAS 7000 Final Planning Documents except where modified below.
Reason for condition
To clarify the scope of the permit.
TW
The use and/or development must comply with the requirements of TasWater as detailed in the form Submission to Planning Authority Notice, Reference No. TWDA 2020/01223HCC dated 16 October 2020 as attached to the permit.
Reason for condition
To clarify the scope of the permit.
PLN s1
The palette of exterior colours, finishes and materials must be provided. The palette of exterior colours, finishes and materials should address the following:
1. Consideration of providing additional windows and/or other design elements on the exposed south eastern side of the building, in order to relieve its ‘blankness’. 2. Consideration of the potential for some of the balconies facing Murray Street to gain ‘sideways’ views down that street towards the river. 3. Consideration of introducing more natural light into the restaurant from the planted garden zone above. 4. The outward appearance of the screened carpark to be made more recessive. 5. Reflect the palette of materials within the local streetscape.
Prior to the issue of any approval under the Building Act 2016 (excluding for demolition), revised plans, and montages and samples where appropriate, must be submitted and approved to the satisfaction of the Director City Planning showing exterior colours and materials in accordance with the above requirement.
All work required by this condition must be undertaken in accordance with the approved revised plans, montages and samples.
Reason for condition
In the interest of the streetscape and townscape values of the surrounding area.
PLN s2
A Landscaping Plan prepared by a suitably qualified person for the landscaped spaces, private open space areas and other areas of planting around the site must be submitted and approved by the Council’s Director City Planning prior to the issue of any consent under the Building Act 2016, excluding for demolition.
The Landscaping Plan must include (in addition to that already proposed):
1. Consideration of deep planting boxes on the first floor balcony off the car park level, to encourage an element of softness on the building façade and enable the planting to be more successful over time. 2. Exploration of further opportunities for landscaping generally, including (but not limited to) incorporating it into the apartment entry.
All trees and landscaping must be planted and installed in accordance with the approved Landscaping Plan to the satisfaction of the Council's Director City Planning prior to commencement of use.
The trees and landscaping must be maintained, and replacement trees and landscaping in accordance with the approved Landscaping Plan must be planted if any is lost.
Confirmation by the person who prepared the landscaping plan (or an equivalent suitably qualified person) that the landscaping has been completed in accordance with the approved landscaping plan must be submitted to the Council to the satisfaction of the Director City Planning, prior to commencement of use. Once this has been received, and all landscaping shown on the approved Landscaping Plan has been planted in accordance with the approved plan to the satisfaction of the Council's Director City Planning, the Council will issue a statement confirming satisfactory planting of all trees and landscaping.
Reason for condition
To ensure that the development achieves a high standard of public amenity and to ensure appropriate landscaping close to the property boundary.
ENG 12
A construction waste management plan must be implemented throughout construction.
A construction waste management plan must be submitted and approved, prior to commencement of work on the site. The construction waste management plan must include:
1. Provisions for commercial waste services for the handling, storage, transport and disposal of postconstruction solid waste and recycle bins from the development; and 2. Provisions for the handling, transport and disposal of demolition material, including any contaminated waste and recycling opportunities, to satisfy the above requirement.
All work required by this condition must be undertaken in accordance with the approved construction waste management plan.
Advice:
Once the construction waste management plan has been approved, the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement).
Where building approval is also required, it is recommended that documentation for condition endorsement be submitted well before submitting documentation for building approval. Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.
It is recommended that the developer liaise with the Council’s Cleansing and Solid Waste Unit regarding reducing, reusing and recycling materials associated with demolition on the site to minimise solid waste being directed to landfill. Further information can also be found on the Council’s website.
Reason for condition
To ensure that solid waste management from the site meets the Council’s requirements and standards.
ENG sw1
All stormwater from the proposed development (including but not limited to: roofed areas, ag drains, retaining wall ag drains and impervious surfaces such as driveways and paved areas) must be drained to the Council’s stormwater infrastructure prior to first occupation or commencement of use (whichever occurs first).
Reason for condition
To ensure that stormwater from the site will be discharged to a suitable Council approved outlet.
ENG sw4
The new stormwater connection must be constructed and existing abandoned connections sealed by the Council at the owner’s expense, prior to the first occupation. Under the Urban Drainage Act 2013, a single stormwater connection at the lowest practicable point is allowed.
Detailed engineering drawings must be submitted and approved, prior to the issuing of any approval under the Building Act 2016 or commencement of works (whichever occurs first). The detailed engineering drawings must include:
1. the location of the proposed connection; and 2. the size of the connection appropriate to satisfy the needs of the development. The Council standard for the kerb and gutter connection is 150*75*5 or 250*75*5 mm galvanized RHS
All work required by this condition must be undertaken in accordance with the approved detailed engineering drawings.
Advice: The applicant is advised to submit detailed design drawings via the City Amenity Division’s application for a new stormwater connection. If detailed design to satisfy this condition is submitted via the planning condition endorsement process there may be fees associated with the assessment, and once approved the applicant will still need to submit an application for a new stormwater connection with the City Amenity Division.
Where building / plumbing approval is also required, it is recommended that documentation to satisfy this condition is submitted well before submitting documentation for building/plumbing approval. Failure to address planning condition requirements prior to submitting for building/plumbing approval may result in unexpected delays.
Reason for condition
To ensure the site is drained adequately.
ENG sw7
Stormwater pre treatment for stormwater discharges from the development must be installed prior to commencement of use.
A stormwater management report and design must be submitted and approved, prior to the issuing of any approval under the Building Act 2016 or commencement of works (whichever occurs first). The stormwater management report and design must:
1. be prepared by a suitably qualified person; and 2. include detailed design of the proposed treatment train, including final estimations of contaminant removal.
All work required by this condition must be undertaken in accordance with the approved report.
Advice:
Once the report and design has been approved Council will issue a condition endorsement (see general advice on how to obtain condition endorsement).
Where building approval is also required, it is recommended that documentation for condition endorsement be submitted well before submitting documentation for building approval. Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.
Reason for condition
To avoid the possible pollution of drainage systems and natural watercourses, and to comply with relevant State legislation.
ENG 13
An ongoing waste management plan for all commercial and domestic waste and recycling must be implemented post construction.
A waste management plan must be submitted and approved, prior to the issue of any approvals under the Building Act 2016. The waste management plan must:
1. Include provisions for private waste services for the handling, storage, transport and disposal of domestic and commercial waste and recycle bins from the development.
All work required by this condition must be undertaken in accordance with the approved waste management plan.
Advice:
If the waste management plan for the development relies on Council waste collection from the kerb, approval from the Council's Solid Waste Services Division must be obtained and provided in the documentation submitted to satisfy this condition. Approval and issue of this planning permit does not imply or guarantee that the Council can or will provide waste collection services for this development.
Advice and permission should be sought from the Road Authority that administers the Burnett Street highway reservation with respect to private collection from the road carriageway.
Once the waste management plan has been approved the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement).
Where building approval is also required, it is recommended that documentation for condition endorsement be submitted well before submitting documentation for building approval. Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.
Reason for condition
To ensure that solid waste management from the site meets the Council’s requirements and standards.
ENG tr2
A construction traffic and parking management plan must be implemented prior to the commencement of work on the site (including demolition).
The construction traffic (including cars, public transport vehicles, service vehicles, pedestrians and cyclists) and parking management plan must be submitted and approved, prior to commencement work (including demolition). The construction traffic and parking management plan must:
1. Be prepared by a suitably qualified person. 2. Develop a communications plan to advise the wider community of the traffic and parking impacts during construction. 3. Include a start date and finish dates of various stages of works. 4. Include times that trucks and other traffic associated with the works will be allowed to operate. 5. Nominate a superintendent, or the like, to advise the Council of the progress of works in relation to the traffic and parking management with regular meetings during the works.
All work required by this condition must be undertaken in accordance with the approved construction traffic and parking management plan.
Advice:
Once the construction traffic and parking management plan has been approved, the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement).
Where building approval is also required, it is recommended that documentation for condition endorsement be submitted well before submitting documentation for building approval. Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.
Reason for condition
To ensure the safety of vehicles entering and leaving the development and the safety and access around the development site for the general public and adjacent businesses.
ENG 3a
The access driveway, circulation roadways, ramps and parking module (parking spaces, aisles and manoeuvring area) must be designed and constructed in accordance with Australian Standard AS/NZS 2890.1:2004 (including the requirement for vehicle safety barriers where required), or a Council approved alternate design certified by a suitably qualified engineer to provide a safe and efficient access, and enable safe, easy and efficient use.
Reason for condition
To ensure the safety of users of the access and parking module, and compliance with the relevant Australian Standard.
ENG 3b
The access driveway, circulation roadways, ramps and parking module (parking spaces, aisles and manoeuvring area) design must be submitted and approved, prior to the commencement of work or issuing of any approval under the Building Act 2016 (whichever occurs first).
The access driveway, circulation roadways, ramps and parking module (parking spaces, aisles and manoeuvring area) design must:
1. Be prepared and certified by a suitably qualified engineer; 2. Incorporate all measures
recommended in the traffic impact statement by Midson Traffic Pty Ltd and
dated 1st September 2020 including: · An electronic warning and vehicle priority system that ensures that the waiting vehicle is the exiting vehicle only (to prevent vehicles from propping in the highway reservation); · A speed hump located immediately within the access adjacent to the Bathurst Street highway reservation boundary; and · Signage on the building walls adjacent to the footpath (on the private side) alerting pedestrians to the presence of the access. 3. Include design certification from Midson Traffic Pty Ltd for all aspects relating to item 2 (above); 4. Be generally in accordance with the Australian Standard AS/NZS2890.1:2004; 5. Where the design deviates from AS/NZS2890.1:2004 the designer must demonstrate that the design will provide a safe and efficient access, and enable safe, easy and efficient use; and 6. Show dimensions, levels, gradients and transitions, and other details as Council deem necessary to satisfy the above requirement.
Advice:
Once the design has been approved, the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement) Where building approval is also required, it is recommended that documentation for condition endorsement be submitted well before submitting documentation for building approval. Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.
Reason for condition
To ensure the safety of users of the access and parking module, and compliance with the relevant Australian Standard.
ENG 3c
The access driveway and parking module (parking spaces, aisles and manoeuvring area), including the turntable, stackers, and electronic vehicle warning and priority system, must be constructed in accordance with all plans approved and endorsed under this permit.
Prior to the first occupation or commencement of use (whichever occurs first), documentation by a suitably qualified engineer certifying that the access driveway and parking module (parking spaces, aisles and manoeuvring area), including the turntable, stackers, and electronic vehicle warning and priority system, has been constructed in accordance with the above drawings must be lodged with the Council.
Advice:
Certification must be submitted to Council for condition endorsement (see general advice on how to obtain condition endorsement)
Reason for condition
To ensure the safety of users of the access and parking module, and compliance with the relevant Australian Standard.
ENG 4
The access driveway and parking module (car parking spaces, aisles and manoeuvring area) approved by this permit must be constructed to a sealed standard (spray seal, asphalt, concrete, pavers or equivalent Council approved) and surface drained to the Council's stormwater infrastructure prior to the first occupation or commencement of use (whichever occurs first) .
Reason for condition
To ensure the safety of users of the access driveway and parking module, and that it does not detract from the amenity of users, adjoining occupiers or the environment by preventing dust, mud and sediment transport.
ENG 5
The maximum number of car parking spaces approved on the site, for use is seven (7).
Reason for condition
To ensure the provision of parking for the use is safe and efficient.
ENG 8
The use of the car parking spaces is restricted to User Class 1A (residential) in accordance with Australian Standards AS/NZS 2890.1 2004 Table 1.1.
A sign, approved by council, and in accordance with Australian Standards AS/NZS 1742.11:2016, must be erected at the entry of the parking access to indicate the parking area is for residents only prior to first occupation or commencement of use (whichever occurs first).
Reason for condition
In the interests of vehicle user safety and the amenity of the development.
ENG 1
Any damage to council infrastructure resulting from the implementation of this permit, must, at the discretion of the Council:
1. Be met by the owner by way of reimbursement (cost of repair and reinstatement to be paid by the owner to the Council); or 2. Be repaired and reinstated by the owner to the satisfaction of the 1. Council.
A photographic record of the Council's infrastructure adjacent to the subject site must be provided to the Council prior to any commencement of works.
A photographic record of the Council’s infrastructure (e.g. existing property service connection points, roads, buildings, stormwater, footpaths, driveway crossovers and nature strips, including if any, preexisting damage) will be relied upon to establish the extent of damage caused to the Council’s infrastructure during construction. In the event that the owner/developer fails to provide to the Council a photographic record of the Council’s infrastructure, then any damage to the Council's infrastructure found on completion of works will be deemed to be the responsibility of the owner.
Reason for condition
To ensure that any of the Council's infrastructure and/or siterelated service connections affected by the proposal will be altered and/or reinstated at the owner’s full cost.
ENG r3
Prior to the first occupation or commencement of use (whichever occurs first), the redundant driveway crossover in the Murray Street highway reservation must be removed, and the kerb and channel reinstated in accordance with TSDR15v2 – Concrete Kerbs and Channels Type KC.
Reason for condition
To ensure that the access to a road will comply with the requirements of the road authority.
ENV 2
An approved Demolition and Construction Environmental Management Plan, prepared by suitably qualified persons, must be implemented.
A Demolition and Construction Environmental Management Plan must be submitted and approved prior to the commencement of works and prior to the issue of any approval under the Building Act 2016.
The plan must include, but is not limited to, the following:
1. Details of the proposed demolition and construction methodology and expected likely timeframes. 2. The proposed days and hours of work and proposed hours of activities likely to generate significant noise emissions (including volume and timing of heavy vehicles entering and leaving the site). 3. Details of potential environmental impacts associated with the development works including noise, vibration, erosion and pollution (air, land and water). 4. Details of proposed measures to avoid or mitigate to acceptable levels all identified potential environmental impacts during development works including, but not limited to:
a. A
noise and vibration management plan including, but not limited to: i. identification of potentially noisy or vibrationcausing construction activities; ii. measures to ensure that all reasonable and feasible noise and vibration mitigation measures are applied during operation of the demolition and construction management plan; and iii. details of monitoring measures and triggers for corrective actions.
b. A
soil and water management plan including: i. measures to minimise erosion and the discharge of contaminated stormwater offsite; ii. measures to minimise dust emissions from the site; and
iii. measures to prevent soil and debris being carried onto the street.
5. Details of proposed responsible persons, public communication protocols, compliance, recording and auditing procedures and complaint handling and response procedures.
The approved Demolition and Construction Environmental Management Plan forms part of this permit and must be complied with.
Advice:
Once the plan has been approved the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement).
Reason for condition
To minimise the potential for environmental impacts from the construction works.
HER 9
All construction documentation must contain protocols and recommendations for all contractors working in close proximity to the stone wall along the boundary of 126 Murray Street to be familiar with the heritage values of the heritage listed site and for the need to protect the wall at all costs whilst undertaking the proposed works to upgrade infrastructure.
Prior to the commencement of works (including demolition and excavation), all workers and managers must be briefed on the importance of the cultural heritage values of the site as part of a site induction. This must be undertaken by a suitably qualified heritage practitioner.
Documents containing protocols for the protection of the wall must be submitted and approved, prior to the issuing of any approval under the Building Act 2016 or commencement of works (whichever occurs first).
Reason for condition
To ensure that there is no loss or damage to the heritage values or fabric of the site.
HER 10
The soffits of the balconies on the primary facade must be timber.
Prior to the issue of any approval under the Building Act 2016, revised plans must be submitted and approved showing timber soffits in accordance with the above requirement.
All work required by this condition must be undertaken in accordance with the approved revised plans.
Reason for condition
To ensure that materials and finishes are sympathetic to an adjacent listed place and do not result in the loss of historic cultural heritage values.
ADVICE
The following advice is provided to you to assist in the implementation of the planning permit that has been issued subject to the conditions above. The advice is not exhaustive and you must inform yourself of any other legislation, bylaws, regulations, codes or standards that will apply to your development under which you may need to obtain an approval. Visit the Council's website for further information.
Prior to any commencement of work on the site or commencement of use the following additional permits/approval may be required from the Hobart City Council.
CONDITION ENDORSEMENT ENGINEERING
All engineering drawings required to be submitted and approved by this planning permit must be submitted to the City of Hobart as a CEP (Condition Endorsement) via the City’s Online Service Development Portal. When lodging a CEP, please reference the PLN number of the associated Planning Application. Each CEP must also include an estimation of the cost of works shown on the submitted engineering drawings. Once that estimation has been confirmed by the City’s Engineer, the following fees are payable for each CEP submitted and must be paid prior to the City of Hobart commencing assessment of the engineering drawings in each CEP:
Value of Building Works Approved by Planning Permit Fee: Up to $20,000: $150 per application. Over $20,000: 2% of the value of the works as assessed by the City's Engineer per assessment.
These fees are additional to building and plumbing fees charged under the Building and Plumbing Regulations.
Once the CEP is lodged via the Online Service Development Portal, if the value of building works approved by your planning permit is over $20,000, please contact the City’s Development Engineer on 6238 2715 to confirm the estimation of the cost of works shown on the submitted engineering drawings has been accepted.
Once confirmed, pleased call one of the City’s Customer Service Officers on 6238 2190 to make payment, quoting the reference number (ie. CEP number) of the Condition Endorsement you have lodged. Once payment is made, your engineering drawings will be assessed.
BUILDING PERMIT
You may need building approval in accordance with the Building Act 2016. Click here for more information.
This is a Discretionary Planning Permit issued in accordance with section 57 of the Land Use Planning and Approvals Act 1993.
PLUMBING PERMIT
You may need plumbing approval in accordance with the Building Act 2016, Building Regulations 2016 and the National Construction Code. Click here for more information.
NEW SERVICE CONNECTION
Please contact the Hobart City Council's City Amenity Division to initiate the application process for your new stormwater connection.
STORMWATER
Please note that in addition to a building and/or plumbing permit, development must be in accordance with the Hobart City Council’s Infrastructure By law. Click here for more information.
STRUCTURES CLOSE TO COUNCILS' STORMWATER MAIN
Council records suggest thirdparty or shared private pipes pass along the Right of Way. The design of works (including altered levels in the ROW) must provide protection for any thirdparty or shared private pipes passing through the Lot. You may need separate consent from Council's Development Compliance Unit under section 73 of the Building Act 2016.
WORK WITHIN THE HIGHWAY RESERVATION
Please note development must be in accordance with the Hobart City Council’s Infrastructure By law. Click here for more information.
CBD AND HIGH VOLUME FOOTPATH CLOSURES
Please note that the City of Hobart does not support the extended closure of public footpaths or roads to facilitate construction on adjacent land.
It is the developer's responsibility to ensure that the proposal as designed can be constructed without reliance on such extended closures.
In special cases, where it can be demonstrated that closure of footpaths in the CBD and/or other high volume footpaths can occur for extended periods without unreasonable impact on other businesses or the general public, such closures may only be approved by the full Council.
For more information about this requirement please contact the Council's Traffic Engineering Unit on 6238 2804.
REDUNDANT CROSSOVERS
Redundant crossovers are required to be reinstated under the Hobart City Council’s Infrastructure By law. Click here for more information.
STORMWATER / ROADS / ACCESS
Services to be designed and constructed in accordance with the (IPWEA) LGAT – standard drawings. Click here for more information.
RIGHT OF WAY
The private right of way must not be reduced, restricted or impeded in any way, and all beneficiaries must have complete and unrestricted access at all times.
You should inform yourself as to your rights and responsibilities in respect to the private right of way particularly reducing, restricting or impeding the right during and after construction.
NOISE REGULATIONS
Click here for information with respect to noise nuisances in residential areas.
WASTE DISPOSAL
It is recommended that the developer liaise with the Council’s Cleansing and Solid Waste Unit regarding reducing, reusing and recycling materials associated with demolition on the site to minimise solid waste being directed to landfill.
Further information regarding waste disposal can also be found on the Council’s website.
FEES AND CHARGES
Click here for information on the Council's fees and charges.
DIAL BEFORE YOU DIG
Click here for dial before you dig information.
|
Delegation: Council
7.1.2 21 Carr Street, 19 Carr Street, 386 Argyle Street, North Hobart and Adjacent Road Reserve - Subdivision (One Additional Lot) |
||||||||||
BRISCOE |
||||||||||
That the recommendation contained in the report of the Development Appraisal Planner and the Senior Statutory Planner of 23 November 2020, be adopted. |
||||||||||
MOTION CARRIED VOTING RECORD
|
||||||||||
COMMITTEE RESOLUTION: |
||||||||||
That pursuant to the Hobart Interim Planning Scheme 2015, the City Planning Committee, in accordance with the delegations contained in its terms of reference, approve the application for a subdivision (one additional lot) at 21 Carr Street, 19 Carr Street, 386 Argyle Street, and adjacent road reserve for the reasons outlined in the officer’s report attached to item 7.1.2 of the Open City Planning Committee agenda of 30 November 2020 and a permit containing the following conditions be issued:
GEN
The use and/or development must be substantially in accordance with the documents and drawings that comprise PLN19496 21 CARR STREET & 19 CARR STREET & 386 ARGYLE STREET NORTH HOBART TAS 7000 & ADJACENT ROAD RESERVE Final Planning Documents except where modified below.
Reason for condition
To clarify the scope of the permit.
TW
The use and/or development must comply with the requirements of TasWater as detailed in the form Submission to Planning Authority Notice, Reference No. TWDA2019/01173HCC dated 19/10/2020 as attached to the permit.
Reason for condition
To clarify the scope of the permit.
ENG sw1
All stormwater from the proposed development (including but not limited to: roofed areas, ag drains, and impervious surfaces such as driveways and paved areas) must be drained to the Council’s stormwater infrastructure prior to sealing of the final plan.
Advice:
Under section 23 of the Urban Drainage Act 2013 it is an offence for a property owner to direct stormwater onto a neighbouring property.
Reason for condition
To ensure that stormwater from the site will be discharged to a suitable Council approved outlet.
ENG sw3
The proposed main must be designed and installed to maximise access for its installation and maintenance, given the existing and proposed structures adjacent to and across it.
The detailed design drawings required under ENG14 prior to commencement of works must:
1. Demonstrate how the overland flow path will be provided, prevent nuisance soakage from the main and trenching, provide adequate access to the main, impose no loads onto the main and that the structures will be fully independent of the main and its trenching. 2. Include multiple crosssections clearly showing the relationship both vertically and horizontally between the Council’s stormwater infrastructure and the structures (including footings and overhangs) and boundaries, and stating the minimum setbacks from the works to the nearest external surface of the main. 3. Include a longsection of Council's stormwater main clearly showing proposed cover. If the cover is less than 600mm, engineering details and full calculations to relevant Australian standards (including construction traffic loading) must be submitted to demonstrate the mains can withstand the likely forces and will be adequately protected. All assumptions must be stated. 4. Include a Construction Management Plan detailing any required alterations to the structures (eg underpinning) and methodology for both construction and future maintenance to protect existing and proposed structures. 5. Be certified by a suitably qualified engineer
All work required by this condition must be undertaken in accordance with the approved detailed design.
Advice:
Council's preference is for shallow mains where access is limited (where practicable).
The applicant is required submit detailed design documentation to satisfy this condition via the Council's planning condition endorsement process (noting there is a fee associated with condition endorsement approval of engineering drawings [see general advice on how to obtain condition endorsement and for fees and charges]). This is a separate process to any building approval under the Building Act 2016.
Failure to address condition requirements prior to submitting for building approval may result in unexpected delays.
Reason for condition
To ensure the protection of the Council’s hydraulic infrastructure.
ENG 3a
The access driveway, circulation roadways, ramps and manoeuvring area must be designed and constructed in accordance with Australian Standard AS/NZS2890.1:2004 (including the requirement for vehicle safety barriers where required), or a Council approved alternate design certified by a suitably qualified engineer to provide a safe and efficient access, and enable safe, easy and efficient use.
Advice:
It is advised that designers consider the detailed design of the access and parking module prior to finalising the Finished Floor Level (FFL) of the parking spaces (especially if located within a garage incorporated into the dwelling), as failure to do so may result in difficulty complying with this condition.
Reason for condition
To ensure the safety of users of the access and parking module, and compliance with the relevant Australian Standard.
ENG 3b
The access driveway, circulation roadways, ramps and manoeuvring area design must be submitted and approved, prior to the commencement of work.
The access driveway, circulation roadways, ramps and manoeuvring area design must:
1. Be prepared and certified by a suitably qualified engineer, 2. Be generally in accordance with the Australian Standard AS/NZS 2890.1:2004, 3. Where the design deviates from AS/NZS 2890.1:2004 the designer must demonstrate that the design will provide a safe and efficient access, and enable safe, easy and efficient use, and 4. Show dimensions, levels, gradients and transitions, and other details as Council deem necessary to satisfy the above requirement.
Advice:
Once the design has been approved, the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement)
Reason for condition
To ensure the safety of users of the access and parking module, and compliance with the relevant Australian Standard.
ENG 3c
The access driveway, circulation roadways, ramps and manoeuvring area must be constructed in accordance with the design drawings approved by Condition ENG 3b.
Prior to the first occupation / commencement of use, documentation by a suitably qualified engineer certifying that the access driveway and parking module has been constructed in accordance with the above drawings must be lodged with the Council.
Advice:
Certification may be submitted to Council as part of the Building Act 2016 approval process or via condition endorsement (see general advice on how to obtain condition endorsement)
Reason for condition
To ensure the safety of users of the access and parking module, and compliance with the relevant Australian Standard.
ENG 4
The access driveway and parking module (car parking spaces, aisles and manoeuvring area) approved by this permit must be constructed to a sealed standard (spray seal, asphalt, concrete, pavers or equivalent Council approved) and surface drained to the Council's stormwater infrastructure prior upon completion.
Reason for condition
To ensure the safety of users of the access driveway and parking module, and that it does not detract from the amenity of users, adjoining occupiers or the environment by preventing dust, mud and sediment transport.
ENG 1
Any damage to council infrastructure resulting from the implementation of this permit, must, at the discretion of the Council:
1. Be met by the owner by way of reimbursement (cost of repair and reinstatement to be paid by the owner to the Council); or 2. Be repaired and reinstated by the owner to the satisfaction of the Council.
A photographic record of the Council's infrastructure adjacent to the subject site must be provided to the Council prior to any commencement of works.
A photographic record of the Council’s infrastructure (e.g. existing property service connection points, roads, buildings, stormwater, footpaths, driveway crossovers and nature strips, including if any, preexisting damage) will be relied upon to establish the extent of damage caused to the Council’s infrastructure during construction. In the event that the owner/developer fails to provide to the Council a photographic record of the Council’s infrastructure, then any damage to the Council's infrastructure found on completion of works will be deemed to be the responsibility of the owner.
Reason for condition
To ensure that any of the Council's infrastructure and/or siterelated service connections affected by the proposal will be altered and/or reinstated at the owner’s full cost.
ENV 2
Sediment and erosion control measures sufficient to prevent sediment leaving the site and in accordance with an approved soil and water management plan (SWMP), must be installed prior to the commencement of work and maintained until such time as all disturbed areas have been stabilised and/or restored or sealed to the Council’s satisfaction.
A SWMP must be submitted prior to the issue of any approval under the Building Act 2016 or the commencement of work, whichever occurs first. The SWMP must be prepared in accordance with the Soil and Water Management on Building and Construction Sites fact sheets (Derwent Estuary Program, 2008), available here.
All work required by this condition must be undertaken in accordance with the approved SWMP.
Advice:
Once the SWMP has been approved, the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement).
Where building approval is also required, it is recommended that documentation for condition endorsement be submitted well before submitting documentation for building approval. Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.
Reason for condition
To avoid the pollution and sedimentation of roads, drains and natural watercourses that could be caused by erosion and runoff from the development.
SURV 1
The applicant must submit to the Council a copy of the surveyor’s survey notes at the time of lodging the final plan.
Reason for condition
To enable the Council to accurately update cadastral layers on the corporate Geographic Information System.
SURV 2
The final plan and schedule of easements must be submitted and approved in accordance with section 89 of the Local Government (Building & Miscellaneous Provisions) Act 1993.
Reason for condition
To ensure that the subdivision/boundary adjustment is carried out in accordance with the Council's requirements under the provisions of Part 3 of the Local Government (Building & Miscellaneous Provisions) Act 1993.
SURV 3
The final plan and schedule of easements must be submitted and approved under section 89 of the Local Government (Building & Miscellaneous Provisions) Act 1993.
The final plan and schedule of easements must provide easements to the satisfaction of the Council:
1. Over any proposed or existing stormwater or sewer mains passing through the lots on the final plan and the property at 386 Argyle Street (CT 51563/1, in favour of the Hobart City Council and/orTasWater (minimum width of 2m, or 3m (where possible) if they cover two pipes). 2. Over any existing or proposed private rights of way or service easements in favour of the lots they are required to serve.
3. A Right of Carriageway in favour of Lot 1 over the hardstand area within the property at 386 Argyle Street is required to allow a vehicle to turn at the end of the driveway within Lot 1 as shown on PDA Surveyors B85 Vehicle Tracking Path plan 4302HC15.
Reason for condition
To ensure that there are no impediments to the provision of public and private services and access to the lots.
ENG 14
Access and services to each lot must be designed and installed to meet the needs of future development, prior to the sealing of the final plan or commencement of the use (whichever occurs first).
Detailed engineering drawings must be submitted and approved prior to the commencement of work on the site. The drawings must be certified by a suitably qualified and experienced engineer and must:
1. be generally in accordance with Local Government Association of Tasmania: Tasmanian Municipal Standard Drawings (May 2020), as varied by the Council’s published departures from those Drawings, and Tasmanian Subdivision Guidelines (October 2013); 2. clearly distinguish between public and private infrastructure; 3. show the final lot boundaries, with each lot serviced separately by Council infrastructure and all private plumbing contained within each lot; 4. include a branch to 19 Carr Street to separate surface drainage from Lot 1; 5. show the proposed location and size of each lot connection such that the majority of the lot, including the driveway, can be efficiently drained via gravity; 6. show all stormwater from the existing and proposed development (including but not limited to: roofed areas, ag drains, and impervious surfaces such as driveways and paved areas) drained to Council stormwater infrastructure with sufficient receiving capacity;
7. show the location of all existing connections and thirdparty private services passing through the lots; 8. show in plan, crosssection and longsection the proposed stormwater infrastructure, including but not limited to, connections, flows, velocities, hydraulic grade lines, clearances from structures, boundaries and other services, cover, gradients, sizing, material, pipe class, easements and inspection openings; and 9. include the associated calculations and catchment area plans. The stormwater system (including defined overland flow paths) must cater for all 1% AEP at 2100 event (i.e including climate change loading) from a fully developed future catchment. The main itself must be sized to accommodate at least the 5% AEP flows from a fullydeveloped catchment. Fullydeveloped is to be taken as the maximum permitted under the planning scheme, unless demonstrated to be unsuitable.
A structural condition assessment and visual record of the new public infrastructure must be submitted prior to issue of practical completion.
All work required by this condition must be constructed in accordance with the approved engineering drawings.
Advice:
Council notes that the catchment for sizing the proposed mains extension should also include 17 Carr Street.
Once the engineering drawings have been approved the Council will issue a condition endorsement.
Please note that once the condition endorsement has been issued you will need to contact the Council’s City Amenity Division to obtain a Permit to Construct Public Infrastructure and an application for new stormwater connection.
Reason for condition
To ensure that the subdivision of land provides adequate services to meet the projected needs of future development.
ENG15
The driveway associated with the shared right of way access must be designed and constructed to a sealed standard prior to the sealing of titles.
Design drawings must be submitted and approved, prior to commencement of work. The design drawing must:
1. be in accordance with the Australian Standard Parking facilities, Part 1: OffStreet Carparking, AS 2890.1 – 2004, or ensure safe access; and 2. be prepared and certified by a suitable qualified professional.
All work required by this condition must be undertaken in accordance with the approved design drawings.
Advice:
Once the design drawing has been approved the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement).
Reason for condition
To ensure that the driveway for the development is constructed to ensure public safety standards.
ENG 16
Prior to the sealing of the final plan, private sewer, stormwater (including surface runoff) and water services/connections are to be entirely separate to each lot and contained wholly within the lots served.
Reason for condition
To ensure that each lot is services separately.
ENG 17
Prior to the sealing of the final plan, the developer must verify compliance with condition ENG 16 by supplying the Council with an asinstalled services plan clearly indicating the location and details of all relevant services (entirely contained within their respective lots or appropriate easements). The as installed services plan must be accompanied by certification from a suitably qualified person that all engineering work required by this permit has been completed.
Advice:
Any final plan submitted for sealing will not be processed unless it is accompanied by documentation by a suitably qualified person that clearly certifies that this condition has been satisfied and that all the work required by this condition has been completed. A 'suitably qualified person' must be a professional engineer or professional surveyor or other persons acceptable to the Council.
Reason for condition
To ensure that the developer provides the Council with clear written confirmation that the separation of services is complete.
OPS 1
The owner must pay a cash contribution to the Council for contribution to public open space, prior to sealing of the final plan.
The open space contribution is equal to 5% of the undeveloped value of Lot 1 in the final plan, in lieu of the provision of public open space within the subdivision.
Advice:
The value is to be determined by a registered valuer commissioned by the Council at the developer's cost. Please contact the Council's Development Appraisal Unit on 6238 2715 to instigate the valuation process.
Reason for condition
Approval of the subdivision will create further demand upon Hobart's Public Open Space System. The funds obtained will be used for future expenditure on the purchase or improvement of land for public open space in Hobart.
ADVICE
The following advice is provided to you to assist in the implementation of the planning permit that has been issued subject to the conditions above. The advice is not exhaustive and you must inform yourself of any other legislation, bylaws, regulations, codes or standards that will apply to your development under which you may need to obtain an approval. Visit the Council's website for further information.
Prior to any commencement of work on the site or commencement of use the following additional permits/approval may be required from the Hobart City Council.
CONDITION ENDORSEMENT ENGINEERING
All engineering drawings required to be submitted and approved by this planning permit must be submitted to the City of Hobart as a CEP (Condition Endorsement) via the City’s Online Service Development Portal. When lodging a CEP, please reference the PLN number of the associated Planning Application. Each CEP must also include an estimation of the cost of works shown on the submitted engineering drawings. Once that estimation has been confirmed by the City’s Engineer, the following fees are payable for each CEP submitted and must be paid prior to the City of Hobart commencing assessment of the engineering drawings in each CEP:
Value of Building Works Approved by Planning Permit Fee:
Up to $20,000: $150 per application. Over $20,000: 2% of the value of the works as assessed by the City's Engineer per assessment.
These fees are additional to building and plumbing fees charged under the Building and Plumbing Regulations.
Once the CEP is lodged via the Online Service Development Portal, if the value of building works approved by your planning permit is over $20,000, please contact the City’s Development Engineer on 6238 2715 to confirm the estimation of the cost of works shown on the submitted engineering drawings has been accepted.
Once confirmed, pleased call one of the City’s Customer Service Officers on 6238 2190 to make payment, quoting the reference number (ie. CEP number) of the Condition Endorsement you have lodged. Once payment is made, your engineering drawings will be assessed.
PLUMBING PERMIT
You may need plumbing approval in accordance with the Building Act 2016, Building Regulations 2016 and the National Construction Code. Click here for more information.
OCCUPATION OF THE PUBLIC HIGHWAY
You may require a permit for the occupation of the public highway for construction or special event (e.g. placement of skip bin, crane, scissor lift etc). Click here for more information.
You may require an occupational license for structures in the Hobart City Council highway reservation, in accordance with conditions to be established by the Council. Click here for more information.
You may require a road closure permit for construction or special event. Click here for more information.
You may require a Permit to Open Up and Temporarily Occupy a Highway (for work in the road reserve). Click here for more information.
GENERAL EXEMPTION (TEMPORARY) PARKING PERMITS
You may qualify for a General Exemption permit for construction vehicles i.e. residential or meter parking/loading zones. Click here for more information.
PERMIT TO CONSTRUCT PUBLIC INFRASTRUCTURE
You will require a permit to construct public infrastructure. A 12 month maintenance period, bond and CCTV will be required. Please contact the Hobart City Council's City Amenity Division to initiate the permit process.
NEW SERVICE CONNECTION
Please contact the Hobart City Council's City Amenity Division to initiate the application process for your new stormwater connection.
STORMWATER
Please note that in addition to a building and/or plumbing permit, development must be in accordance with the Hobart City Council’s Infrastructure By law. Click here for more information.
STRUCTURES CLOSE TO COUNCILS' STORMWATER MAIN
The design of structures (including footings) must provide protection for the Council’s infrastructure. For information regarding appropriate designs please contact the Council's City Amenity Division. You may need the General Manager's consent under section 13 of the Urban Drainage Ace 2013 and consent under section 73 of the Building Act 2016.
WORK WITHIN THE HIGHWAY RESERVATION
Please note development must be in accordance with the Hobart City Council’s Infrastructure By law. Click here for more information.
DRIVEWAY SURFACING OVER HIGHWAY RESERVATION
If a coloured or textured surface is used for the driveway access within the Highway Reservation, the Council or other service provider will not match this on any reinstatement of the driveway access within the Highway Reservation required in the future.
RIGHT OF WAY
The private right of way must not be reduced, restricted or impeded in any way, and all beneficiaries must have complete and unrestricted access at all times.
You should inform yourself as to your rights and responsibilities in respect to the private right of way particularly reducing, restricting or impeding the right during and after construction.
WASTE DISPOSAL
It is recommended that the developer liaise with the Council’s Cleansing and Solid Waste Unit regarding reducing, reusing and recycling materials associated with demolition on the site to minimise solid waste being directed to landfill.
Further information regarding waste disposal can also be found on the Council’s website.
FEES AND CHARGES
Click here for information on the Council's fees and charges.
DIAL BEFORE YOU DIG
Click here for dial before you dig information.
SUBDIVISION ADVICE
For information regarding standards and guidelines for subdivision works click here. All conditions imposed by this permit are in accordance with the Local Government Building & Miscellaneous Provisions) Act 1993 and the Conveyancing and Law of Property Act 1884.
PUBLIC OPEN SPACE CASH IN LIEU VALUATION
Please contact the Council's Development Appraisal Unit on 6238 2715 to instigate the valuation process.
|
Delegation: Committee
7.1.3 2 Evelyn Crescent, Sandy Bay and Adjacent Road Reserve - Two Multiple Dwellings (One Existing, One New) Carparking and Associated Works |
||||||||||
BRISCOE |
||||||||||
That the recommendation contained in the report of the Development Appraisal Planner and the Senior Statutory Planner of 24 November 2020, be adopted. |
||||||||||
MOTION CARRIED VOTING RECORD
|
||||||||||
COMMITTEE RESOLUTION: |
||||||||||
That pursuant to the Hobart Interim Planning Scheme 2015, the City Planning Committee, in accordance with the delegations contained in its terms of reference, approve the application for two multiple dwellings (one existing, one new), car parking, and associated works at 2 Evelyn Crescent, Sandy Bay, for the reasons outlined in the officer’s report attached to item 7.1.3 of the Open City Planning Committee agenda of 30 November 2020 and a permit containing the following conditions be issued:
GEN
The use and/or development must be substantially in accordance with the documents and drawings that comprise PLN18230 2 EVELYN CRESCENT SANDY BAY TAS 7005 Final Planning Documents except where modified below.
Reason for condition
To clarify the scope of the permit.
TW
The use and/or development must comply with the requirements of TasWater as detailed in the form Submission to Planning Authority Notice, Reference No. TWDA 2018/00654HCC dated 30/9/2020 as attached to the permit.
Reason for condition
To clarify the scope of the permit.
PLN 1
Either:
(a) Screening must be installed and maintained along the sections of retaining wall at the edge of the shared driveway that are adjacent to the windows to the bedrooms on the western side of the existing dwelling. The screening must have a height equivalent to 1.7m above the floor level of the bedrooms, a uniform transparency of no more than 25%, and must extend the full width of the respective window. The screening must be installed prior to first use of the shared driveway.
or,
(b) The windows to the bedrooms on the western side of the existing dwelling must be replaced with windows that are less likely to admit vehicle noise and vehicle light intrusion. Any replacement windows may have a reduced glazed area, double glazing, or other features which will reduce the admission of light and noise into the bedrooms. The replaced windows must be installed prior to first use of the shared driveway.
Any plans submitted for building approval for the development must demonstrate likely compliance with this condition.
Advice:
If screening is to be provided as per the above option a) and the existing bedroom windows are to be retained, it is not considered necessary to install frosted glass in the windows.
Reason for condition
To provide reasonable opportunity for privacy for dwellings.
PLN 2
Screening with a uniform transparency no more than 25% and a minimum height of 1.5m above finished surface level, must be installed and maintained along the northern edge of the car parking spaces approved at the northwest corner of the site, prior to the first occupation.
Prior to the issue of any approval under the Building Act 2016, revised plans must be submitted and approved showing screening in accordance with the above requirement.
All work required by this condition must be undertaken in accordance with the approved revised plans.
Reason for condition
To provide reasonable opportunity for privacy for dwellings.
PLN 3
A storage area, for waste and recycling bins, with an area of at least 1.5 m² per dwelling must be provided for the exclusive use of each dwelling. The storage areas must be screened from the property frontage.
Any plans submitted for building approval for the development must demonstrate likely compliance with this condition.
Reason for condition
To provide for the storage of waste and recycling bins for multiple dwellings.
PLN s2
The dwelling approved at the rear of the site must be provided with an area of Private Open Space (POS) that:
· has a minimum area of 24m², · receives a minimum of three hours of sunlight to 50% of its total area upon 21 June, · has a gradient no steeper than 1 in 10, and, · has a difference in level from the ground floor of the dwelling of no greater than one metre.
Any plans submitted for building approval for the development must demonstrate likely compliance with this condition. The POS required by this condition must be provided prior to occupation of the above dwelling.
Advice:
The developer should consult with TasWater if any additional structures (such as retaining walls for example) are required adjacent to its infrastructure in order to satisfy this condition.
Reason for condition
To provide:
a) for outdoor recreation and the operational needs of residents; and b) opportunities for the planting of gardens and landscaping; and c) private open space that is integrated with the living areas of the dwelling; and d) private open space that has access to sunlight.
ENG sw1
All stormwater from the proposed development (including but not limited to: roofed areas, ag drains, retaining wall ag drains and impervious surfaces such as driveways and paved areas) must be drained to the Council’s stormwater infrastructure prior to first occupation or commencement of use (whichever occurs first).
Advice:
Under section 23 of the Urban Drainage Act 2013 it is an offence for a property owner to direct stormwater onto a neighbouring property.
Reason for condition
To ensure that stormwater from the site will be discharged to a suitable Council approved outlet.
ENG 2a
Prior to first occupation or commencement of use (whichever occurs first), vehicular barriers compliant with the Australian Standard AS/NZS 1170.1:2002 must be installed to prevent vehicles running off the edge of an access driveway or parking module (parking spaces, aisles and manoeuvring area) where the drop from the edge of the trafficable area to a lower level is 600mm or greater, and wheel stops (kerb) must be installed for drops between 150mm and 600mm. Barriers must not limit the width of the driveway access or parking and turning areas approved under the permit.
Advice:
The Council does not consider a slope greater than 1 in 4 to constitute a lower level as described in AS/NZS 2890.1:2004 Section 2.4.5.3. Slopes greater than 1 in 4 will require a vehicular barrier or wheel stop.
Designers are advised to consult the National Construction Code 2016 to determine if pedestrian handrails or safety barriers compliant with the NCC2016 are also required in the parking module this area may be considered as a path of access to a building.
Reason for condition
To ensure the safety of users of the access driveway and parking module and compliance with the standard.
ENG 2b
Prior to the issue of any approval under the Building Act 2016 or the commencement of works on site (whichever occurs first), a certified vehicle barrier design (including site plan with proposed location(s) of installation) prepared by a suitably qualified engineer, compliant with Australian Standard AS/NZS 1170.1:2002, must be submitted to Council.
Advice:
If the development's building approval includes the need for a Building Permit from Council, the applicant is advised to submit detailed design of vehicular barrier as part of the Building Application.
If the development's building approval is covered under Notifiable Work the applicant is advised to submit detailed design of vehicular barrier as a condition endorsement of the planning permit condition. Once the certification has been accepted, the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement).
Reason for condition
To ensure the safety of users of the access driveway and parking module and compliance with the standard.
ENG 2c
Prior to the commencement of use, vehicular barriers must be inspected by a qualified engineer and certification submitted to the Council confirming that the installed vehicular barriers comply with the certified design and Australian Standard AS/NZS 1170.1:2002.
Advice:
Certification may be submitted to the Council as part of the Building Act 2016 approval process or via condition endorsement (see general advice on how to obtain condition endorsement).
Reason for condition
To ensure the safety of users of the access driveway and parking module and compliance with the relevant standards.
ENG 3a
The access driveway, and parking module (parking spaces, aisles and manoeuvring area) must be designed and constructed in accordance with Australian Standard AS/NZS 2890.1:2004 (including the requirement for vehicle safety barriers where required), or a Council approved alternate design certified by a suitably qualified engineer to provide a safe and efficient access, and enable safe, easy and efficient use.
Advice:
It is advised that designers consider the detailed design of the access and parking module prior to finalising the Finished Floor Level (FFL) of the parking spaces (especially if located within a garage incorporated into the dwelling), as failure to do so may result in difficulty complying with this condition.
Reason for condition
To ensure the safety of users of the access and parking module, and compliance with the relevant Australian Standard.
ENG 3c
The access driveway, and parking module (parking spaces, aisles and manoeuvring area) must be constructed in accordance with the drawings approved by this planning permit.
Prior to the commencement of use, documentation by a suitably qualified engineer certifying that the access driveway and parking module has been constructed in accordance with the above drawings must be lodged with Council.
Advice:
Certification may be submitted to Council as part of the Building Act 2016 approval process or via condition endorsement (see general advice on how to obtain condition endorsement)
Reason for condition
To ensure the safety of users of the access and parking module, and compliance with the relevant Australian Standard.
ENG 4
The access driveway and parking module (car parking spaces, aisles and manoeuvring area) approved by this permit must be constructed to a sealed standard (spray seal, asphalt, concrete, pavers or equivalent Council approved) and surface drained to the Council's stormwater infrastructure prior to the commencement of use.
Reason for condition
To ensure the safety of users of the access driveway and parking module, and that it does not detract from the amenity of users, adjoining occupiers or the environment by preventing dust, mud and sediment transport.
ENG 1
Any damage to council infrastructure resulting from the implementation of this permit, must, at the discretion of the Council:
1. Be met by the owner by way of reimbursement (cost of repair and reinstatement to be paid by the owner to the Council); or 2. Be repaired and reinstated by the owner to the satisfaction of the Council.
A photographic record of the Council's infrastructure adjacent to the subject site must be provided to the Council prior to any commencement of works.
A photographic record of the Council’s infrastructure (e.g. existing property service connection points, roads, buildings, stormwater, footpaths, driveway crossovers and nature strips, including if any, preexisting damage) will be relied upon to establish the extent of damage caused to the Council’s infrastructure during construction. In the event that the owner/developer fails to provide to the Council a photographic record of the Council’s infrastructure, then any damage to the Council's infrastructure found on completion of works will be deemed to be the responsibility of the owner.
Reason for condition
To ensure that any of the Council's infrastructure and/or siterelated service connections affected by the proposal will be altered and/or reinstated at the owner’s full cost.
ENV 1
Sediment and erosion control measures sufficient to prevent sediment from leaving the site must be installed prior to any disturbance of the site, and maintained until all areas of disturbance have been stabilized or revegetated.
Advice:
For further guidance in preparing a Soil and Water Management Plan – in accordance with Fact sheet 3 Derwent Estuary Program click here.
Reason for condition
To avoid the sedimentation of roads, drains, natural watercourses, Council land that could be caused by erosion and runoff from the development, and to comply with relevant State legislation.
ADVICE
The following advice is provided to you to assist in the implementation of the planning permit that has been issued subject to the conditions above. The advice is not exhaustive and you must inform yourself of any other legislation, bylaws, regulations, codes or standards that will apply to your development under which you may need to obtain an approval. Visit the Council's website for further information.
Prior to any commencement of work on the site or commencement of use the following additional permits/approval may be required from the Hobart City Council.
CONDITION ENDORSEMENT ENGINEERING
All engineering drawings required to be submitted and approved by this planning permit must be submitted to the City of Hobart as a CEP (Condition Endorsement) via the City’s Online Service Development Portal. When lodging a CEP, please reference the PLN number of the associated Planning Application. Each CEP must also include an estimation of the cost of works shown on the submitted engineering drawings. Once that estimation has been confirmed by the City’s Engineer, the following fees are payable for each CEP submitted and must be paid prior to the City of Hobart commencing assessment of the engineering drawings in each CEP:
Value of Building Works Approved by Planning Permit Fee: Up to $20,000: $150 per application. Over $20,000: 2% of the value of the works as assessed by the City's Engineer per assessment.
These fees are additional to building and plumbing fees charged under the Building and Plumbing Regulations.
Once the CEP is lodged via the Online Service Development Portal, if the value of building works approved by your planning permit is over $20,000, please contact the City’s Development Engineer on 6238 2715 to confirm the estimation of the cost of works shown on the submitted engineering drawings has been accepted.
Once confirmed, pleased call one of the City’s Customer Service Officers on 6238 2190 to make payment, quoting the reference number (ie. CEP number) of the Condition Endorsement you have lodged. Once payment is made, your engineering drawings will be assessed.
BUILDING PERMIT
You may need building approval in accordance with the Building Act 2016. Click here for more information.
This is a Discretionary Planning Permit issued in accordance with section 57 of the Land Use Planning and Approvals Act 1993.
PLUMBING PERMIT
You may need plumbing approval in accordance with the Building Act 2016, Building Regulations 2016 and the National Construction Code. Click here for more information.
OCCUPATION OF THE PUBLIC HIGHWAY
You may require a Permit to Open Up and Temporarily Occupy a Highway (for work in the road reserve). Click here for more information.
STORMWATER
Please note that in addition to a building and/or plumbing permit, development must be in accordance with the Hobart City Council’s Infrastructure By law. Click here for more information.
WORK WITHIN THE HIGHWAY RESERVATION
Please note development must be in accordance with the Hobart City Council’s Infrastructure By law. Click here for more information.
DRIVEWAY SURFACING OVER HIGHWAY RESERVATION
If a coloured or textured surface is used for the driveway access within the Highway Reservation, the Council or other service provider will not match this on any reinstatement of the driveway access within the Highway Reservation required in the future.
ACCESS
Designed in accordance with LGAT IPWEA – Tasmanian standard drawings. Click here for more information.
CROSS OVER CONSTRUCTION
The construction of the crossover can be undertaken by the Council or by a private contractor, subject to Council approval of the design. Click here for more information.
FEES AND CHARGES
Click here for information on the Council's fees and charges.
DIAL BEFORE YOU DIG
Click here for dial before you dig information.
|
Delegation: Committee
Item 8.1 was then taken.
Denis McLoughlin and Cassie Midgley (Representors), Frazer Read, Glenn Evans and Phil McMahon (Applicant) addressed the Committee in relation to item 7.1.4
7.1.4 139 Elizabeth Street, 40 Melville Street, 44 Melville Street, Hobart and Adjacent Road Reserve - Demolition, New Pedestrian Link, Landscaping and Associated Works |
||||||||||
HARVEY |
||||||||||
That the recommendation contained in the report of the Development Appraisal Planner and the Senior Statutory Planner of 24 November 2020, be adopted. |
||||||||||
MOTION CARRIED VOTING RECORD
|
||||||||||
COMMITTEE RESOLUTION: |
||||||||||
That pursuant to the Hobart Interim Planning Scheme 2015, the City Planning Committee, in accordance with the delegations contained in its terms of reference, approve the application for demolition, new pedestrian link, landscaping and associated works at 139 Elizabeth Street,40 and 44 Melville Street Hobart and adjacent road reserve for the reasons outlined in the officer’s report attached to item 7.1.4 of the Open City Planning Committee agenda of 30 November 2020 and a permit containing the following conditions be issued:
GEN
The use and/or development must be substantially in accordance with the documents and drawings that comprise PLN20289 139 ELIZABETH STREET HOBART TAS 7000 Final Planning Documents except where modified below.
Reason for condition
To clarify the scope of the permit.
PLN s1
More details are required of the hard and soft landscaping for the laneway, including the proposed materials for construction and the species of each tree.
Prior to the issue of any approval under the Building Act 2016 (excluding demolition and excavation), plans must be submitted and approved to the satisfaction of the Director City Planning in accordance with the above requirement.
All work in relation to this condition must be undertaken in accordance with the approved revised plans implemented prior to the use of the space.
Reason for condition
In the interest of the amenity of the space.
PLN s2
A lighting plan for the laneway must be implemented.
Prior to the issue of any approval under the Building Act 2016 (excluding demolition and excavation), a lighting plan must be submitted and approved to the satisfaction of the Director City Planning in accordance with the above requirement.
All work required by this condition must be undertaken in accordance with the approved lighting plan implemented prior to the use of the space.
Reason for condition
In the interest of the amenity of the space.
ENG 12
A construction waste management plan must be implemented throughout construction.
A construction waste management plan must be submitted and approved, prior to commencement of work on the site. The construction waste management plan must include:
1. Provisions for commercial waste services for the handling, storage, transport and disposal of postconstruction solid waste and recycle bins from the development; and 2. Provisions for the handling, transport and disposal of demolition material, including any contaminated waste and recycling opportunities, to satisfy the above requirement.
All work required by this condition must be undertaken in accordance with the approved construction waste management plan.
Advice:
Once the construction waste management plan has been approved, the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement).
Where building approval is also required, it is recommended that documentation for condition endorsement be submitted well before submitting documentation for building approval. Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.
It is recommended that the developer liaise with the Council’s Cleansing and Solid Waste Unit regarding reducing, reusing and recycling materials associated with demolition on the site to minimise solid waste being directed to landfill. Further information can also be found on the Council’s website.
Reason for condition
To ensure that solid waste management from the site meets the Council’s requirements and standards.
ENG sw4
Prior to occupancy or the commencement of the use (whichever occurs first), any new stormwater connection required must be constructed and existing redundant connection(s) be abandoned and sealed at the owner’s expense.
Prior to the issuing of any approval under the Building Act 2016 or commencement of works (whichever occurs first), detailed engineering drawings must be submitted via the Council’s online request form which is available on its website and approved. The detailed engineering drawings must include:
1. the location of the proposed connections and all existing connections. 2. the size and design of the connection such that it is appropriate to safely service the development. 3. longsections of the proposed connection clearly showing clearances from any nearby services, cover, grade, size, material and delineation of public and private infrastructure. 4. connections which are freeflowing gravity driven.
All work required by this condition must be undertaken and maintained in accordance with the approved detailed engineering drawings.
Advice:
Council notes the proposed connection is oversized for the proposed discharge and catchment. The connection is approved under this application for flows from 139 Elizabeth only. Detention would be required should additional catchments be discharged to this connection in the future.
Once the engineering drawings have been approved, the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement). Once approved the applicant will need to submit an application for a new stormwater connection with Council's City Amenity Division. Should the applicant wish to have their contractor install the connection, an Application to Construct Public Infrastructure is required.
The stormwater service connection may be required to have been approved prior to any plumbing permits being issued for private plumbing works.
Reason for condition
To ensure the site is drained adequately.
ENG tr2
A construction traffic and parking management plan must be implemented prior to the commencement of work on the site (including demolition).
The construction traffic (including cars, public transport vehicles, service vehicles, pedestrians and cyclists) and parking management plan must be submitted and approved, prior to commencement work (including demolition). The construction traffic and parking management plan must:
1. Be prepared by a suitably qualified person. 2. Develop a communications plan to advise the wider community of the traffic and parking impacts during construction. 3. Include a start date and finish dates of various stages of works. 4. Include times that trucks and other traffic associated with the works will be allowed to operate. 5. Nominate a superintendent, or the like, to advise the Council of the progress of works in relation to the traffic and parking management with regular meetings during the works.
All work required by this condition must be undertaken in accordance with the approved construction traffic and parking management plan.
Advice:
Once the construction traffic and parking management plan has been approved, the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement).
Where building approval is also required, it is recommended that documentation for condition endorsement be submitted well before submitting documentation for building approval. Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.
Reason for condition
To ensure the safety of vehicles entering and leaving the development and the safety and access around the development site for the general public and adjacent businesses.
ENG 1
Any damage to council infrastructure resulting from the implementation of this permit, must, at the discretion of the Council:
1. Be met by the owner by way of reimbursement (cost of repair and reinstatement to be paid by the owner to the Council); or 2. Be repaired and reinstated by the owner to the satisfaction of the Council.
Any damage must be reported to Council immediately.
A photographic record of the Council's infrastructure adjacent to the subject site must be provided to the Council prior to any commencement of works.
A photographic record of the Council’s infrastructure (e.g. existing property service connection points, roads, buildings, stormwater, footpaths, driveway crossovers and nature strips, including if any, preexisting damage) will be relied upon to establish the extent of damage caused to the Council’s infrastructure during construction. In the event that the owner/developer fails to provide to the Council a photographic record of the Council’s infrastructure, then any damage to the Council's infrastructure found on completion of works will be deemed to be the responsibility of the owner.
Reason for condition
To ensure that any of the Council's infrastructure and/or siterelated service connections affected by the proposal will be altered and/or reinstated at the owner’s full cost.
ENG s1
No works within the Melville Street road reservation have been approved by this permit. All notations on the plans referring to these works must be removed from any plans submitted for approval prior to the issue of any permit under the Building Act 2016.
Reason for condition
To clarify the scope of the permit.
ENV 2
Sediment and erosion control measures, sufficient to prevent sediment leaving the site and in accordance with an approved soil and water management plan (SWMP), must be installed prior to the commencement of work and maintained until such time as all disturbed areas have been stabilised and/or restored or sealed to the Council’s satisfaction.
A SWMP must be submitted prior to the issue of any approval under the Building Act 2016 or the commencement of work, whichever occurs first. The SWMP must be prepared in accordance with the Soil and Water Management on Building and Construction Sites fact sheets (Derwent Estuary Program, 2008), available here.
All work required by this condition must be undertaken in accordance with the approved SWMP.
Advice:
Once the SWMP has been approved, the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement).
Where building approval is also required, it is recommended that documentation for condition endorsement be submitted well before submitting documentation for building approval. Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.
Reason for condition
To avoid the pollution and sedimentation of roads, drains and natural watercourses that could be caused by erosion and runoff from the development.
HER s1
The recommendations contained within the Statements of Historical Archaeological Potential prepared by Brad Williams of Praxis Environment (March 2020) are to be implemented in full. Namely –
1. Prior to the issue of any approval under the Building Act 2016, a detailed demolition and construction management plan giving clear instruction as to avoiding impact upon the adjacent heritage building(s) must be submitted and approved. All work required by this condition must be undertaken in accordance with the approved documentation.
Advice:
Note a demolition management plan is required under condition ENVHE 2. The above requirement could form part of that document.
Reason for condition
To ensure that demolition effecting parts of a heritage listed place does not result in the loss of historic cultural heritage values in compliance with E13.7.1 Demolition.
HER s2
The recommendations contained within the Statements of Historical Archaeological Potential prepared by Brad Williams of Praxis Environment (March 2020) are to be implemented in full. Namely –
1. All works of excavation must comply with the archaeological method statement in full as set out within the Statements of Historical Archaeological Potential prepared by Brad Williams of Praxis Environment, dated October 2019.
Reason for condition
To ensure that work is planned, implemented and subject to review in a manner that seeks to understand, retain, protect, preserve and manage significant archaeological evidence in compliance with E13.10.1.
ENVHE 1
Recommendations in the report by GeoEnvironmental Solutions, titled Phase II Environmental Site Assessment, 4044 Melville Street Hobart, dated March 2020, must be implemented, for the duration of the development and use.
Reason for condition
To ensure that the risk to future occupants of the building remain low and acceptable.
ENVHE 2
A demolition and construction management plan must be implemented throughout the construction works.
A demolition and construction management plan must be submitted and approved prior to the issuing of any building permit under the Building Act 2016. The plan must include but is not limited to the following:
1. Identification and disposal of any potentially contaminated waste and asbestos; 2. Proposed hours of work (including volume and timing of heavy vehicles entering and leaving the site, and works undertaken on site); 3. Proposed hours of construction;
4. Identification of potentially noisy construction phases, such as operation of rock breakers, explosives or pile drivers, and proposed means to minimise impact on the amenity of neighbouring buildings; 5. Control of dust and emissions during working hours; 6. Proposed screening of the site and vehicular access points during work; and 7. Procedures for washing down vehicles, to prevent soil and debris being carried onto the street.
All work required by this condition must be undertaken in accordance with the approved demolition and construction management plan.
Advice:
Once the demolition and construction management plan has been approved the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement).
Where building approval is also required, it is recommended that documentation for condition endorsement be submitted well before submitting documentation for building approval. Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.
Note also the requirement of condition ENG tr 2. That information could form part of the above document.
Reason for condition
To ensure minimal impact on the amenity of adjoining properties and members of the public during the construction period.
ENVHE 4
A contamination management plan (in accordance with the GES ENVIRONMENTAL SITE ASSESSMENT titled 139 Elizabeth Street, Hobart March 2020) must be implemented throughout the construction works.
A contamination management plan must be submitted and approved prior to the issuing of any building permit under the Building Act 2016.
Reason for condition
To ensure the health of the environment, workers and future users of the site.
ADVICE
The following advice is provided to you to assist in the implementation of the planning permit that has been issued subject to the conditions above. The advice is not exhaustive and you must inform yourself of any other legislation, bylaws, regulations, codes or standards that will apply to your development under which you may need to obtain an approval. Visit the Council's website for further information.
Prior to any commencement of work on the site or commencement of use the following additional permits/approval may be required from the Hobart City Council.
CONDITION ENDORSEMENT PLANNING
If a condition endorsement is required by a planning condition above, you will need to submit the relevant documentation to satisfy the condition via the Condition Endorsement Submission on Council's online services eplanning portal.
Where building approval is also required, it is recommended that documentation for condition endorsement be submitted well before submitting documentation for building approval. Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.
Once approved, the Council will respond to you via email that the condition has been endorsed (satisfied). Detailed instructions can be found here.
CONDITION ENDORSEMENT ENGINEERING
All engineering drawings required to be submitted and approved by this planning permit must be submitted to the City of Hobart as a CEP (Condition Endorsement) via the City’s Online Service Development Portal. When lodging a CEP, please reference the PLN number of the associated Planning Application. Each CEP must also include an estimation of the cost of works shown on the submitted engineering drawings. Once that estimation has been confirmed by the City’s Engineer, the following fees are payable for each CEP submitted and must be paid prior to the City of Hobart commencing assessment of the engineering drawings in each CEP:
Value of Building Works Approved by Planning Permit Fee: Up to $20,000: $150 per application. Over $20,000: 2% of the value of the works as assessed by the City's Engineer per assessment.
These fees are additional to building and plumbing fees charged under the Building and Plumbing Regulations.
Once the CEP is lodged via the Online Service Development Portal, if the value of building works approved by your planning permit is over $20,000, please contact the City’s Development Engineer on 6238 2715 to confirm the estimation of the cost of works shown on the submitted engineering drawings has been accepted.
Once confirmed, pleased call one of the City’s Customer Service Officers on 6238 2190 to make payment, quoting the reference number (ie. CEP number) of the Condition Endorsement you have lodged. Once payment is made, your engineering drawings will be assessed.
BUILDING PERMIT
You may need building approval in accordance with the Building Act 2016. Click here for more information.
This is a Discretionary Planning Permit issued in accordance with section 57 of the Land Use Planning and Approvals Act 1993.
PLUMBING PERMIT
You may need plumbing approval in accordance with the Building Act 2016, Building Regulations 2016 and the National Construction Code. Click here for more information.
OCCUPATION OF THE PUBLIC HIGHWAY
You may require a Permit to Open Up and Temporarily Occupy a Highway (for work in the road reserve). Click here for more information.
GENERAL EXEMPTION (TEMPORARY) PARKING PERMITS
You may qualify for a General Exemption permit for construction vehicles i.e. residential or meter parking/loading zones. Click here for more information.
NEW SERVICE CONNECTION
Please contact the Hobart City Council's City Amenity Division to initiate the application process for your new stormwater connection.
STORMWATER
Please note that in addition to a building and/or plumbing permit, development must be in accordance with the Hobart City Council’s Infrastructure By law. Click here for more information.
WORK WITHIN THE HIGHWAY RESERVATION
Please note development must be in accordance with the Hobart City Council’s Infrastructure By law. Click here for more information.
CBD AND HIGH VOLUME FOOTPATH CLOSURES
Please note that the City of Hobart does not support the extended closure of public footpaths or roads to facilitate construction on adjacent land.
It is the developer's responsibility to ensure that the proposal as designed can be constructed without reliance on such extended closures.
In special cases, where it can be demonstrated that closure of footpaths in the CBD and/or other high volume footpaths can occur for extended periods without unreasonable impact on other businesses or the general public, such closures may only be approved by the full Council.
For more information about this requirement please contact the Council's Traffic Engineering Unit on 6238 2804.
DRIVEWAY SURFACING OVER HIGHWAY RESERVATION
If a coloured or textured surface is used for the access within the Highway Reservation, the Council or other service provider will not match this on any reinstatement of the access within the Highway Reservation required in the future.
RIGHT OF WAY
The private right of way must not be reduced, restricted or impeded in any way, and all beneficiaries must have complete and unrestricted access at all times.
You should inform yourself as to your rights and responsibilities in respect to the private right of way particularly reducing, restricting or impeding the right during and after construction.
WASTE DISPOSAL
It is recommended that the developer liaise with the Council’s Cleansing and Solid Waste Unit regarding reducing, reusing and recycling materials associated with demolition on the site to minimise solid waste being directed to landfill.
Further information regarding waste disposal can also be found on the Council’s website.
FEES AND CHARGES
Click here for information on the Council's fees and charges.
DIAL BEFORE YOU DIG
Click here for dial before you dig information.
|
Delegation: Committee
Item 7.1.1 was then taken
The Deputy Lord Mayor vacated the Chair.
The Deputy Lord Mayor and Councillor Harvey declared an interest in item 7.1.5 and left the meeting at 5.03pm.
BRISCOE
That Alderman Behrakis Chair the meeting for item 7.1.5
MOTION CARRIED
VOTING RECORD
AYES |
NOES |
Briscoe |
|
Behrakis |
|
Dutta |
|
Coats |
|
Alderman Behrakis assumed the Chair.
7.1.5 48, 50, 52 and 56 Salvator Road, West Hobart - Partial Demolition, Alterations, Extension, New Building and Change of Use to Two Multiple Dwellings (One Existing, One New) |
||||||||||
BRISCOE |
||||||||||
That the recommendation contained in the report of the Development Appraisal Planner and the Senior Statutory Planner of 25 November 2020, be adopted. |
||||||||||
MOTION CARRIED VOTING RECORD
|
||||||||||
COMMITTEE RESOLUTION: |
||||||||||
That pursuant to the Hobart Interim Planning Scheme 2015, the City Planning Committee, in accordance with the delegations contained in its terms of reference, approve the application for Partial Demolition, Alterations, Extension, New Building, and Change of Use to Two Multiple Dwellings (One Existing, One New), at 48, 50, 52 and 56 Salvator Road, West Hobart for the reasons outlined in the officer’s report attached to item 7.1.5 of the Open City Planning Committee agenda of 30 November 2020 and a permit containing the following conditions be issued:
GEN
The use and/or development must be substantially in accordance with the documents and drawings that comprise PLN20355 48, 50, 52 and 56 SALVATOR ROAD WEST HOBART TAS 7000 Final Planning Documents, except where modified below.
Reason for condition
To clarify the scope of the permit.
TW
The use and/or development must comply with the requirements of TasWater as detailed in the form Submission to Planning Authority Notice, Reference No. TWDA 2020/00961HCC dated 15/07/2020 as attached to the permit.
Reason for condition
To clarify the scope of the permit.
PLN 3
The bin storage area adjacent to the car parking for the new dwelling must be increased in size to 3m2 and must provide adequate storage for the bins for both dwellings in that location.
Reason for condition
To ensure that the rubbish bins do not impact on the amenity of the locality, and to ensure compliance with the outdoor storage standards in the Hobart Interim Planning Scheme 2015.
ENG sw1
All stormwater from the proposed development (including but not limited to: roofed areas, ag drains, retaining wall ag drains and impervious surfaces such as driveways and paved areas) must be drained to the Council’s stormwater infrastructure prior to first occupation or commencement of use (whichever occurs first).
Advice:
Under section 23 of the Urban Drainage Act 2013 it is an offence for a property owner to direct stormwater onto a neighbouring property.
Reason for condition
To ensure that stormwater from the site will be discharged to a suitable Council approved outlet.
ENG sw8
Stormwater detention for stormwater discharges from the development must be installed prior to issue of a Certificate of Completion. A stormwater management report and design must be submitted and approved, prior to issue of any consent under the Building Act 2016 or construction. The stormwater management report and design must:
1. be prepared by a suitably qualified engineer; 2. include detailed design and supporting calculations of the detention tank, sized such that there is no increase in flows from the developed site up to 5% AEP storm events and such that flows are limited to the receiving capacity of the kerb and gutter. All assumptions must be clearly stated; 3. include design drawings of the detention tank showing the layout, the inlet and outlet (including long section), emptying times and the overflow mechanism; and 4. include a supporting maintenance plan.
All work required by this condition must be undertaken and maintained in accordance with the approved stormwater management report and design.
Reason for condition
To avoid the possible pollution of drainage systems and natural watercourses, to comply with relevant State legislation, and to ensure the development’s stormwater system takes into account limited receiving capacity of Council’s infrastructure.
ENG tr2
A construction traffic and parking management plan must be implemented prior to the commencement of work on the site (including demolition).
The construction traffic (trucks, service and delivery vehicles) and parking management plan for all tradesperson vehicles must be submitted and approved, prior to commencement work (including demolition). The construction traffic and parking management plan must:
1. Be prepared by a suitably qualified person. 2. Develop a communications plan to advise other right of way users / owners, as well as the wider community, of the traffic and parking impacts during construction. 3. Include a start date and finish dates of various stages of works. 4. Include times that trucks and other traffic associated with the works will be allowed to operate. 5. Nominate a superintendent, or the like, to advise the Council of the progress of works in relation to the traffic and parking management with regular meetings during the works.
All work required by this condition must be undertaken in accordance with the approved construction traffic and parking management plan.
Advice:
Once the construction traffic and parking management plan has been approved, the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement).
Where building approval is also required, it is recommended that documentation for condition endorsement be submitted well before submitting documentation for building approval. Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.
Reason for condition
To ensure the safety of vehicles entering and leaving the development and the safety and access around the development site for the general public and adjacent businesses.
ENG 2a
Prior to first occupation or commencement of use (whichever occurs first), vehicular barriers compliant with the Australian Standard AS/NZS1170.1:2002 must be installed to prevent vehicles running off the edge of an access driveway or parking module (parking spaces, aisles and manoeuvring area) where the drop from the edge of the trafficable area to a lower level is 600mm or greater, and wheel stops (kerb) must be installed for drops between 150mm and 600mm. Barriers must not limit the width of the driveway access or parking and turning areas approved under the permit.
Advice:
The Council does not consider a slope greater than 1 in 4 to constitute a lower level as described in AS/NZS 2890.1:2004 Section 2.4.5.3. Slopes greater than 1 in 4 will require a vehicular barrier or wheel stop.
Designers are advised to consult the National Construction Code 2016 to determine if pedestrian handrails or safety barriers compliant with the NCC2016 are also required in the parking module this area may be considered as a path of access to a building.
Reason for condition
To ensure the safety of users of the access driveway and parking module and compliance with the standard.
ENG 2b
Prior to the issue of any approval under the Building Act 2016 or the commencement of works on site (whichever occurs first), a certified vehicle barrier design (including site plan with proposed location(s) of installation) prepared by a suitably qualified engineer, compliant with Australian Standard AS/NZS1170.1:2002, must be submitted to Council.
Advice:
If the development's building approval includes the need for a Building Permit from Council, the applicant is advised to submit detailed design of vehicular barrier as part of the Building Application.
If the development's building approval is covered under Notifiable Work the applicant is advised to submit detailed design of vehicular barrier as a condition endorsement of the planning permit condition. Once the certification has been accepted, the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement).
Reason for condition
To ensure the safety of users of the access driveway and parking module and compliance with the standard.
ENG 2c
Prior to the commencement of use, vehicular barriers must be inspected by a qualified engineer and certification submitted to the Council confirming that the installed vehicular barriers comply with the certified design and Australian Standard AS/NZS1170.1:2002.
Advice:
Certification may be submitted to the Council as part of the Building Act 2016 approval process or via condition endorsement (see general advice on how to obtain condition endorsement).
Reason for condition
To ensure the safety of users of the access driveway and parking module and compliance with the relevant standards.
ENG 3a
The access driveway, circulation roadways, ramps and parking module (parking spaces, aisles and manoeuvring area) must be designed and constructed in accordance with Australian Standard AS/NZS2890.1:2004 (including the requirement for vehicle safety barriers where required), or a Council approved alternate design certified by a suitably qualified engineer to provide a safe and efficient access, and enable safe, easy and efficient use.
Advice:
It is advised that designers consider the detailed design of the access and parking module prior to finalising the Finished Floor Level (FFL) of the parking spaces (especially if located within a garage incorporated into the dwelling), as failure to do so may result in difficulty complying with this condition.
Reason for condition
To ensure the safety of users of the access and parking module, and compliance with the relevant Australian Standard.
ENG 3b
The access driveway, circulation roadways, ramps and parking module (parking spaces, aisles and manoeuvring area) design must be submitted and approved, prior to the commencement of work, or the issuing of any approval under the Building Act 2016, whichever occurs first.
The access driveway, circulation roadways, ramps and parking module (parking spaces, aisles and manoeuvring area) design must:
1. Be prepared and certified by a suitably qualified engineer, 2. Be generally in accordance with the Australian Standard AS/NZS 2890.1:2004, 3. Where the design deviates from AS/NZS2890.1:2004 the designer must demonstrate that the design will provide a safe and efficient access, and enable safe, easy and efficient use, and
4. Show dimensions, levels, gradients and transitions, and other details as Council deem necessary to satisfy the above requirement.
Advice:
It is advised that designers consider the detailed design of the access and parking module prior to finalising the Finished Floor Level (FFL) of the parking spaces (especially if located within a garage incorporated into the dwelling), as failure to do so may result in difficulty complying with this condition.
Once the design has been approved, the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement) Where building approval is also required, it is recommended that documentation for condition endorsement be submitted well before submitting documentation for building approval. Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.
Reason for condition
To ensure the safety of users of the access and parking module, and compliance with the relevant Australian Standard.
ENG 3c
The access driveway, circulation roadways, ramps and parking module (parking spaces, aisles and manoeuvring area) must be constructed in accordance with the design drawings approved by Condition ENG 3b.
Prior to the commencement of use, documentation by a suitably qualified engineer certifying that the access driveway and parking module has been constructed in accordance with the above drawings must be lodged with Council.
Advice:
Certification may be submitted to Council as part of the Building Act 2016 approval process or via condition endorsement (see general advice on how to obtain condition endorsement)
Reason for condition
To ensure the safety of users of the access and parking module, and compliance with the relevant Australian Standard.
ENG 4
The access driveway and parking module (car parking spaces, aisles and manoeuvring area) approved by this permit must be constructed to a sealed standard (spray seal, asphalt, concrete, pavers or equivalent Council approved) and surface drained to the Council's stormwater infrastructure prior to the commencement of use.
Reason for condition
To ensure the safety of users of the access driveway and parking module, and that it does not detract from the amenity of users, adjoining occupiers or the environment by preventing dust, mud and sediment transport.
ENG 5
The number of car parking spaces approved on the site, for use is five (5).
All parking spaces must be delineated by means of white or yellow lines 80mm to 100mm wide, or white or yellow pavement markers in accordance with Australian Standards AS/NZS 2890.1 2004, prior to first occupation / commencement of use.
Reason for condition
To ensure the provision of parking for the use is safe and efficient.
ENG 10
The condition endorsed passing bay design must be signed by a suitably qualified engineer, certifying the driveway/access has been constructed in accordance with the condition endorsed design drawings/approved passing bay design, must be lodged with the Council prior to the issuing of any Completion or Occupancy Certificate under the Building Act 2016.
Reason for condition
To ensure the safety of users of the access / adjacent properties.
ENG 1
Any damage to council infrastructure resulting from the implementation of this permit, must, at the discretion of the Council:
1. Be met by the owner by way of reimbursement (cost of repair and reinstatement to be paid by the owner to the Council); or 2. Be repaired and reinstated by the owner to the satisfaction of the Council.
A photographic record of the Council's infrastructure adjacent to the subject site must be provided to the Council prior to any commencement of works.
A photographic record of the Council’s infrastructure (e.g. existing property service connection points, roads, buildings, stormwater, footpaths, driveway crossovers and nature strips, including if any, preexisting damage) will be relied upon to establish the extent of damage caused to the Council’s infrastructure during construction. In the event that the owner/developer fails to provide to the Council a photographic record of the Council’s infrastructure, then any damage to the Council's infrastructure found on completion of works will be deemed to be the responsibility of the owner.
Reason for condition
To ensure that any of the Council's infrastructure and/or siterelated service connections affected by the proposal will be altered and/or reinstated at the owner’s full cost.
ENG s1
Passing bays must be constructed wholly within the right of way at or before the main bend of the existing access driveway.
The passing bay design must be submitted and approved, prior to the issuing of any approval under the Building Act 2016. The passing bay design must:
1. Be prepared and certified by a suitably qualified engineer; 2. Be generally in accordance with the Australian Standards AS1170.1, AS2890.1 and AS4678; 3. Show the passing bay sealed and drained to council’s stormwater infrastructure; and 4. Show dimensions, levels, gradients and transitions, and other details as Council deem necessary to satisfy the above requirement.
All work required by this condition must be undertaken in accordance with the passing bay design.
Advice
Once the design has been approved, the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement) Where building approval is also required, it is recommended that documentation for condition endorsement be submitted well before submitting documentation for building approval. Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.
Reason for condition
To allow safe vehicular access for all users.
ENV 1
Sediment and erosion control measures sufficient to prevent sediment from leaving the site must be installed prior to any disturbance of the site, and maintained until all areas of disturbance have been stabilized or revegetated.
Advice:
For further guidance in preparing a Soil and Water Management Plan – in accordance with Fact sheet 3 Derwent Estuary Program click here.
Reason for condition
To avoid the sedimentation of roads, drains, natural watercourses, Council land that could be caused by erosion and runoff from the development, and to comply with relevant State legislation.
ADVICE
The following advice is provided to you to assist in the implementation of the planning permit that has been issued subject to the conditions above. The advice is not exhaustive and you must inform yourself of any other legislation, bylaws, regulations, codes or standards that will apply to your development under which you may need to obtain an approval. Visit the Council's website for further information.
Prior to any commencement of work on the site or commencement of use the following additional permits/approval may be required from the Hobart City Council.
BUILDING PERMIT
You may need building approval in accordance with the Building Act 2016. Click here for more information.
This is a Discretionary Planning Permit issued in accordance with section 57 of the Land Use Planning and Approvals Act 1993.
PLUMBING PERMIT
You may need plumbing approval in accordance with the Building Act 2016, Building Regulations 2016 and the National Construction Code. Click here for more information.
OCCUPATION OF THE PUBLIC HIGHWAY
You may require a permit for the occupation of the public highway for construction or special event (e.g. placement of skip bin, crane, scissor lift etc). Click here for more information.
You may require an occupational license for structures in the Hobart City Council highway reservation, in accordance with conditions to be established by the Council. Click here for more information.
You may require a road closure permit for construction or special event. Click here for more information.
You may require a Permit to Open Up and Temporarily Occupy a Highway (for work in the road reserve). Click here for more information.
RIGHT OF WAY
The private right of way must not be reduced, restricted or impeded in any way, and all beneficiaries must have complete and unrestricted access at all times.
You should inform yourself as to your rights and responsibilities in respect to the private right of way particularly reducing, restricting or impeding the right during and after construction.
NOISE REGULATIONS
Click here for information with respect to noise nuisances in residential areas.
FEES AND CHARGES
Click here for information on the Council's fees and charges.
DIAL BEFORE YOU DIG
Click here for dial before you dig information.
|
Delegation: Committee
The Deputy Lord Mayor and Councillor Harvey returned to the meeting at 5.04pm.
Alderman Behrakis vacated the Chair.
The Deputy Lord Mayor resumed the Chair.
Supplementary item 13 was then taken.
8. Reports
Delegation: Council
HARVEY |
||||||||||
That the recommendation contained in the memorandum of the Director City Planning of 23 November 2020, be adopted. |
||||||||||
MOTION CARRIED VOTING RECORD
|
||||||||||
COMMITTEE RESOLUTION: |
||||||||||
That the information contained in the memorandum Delegated Decision Report (Planning) be received and noted.
|
Delegation: Committee
HARVEY |
||||||||||
That the recommendation contained in the memorandum of the Director City Planning of 24 November 2020, be adopted. |
||||||||||
MOTION CARRIED VOTING RECORD
|
||||||||||
COMMITTEE RESOLUTION: |
||||||||||
That the information contained in the memorandum City Planning – Advertising Report be received and noted.
|
Delegation: Committee
9. Committee Action Status Report
DUTTA |
||||||||||
MOTION CARRIED VOTING RECORD
|
Delegation: Committee
Regulation 29(3) Local Government
(Meeting Procedures) Regulations 2015.
File Ref: 13-1-10
10.1 Boarding Houses
File Ref: F20/83419; 13-1-10
Memorandum of the Director City Planning of 24 November 2020.
10.2 Building Permits - Timeframe
File Ref: F20/109743
Memorandum of the Director City Planning of 24 November 2020.
10.3 Development Applications - Documentation
File Ref: F20/100949; 13-1-10
Memorandum of the Director City Planning of 24 November 2020.
10.4 Environmental Standards - Multi-Residential Developments
File Ref: F20/124660; 13-1-10
Memorandum of the Director City Planning of 25 November 2020.
10.5 Planning Authority - Roles and Responsibilities
File Ref: F20/124663; 13-1-10
Memorandum of the Director City Planning of 24 November 2020.
10.6 Multi-Story Apartments / Commercial Properties - Commencement
File Ref: F20/124669; 13-1-10
Memorandum of the Director City Planning of 24 November 2020 and attachments.
10.7 Questions Without Notice
File Ref: F20/124674; 13-1-10
Memorandum of the Director City Planning of 24 November 2020.
BRISCOE
MOTION CARRIED VOTING RECORD
|
Delegation: Committee
Section 29 of the Local Government (Meeting Procedures) Regulations 2015.
File Ref: 13-1-10
11.1 Alderman Briscoe - Building Permits - Timeframe File Ref: 13-1-10 |
|
|
Question: Can the Director advise if we have any statistics on the range of time it takes to receive a building permit over the past 2 years? Answer: The Director City Planning took the question on notice.
|
HARVEY
|
||||||||||
That the Committee resolve by majority that the meeting be closed to the public pursuant to regulation 15(1) of the Local Government (Meeting Procedures) Regulations 2015 because the items included on the closed agenda contain the following matters:
· Confirm the minutes of the Closed portion of the meeting · Questions without notice in the Closed portion
The following items were discussed:-
Item No. 1 Minutes of the last meeting of the Closed Portion of the Committee Meeting Item No. 2 Consideration of supplementary items to the agenda Item No. 3 Indications of pecuniary and conflicts of interest Item No. 4 Questions Without Notice
|
||||||||||
MOTION CARRIED VOTING RECORD
|
Delegation: Committee
Felicity Spaulding, Sam Stark, Peter Blackwell, Millard Ziegler, Jonah Gouldthorpe and Donald Knowler (Representors), Frazer Read and James Atkinson (Applicant) addressed the Committee in relation to supplementary item 13.
13 32 and 30 Romilly Street, South Hobart and Adjacent Rivulet and Adjacent Road Reserve |
||||||||||
BRISCOE
|
||||||||||
That the recommendation contained in the report of the Development Appraisal Planner and the Senior Statutory Planner of 26 November 2020, be adopted, as amended by the inclusion of an additional condition PLN s4 and advice clause:
“PLN s4
Prior to the issue of any approval under the Building Act 2016 (excluding for demolition) or the commencement of work on the site (whichever occurs first), a landscaping plan for the site prepared by a suitably qualified landscape expert must be submitted and approved. The landscaping plan must show:
1. species of proposed planting, with priority given to native vegetation which is intended to attract birds and resist fire; and
2. removal of weeds from the whole site, including the covenanted area.
All work required by this condition must be undertaken in accordance with the approved landscaping plan and must be completed prior to first occupation of the new dwellings.
The vegetation which is planted on the site pursuant to the landscaping plan must be maintained and must not be disturbed. If any vegetation dies or is destroyed, replacement vegetation of a similar size must be planted within 30 days of the death or destruction.
Advice – protection of historic track
If, the new stormwater connection to Sandy Bay Rivulet crosses remains of the historic track found on the site then the Applicant is encouraged to minimise disturbance to the track and reinstate the track to the state that it was prior to the works commencing.” |
||||||||||
MOTION CARRIED
VOTING RECORD
|
||||||||||
BRISCOE
The addition of a Part B to read as follows:
PART B
That a traffic and parking management plan for Romilly Street, South Hobart be considered by the City Infrastructure Committee. |
||||||||||
MOTION CARRIED VOTING RECORD
|
||||||||||
COMMITTEE RESOLUTION: |
||||||||||
That pursuant to the Hobart Interim Planning Scheme 2015, the Council approve the application for subdivision (boundary adjustment), 10 multiple dwellings (nine new, one existing), works in road reserve and associated hydraulic infrastructure, at 30 and 32 Romilly Street, South Hobart for the reasons outlined in the officer’s report attached to supplementary item 13 of the Open City Planning Committee agenda of 30 November 2020 and a permit containing the following conditions be issued:
GEN
The use and/or development must be substantially in accordance with the documents and drawings that comprise PLN20423 32 ROMILLY STREET & 30 ROMILLY STREET SOUTH HOBART TAS 7004 & ADJACENT RIVULET Final Planning Documents, except where modified below.
Reason for condition
To clarify the scope of the permit.
TW
The use and/or development must comply with the requirements of TasWater as detailed in the form Submission to Planning Authority Notice, Reference No. TWDA 2020/01027HCC dated 4 September 2020 as attached to the permit.
Reason for condition
To clarify the scope of the permit.
PLN s1
The approved plan of subdivision is LEISM03 1229610, dated 9/9/2020 which adjusts the lot areas by 54m2.
Reason for condition
To clarify the scope of the permit
PLN s2
The approved plan of the proposed unit development is the set of plans prepared by Lachlan Walsh Design, 20599, DA Set 1, dated 26 June 2020, revision 8, received by Council on 15 September 2020.
Reason for condition
To clarify the scope of the permit
PLN s3
The approval is for a minor boundary adjustment between 30 and 32 Romilly Street and for ten (10) multiple dwellings to be located on 32 Romilly Street, South Hobart. The dwellings are comprised of nine (9) new dwellings and one (1) existing dwelling. This means that the existing dwelling at 32 Romilly Street, South Hobart must function as one dwelling, unless further planning approval is sought and obtained.
Reason for condition
To clarify the scope of the permit
PLN s4
Prior to the issue of any approval under the Building Act 2016 (excluding for demolition) or the commencement of work on the site (whichever occurs first), a landscaping plan for the site prepared by a suitably qualified landscape expert must be submitted and approved. The landscaping plan must show:
1. species of proposed planting, with priority given to native vegetation which is intended to attract birds and resist fire; and
2. removal of weeds from the whole site, including the covenanted area.
All work required by this condition must be undertaken in accordance with the approved landscaping plan and must be completed prior to first occupation of the new dwellings.
The vegetation which is planted on the site pursuant to the landscaping plan must be maintained and must not be disturbed. If any vegetation dies or is destroyed, replacement vegetation of a similar size must be planted within 30 days of the death or destruction.
ENG sw1
All stormwater from the proposed development (including but not limited to: roofed areas, ag drains, retaining wall ag drains and impervious surfaces such as driveways and paved areas) must be drained to the Council’s stormwater infrastructure prior to first occupation or commencement of use (whichever occurs first).
Reason for condition
To ensure that stormwater from the site will be discharged to a suitable Council approved outlet.
ENG sw6
All stormwater from the proposed development (including hardstand runoff) must be discharged to the Council’s stormwater infrastructure with sufficient receiving capacity prior to first occupation. All costs associated with works required by this condition are to be met by the owner.
Design drawings and calculations of the proposed stormwater drainage and connections to the Council's stormwater infrastructure must be submitted and approved prior to the commencement of work. The design drawings and calculations must:
1. Be prepared by a suitably qualified person. 2. Include long section(s)/levels and grades to the point of discharge. 3. Ensure that the design must minimize any hydraulic intrusion at the discharge point into the Sandy Bay Rivulet. It also must demonstrate acceptable erosion and full scour control in the main flow path within the proposed headwall.
All work required by this condition must be undertaken in accordance with the approved design drawings and calculations.
Reason for condition
To ensure that stormwater from the site will be discharged to a suitable Council approved outlet.
SW 9
Prior to occupancy or the commencement of the approved use (whichever occurs first), stormwater pretreatment and detention for stormwater discharges from the development must be installed.
A stormwater management report and design must be submitted and approved, prior to the issue of any approval under the Building Act 2016 or the commencement of work on the site (whichever occurs first). The stormwater management report and design must be prepared by a suitably qualified engineer and must:
1. Include
detailed design (using industry accepted proprietary software, such as MUSIC)
of the proposed treatment train, including final estimations of contaminant
removal; 2. Include detailed
design and supporting calculations of the detention tank showing: 1. Detention tank sizing such that there is no increase in flows from the developed site up to 5% AEP event and no worsening of flooding; 2. The layout, the inlet and outlet (including long section), outlet size, overflow mechanism and invert level; 3. The discharge rates and emptying times; and 4. All assumptions must be clearly stated;
3. Include a supporting maintenance plan, which specifies the required maintenance measures to check and ensure the ongoing effective operation of all systems, such as: inspection frequency; cleanout procedures; descriptions and diagrams of how the installed systems operate; details of the life of assets and replacement requirements.
All work required by this condition must be undertaken and maintained in accordance with the approved stormwater management report and design.
ENG 13
An ongoing waste management plan for all domestic waste and recycling/compost bins must be implemented post construction.
A detailed waste management plan must be submitted and approved, prior to the issuing of any approval under the Building Act 2016 or commencement of works (whichever occurs first), to the satisfaction of the Council's Director City Planning. The waste management plan must:
1. Include details for the handling of waste (i.e. placement of bins on collection day) within Council's highway reservation.
2. Include details of the quantity and type/size of bins.
All work required by this condition must be undertaken in accordance with the approved waste management plan.
Advice:
Council notes that a development of this size would require an allocation in excess of twenty two (23) bins, given the limited available street frontage alternate provisions must be arranged with the Council.
Should you have any queries in relation to formulating a solid waste management plan Council staff can assist with the development of a waste management plan outlining Council's requirements. Please contact the Council’s Customer Liaison Officer, on Phone 6278 0273.
Once the waste management plan has been approved Council will issue a condition endorsement (see general advice on how to obtain condition endorsement).
Where building approval is also required, it is recommended that documentation for condition endorsement be submitted well before submitting documentation for building approval. Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.
Reason for condition
To ensure that solid waste management from the site meets the Council’s requirements and standards.
ENG tr2
A construction traffic and parking management plan must be implemented prior to the commencement of work on the site (including demolition).
The construction traffic (including cars, public transport vehicles, service vehicles, pedestrians and cyclists) and parking management plan must be submitted and approved, prior to commencement work (including demolition). The construction traffic and parking management plan must:
1. Be prepared by a suitably qualified person. 2. Develop a communications plan to advise the wider community of the traffic and parking impacts during construction. 3. Include a start date and finish dates of various stages of works. 4. Include times that trucks and other traffic associated with the works will be allowed to operate. 5. Nominate a superintendent, or the like, to advise the Council of the progress of works in relation to the traffic and parking management with regular meetings during the works.
All work required by this condition must be undertaken in accordance with the approved construction traffic and parking management plan.
Advice:
Once the construction traffic and parking management plan has been approved, the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement).
Where building approval is also required, it is recommended that documentation for condition endorsement be submitted well before submitting documentation for building approval. Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.
Reason for condition
To ensure the safety of vehicles entering and leaving the development and the safety and access around the development site for the general public and adjacent businesses.
ENG 2a
Prior to first occupation or commencement of use (whichever occurs first), vehicular barriers compliant with the Australian Standard AS/NZS 1170.1:2002 must be installed to prevent vehicles running off the edge of an access driveway or parking module (parking spaces, aisles and manoeuvring area) where the drop from the edge of the trafficable area to a lower level is 600mm or greater, and wheel stops (kerb) must be installed for drops between 150mm and 600mm. Barriers must not limit the width of the driveway access or parking and turning areas approved under the permit.
Advice:
The Council does not consider a slope greater than 1 in 4 to constitute a lower level as described in AS/NZS 2890.1:2004 Section 2.4.5.3. Slopes greater than 1 in 4 will require a vehicular barrier or wheel stop.
Designers are advised to consult the National Construction Code 2016 to determine if pedestrian handrails or safety barriers compliant with the NCC2016 are also required in the parking module this area may be considered as a path of access to a building.
Reason for condition
To ensure the safety of users of the access driveway and parking module and compliance with the standard.
ENG 2b
Prior to the issue of any approval under the Building Act 2016 or the commencement of works on site (whichever occurs first), a certified vehicle barrier design (including site plan with proposed location(s) of installation) prepared by a suitably qualified engineer, compliant with Australian Standard AS/NZS 1170.1:2002, must be submitted to the Council.
Advice:
If the development's building approval includes the need for a Building Permit from Council, the applicant is advised to submit detailed design of vehicular barrier as part of the Building Application.
If the development's building approval is covered under Notifiable Work the applicant is advised to submit detailed design of vehicular barrier as a condition endorsement of the planning permit condition. Once the certification has been accepted, the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement).
Reason for condition
To ensure the safety of users of the access driveway and parking module and compliance with the standard.
ENG 2c
Prior to the commencement of use, vehicular barriers must be inspected by a qualified engineer and certification submitted to the Council confirming that the installed vehicular barriers comply with the certified design from condition 2b and Australian Standard AS/NZS1170.1:2002.
Advice:
Certification may be submitted to the Council as part of the Building Act 2016 approval process or via condition endorsement (see general advice on how to obtain condition endorsement).
Reason for condition
To ensure the safety of users of the access driveway and parking module and compliance with the relevant standards.
ENG 3a
The access driveway, circulation roadways, ramps and parking module (parking spaces, aisles and manoeuvring area) must be designed and constructed in accordance with Australian Standard AS/NZS2890.1:2004 (including the requirement for vehicle safety barriers where required), or a Council approved alternate design certified by a suitably qualified engineer to provide a safe and efficient access, and enable safe, easy and efficient use.
Must comply with AS 2890.1 Clause 3.2.4 Sight distance at access driveway exits (pedestrian and vehicular, horizontal and vertical sight distances)
Advice:
It is advised that designers consider the detailed design of the access and parking module prior to finalising the Finished Floor Level (FFL) of the parking spaces (especially if located within a garage incorporated into the dwelling), as failure to do so may result in difficulty complying with this condition.
Reason for condition
To ensure the safety of users of the access and parking module, and compliance with the relevant Australian Standard.
ENG 3b
The access driveway, circulation roadways, ramps and parking module (parking spaces, aisles and manoeuvring area) design must be submitted and approved, prior to the issuing of any approval under the Building Act 2016.
The access driveway, circulation roadways, ramps and parking module (parking spaces, aisles and manoeuvring area) design must:
1. Be prepared and certified by a suitably qualified engineer, 2. Be generally in accordance with the Australian Standard AS/NZS2890.1:2004, 3. Where the design deviates from AS/NZS2890.1:2004 the designer must demonstrate that the design will provide a safe and efficient access, and enable safe, easy and efficient use, and 4. Show dimensions, levels, gradients and transitions, and other details as Council deem necessary to satisfy the above requirement.
Advice:
It is advised that designers consider the detailed design of the access and parking module prior to finalising the Finished Floor Level (FFL) of the parking spaces (especially if located within a garage incorporated into the dwelling), as failure to do so may result in difficulty complying with this condition.
Once the design has been approved, the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement)
Where building approval is also required, it is recommended that documentation for condition endorsement be submitted well before submitting documentation for building approval. Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.
Reason for condition
To ensure the safety of users of the access and parking module, and compliance with the relevant Australian Standard.
ENG 3c
The access driveway, circulation roadways, ramps and parking module (parking spaces, aisles and manoeuvring area) must be constructed in accordance with the design drawings approved by Condition ENG 3b.
Prior to the commencement of use, documentation by a suitably qualified engineer certifying that the access driveway and parking module has been constructed in accordance with the above drawings must be lodged with Council.
Advice:
Certification may be submitted to Council as part of the Building Act 2016 approval process or via condition endorsement (see general advice on how to obtain condition endorsement)
Reason for condition
To ensure the safety of users of the access and parking module, and compliance with the relevant Australian Standard.
ENG 4
The access driveway and parking module (car parking spaces, aisles and manoeuvring area) approved by this permit must be constructed to a sealed standard (spray seal, asphalt, concrete, pavers or equivalent Council approved) and surface drained to the Council's stormwater infrastructure prior to the [first occupation / commencement of use].
Reason for condition
To ensure the safety of users of the access driveway and parking module, and that it does not detract from the amenity of users, adjoining occupiers or the environment by preventing dust, mud and sediment transport.
ENG 5
The number of car parking spaces approved on the site is twenty four (24).
All parking spaces must be delineated by means of white or yellow lines 80mm to 100mm wide, or white or yellow pavement markers in accordance with Australian Standards AS/NZS 2890.1 2004, prior to first occupation / commencement of use (whichever occurs first).
Reason for condition
To ensure the provision of parking for the use is safe and efficient.
ENG 7
The number of car parks spaces approved on Romilly Street is twenty four (24). The parking area must be lined marked on the site prior to the commencement of the use.
Drawings must be submitted and approved, prior to the first occupation. The drawing must:
1. Show the layout of the car parking for the 24 in accordance with the Australian Standards AS/NZS 2890.1 2004, to satisfy the above requirement.
All work required by this condition must be undertaken in accordance with the approved drawings.
Advice:
Once the drawing has been approved the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement). Where building approval is also required, it is recommended that documentation for condition endorsement be submitted well before submitting documentation for building approval.
Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.
Reason for condition
To ensure safe and efficient parking is adequate to provide for the use.
ENG 8
The number of car parking spaces approved on the site, is twenty four (24) and is made up of:
· Twenty (20) user class 1A residence car parking spaces (within garages). · Four (4) user class 1A visitor car parking spaces consisting of the following: o Two visitor parking space in the turning area for dwellings 7, 8 and 9 for use by visitors to dwelling 6, 7, 8, and 9 o One visitor parking space in the garage apron for the existing dwelling for exclusive use of the existing dwelling and dwelling 1 and o One visitor parking space in the turning apron for dwelling 4 for exclusive use of dwelling 2, 3 and 4.
Prior to first occupation, the visitor parking spaces near dwelling 1 must:
· be delineated by means of white or yellow lines 80mm to 100mm wide, or white or yellow pavement markers in accordance with Australian Standards AS/NZS 2890.1 2004. · include pavement messaging indicating VISITOR PARKING in accordance with AS1742.11 Section 7.3, or equivalent Council approved alternative.
Advice:
Please note that the 'informal' visitor parking spaces proposed in front of dwelling 2 and 3 are not approved as these do not comply with AS2890.1 with respect to gradient and dimensions, and prevent formal passing bays at a maximum 30m interval along the circulation roadway servicing dwelling 2 4.
Please note that the two (2) 'informal' visitor parking spaces proposed in front of dwelling 4 are approved as one parking space only.
Please note that the two (2) 'informal' visitor parking spaces proposed in front of dwelling 5 are approved as one parking space only.
Please note that the two (2) 'informal' visitor parking spaces proposed in front of dwelling 1 are approved as one parking space only and that this must be located in the turning area perpendicular to the garage parking spaces for dwelling 1 in order to enable the garaged parking spaces and the visitor parking to operate independently.
Parking of cars is only permitted in approved car parking spaces.
Reason for condition
To ensure the provision of parking for the use is safe and efficient.
ENG 12
Parking, access and turning areas must be generally designed and constructed in accordance with the Australian Standard Parking facilities, Part 1: OffStreet Carparking, AS 2890.1 – 2004, prior to the first occupation.
Design drawings must be submitted and approved, prior to commencement of work. The amended design drawings must:
1. Show dimensions, levels and gradients, transitions and other details as necessary to satisfy the above requirement.
All work required by this condition must be undertaken in accordance with the approved design drawings.
Advice:
Once the design drawing has been approved Council will issue a condition endorsement (see general advice on how to obtain condition endorsement). Where building approval is also required, it is recommended that documentation for condition endorsement be submitted well before submitting documentation for building approval. Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.
Reason for condition
To ensure that the access and parking layout for the development is to accepted standards.
ENG 1
Any damage to council infrastructure resulting from the implementation of this permit, must, at the discretion of the Council:
1. Be met by the owner by way of reimbursement (cost of repair and reinstatement to be paid by the owner to the Council); or 2. Be repaired and reinstated by the owner to the satisfaction of the Council.
A photographic record of the Council's infrastructure adjacent to the subject site must be provided to the Council prior to any commencement of works.
A photographic record of the Council’s infrastructure (e.g. existing property service connection points, roads, buildings, stormwater, footpaths, driveway crossovers and nature strips, including if any, preexisting damage) will be relied upon to establish the extent of damage caused to the Council’s infrastructure during construction. In the event that the owner/developer fails to provide to the Council a photographic record of the Council’s infrastructure, then any damage to the Council's infrastructure found on completion of works will be deemed to be the responsibility of the owner.
Reason for condition
To ensure that any of the Council's infrastructure and/or siterelated service connections affected by the proposal will be altered and/or reinstated at the owner’s full cost.
ENG r3
Prior to the commencement of use, the proposed driveway crossover in the Romilly Street highway reservation must be designed and constructed in general accordance with:
· Rural – TSDR04v1 – Rural Roads Typical Driveway Profile and TSD R03v1 Rural Roads Typical Property Access.
Design drawings must be submitted and approved prior to any approval under the Building Act 2016. The design drawing must:
1. Show the cross and long section of the driveway crossover within the highway reservation and onto the property 2. Consider runoff from the road, be aware that the council is not managing drainage at this section of Romilly Street. 3. Detail any services or infrastructure (ie light poles, pits, awnings) at or near the proposed driveway crossover 4. Be designed for the expected vehicle loadings. A structural certificate to note that driveway is suitable for heavy vehicle loadings. 5. Show swept path templates in accordance with AS/NZS 2890.1 2004(B85 or B99 depending on use, design template) 6. If the design deviates from the requirements of the TSD then the drawings must demonstrate that a B85 vehicle or B99 depending on use (AS/NZS 2890.1 2004, section 2.6.2) can access the driveway from the road pavement into the property without scraping the cars underside 7. Show that vehicular and pedestrian sight lines are met as per AS/NZS 2890.1 2004. 8. Grated wedge, asphalt wedge and the standard open wedge driveway crossover are not permitted. Grated wedges are permits on highly used bike routes and details of the grate (ie mass) will be required. To gain access a concrete plinth to Councils standards may be constructed at the gutter. A drawing of a standard concrete plinth can be obtained from Councils Road Services Engineer. Note: that the agreement of the Council’s is required to adjust footpath levels. 9. Be prepared and certified by a suitable qualified person, to satisfy the above requirement.
All work required by this condition must be undertaken in accordance with the approved drawings.
Advice:
The applicant is required submit detailed design documentation to satisfy this condition via Council's planning condition endorsement process (noting there is a fee associated with condition endorsement approval of engineering drawings [see general advice on how to obtain condition endorsement and for fees and charges]). This is a separate process to any building approval under the Building Act 2016.
Please note that your proposal does not include adjustment of footpath levels. Any adjustment to footpath levels necessary to suit the design of proposed floor, parking module or driveway levels will require separate agreement from Council's Road Services Engineer and may require further planning approvals. It is advised to place a note to this affect on construction drawings for the site and/or other relevant engineering drawings to ensure that contractors are made aware of this requirement.
Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays .
Reason for condition
To ensure that works will comply with the Council’s standard requirements.
ENV 8
All recommended risk mitigation measures in section 7 of the Geotechnical Assessment report by GeoEnvironmental Solutions dated September 2020 must be implemented including:
· The foundations of all units must be socketed in the underlying dolerite bedrock as deemed satisfactory by the project structural engineer. · Fill is not be used to achieve finished floor levels for the units within · Zones 2, 3 and the No Fill Zone. · Cut batters should not exceed 1V:3H in fill material and 1V:2H in natural soils on site. · Fill should not be used on the steep slopes (≥15°) which have previously failed (No Fill Zone), nor to achieve design finished floor levels within construction Zones 2 and 3, or be used on steep slopes (≥15°) as achieving safe batter angles is difficult with regard to the natural slope angle. Fill batters must not exceed 1V:3H. · Only the minimum required vegetation should be removed to satisfy bushfire risk and construction at the site.
· Cutoff drains are to be implemented above all cuts and the downslope edge of the proposed driveways should have guttering where practicable, adequate detention structures and outlet near Sandy Bay rivulet to an appropriate armoured design. In particular, care should be taken to correctly channel any possible accumulated water from sealed areas or any driveway away from the top of the proposed building platforms and the top of the existing active landslide area. · All earthworks on site including formation of internal roads and installation of stormwater and wastewater infrastructure should be conducted as per AS3798 – Guidelines on Earthworks for Commercial and Residential Developments. This includes trenching and compaction of all fill on site. · Further investigations must also include adequate drilling and testing to confirm foundation conditions for the anticipated building loads and depth to underlying competent bedrock. · All building sites/units should be assessed and designed as per AS2870 prior to construction.
Reason for condition
To reduce the risk to life and property, and the cost to the community, caused by landslides.
ENV 9
Trees T5, T10, T12 and T13 shown in ‘Attachment 6 RFI response to PLN 20423’ are not approved to be removed and must be retained.
Reason for condition
To ensure the development does not have an unacceptable impact upon natural values.
ENV 10
An approved construction management plan for any proposed works within the waterway protection area, other than the stormwater works, must be implemented.
A construction management plan for any proposed works within the waterway protection area, other than the stormwater works, prepared by a suitably qualified person, must be submitted and approved prior the commencement of works and prior to the granting of building consent.
The construction management plan must:
· show and detail all proposed works, including earthworks, within the waterway protection area; · demonstrate that all proposed works within the waterway protection area have been avoided or minimised as far as reasonably practicable; · include fencing of the site to separate the development area from the waterway protection area; · show the location of the fencing and include details of the fence design; show the location of the proposed fencing relative to the tree protection zones of trees within the waterway protection area, and be designed · and sited to avoid impacts to those trees; · specify that the fencing is to be installed prior to the commencement of other works and is to remain in place for the duration of the construction works; and · specify that no works, storage or stockpiling, or vehicle movements can occur on the Rivulet side of the fence unless approved by the planning authority or in accordance with the approved stormwater works construction management plan.
Reason for condition
To ensure the development does not have an unacceptable impact on natural values
ENV 15
All construction vehicles and machinery must be effectively cleaned of soil both before entering and before leaving the property.
Soil cleaned from construction vehicles and machinery must not be allowed, either directly or indirectly, to enter waterways or the Council’s stomwater system.
Note: further information on effective measures for washdown can be found here.
Reason for condition
To minimise the spread of weeds and pathogens.
ENV 16
No soil is to be imported onto the site unless determined as being free of weed propagules when tested in accordance with AS 4419 Soils for Landscaping and Garden Use.
Reason for condition
To minimise the spread of weeds.
ENV 2
Sediment and erosion control measures, in accordance with an approved soil and water management plan (SWMP), must be installed prior to the commencement of work and maintained until such time as all disturbed areas have been stabilised and/or restored or sealed to the Council’s satisfaction.
A SWMP must be submitted prior to the issue of any approval under the Building Act 2016 or the commencement of work, whichever occurs first. The SWMP must be prepared in accordance with the Soil and Water Management on Building and Construction Sites fact sheets (Derwent Estuary Program, 2008), available here.
All work required by this condition must be undertaken in accordance with the approved SWMP.
Advice:
Once the SWMP has been approved, the Council will issue a condition endorsement (see general advice on how to obtain condition endorsement).
Where building approval is also required, it is recommended that documentation for condition endorsement be submitted well before submitting documentation for building approval. Failure to address condition endorsement requirements prior to submitting for building approval may result in unexpected delays.
Reason for condition
To avoid the pollution and sedimentation of roads, drains and natural watercourses that could be caused by erosion and runoff from the development.
ENV s1
An approved rock fall management plan must be implemented.
A rock fall management plan, prepared by a suitably qualified person, must be submitted and approved prior the commencement of works and prior to the granting of building consent.
The rock fall management plan must include measures to manage boulders liberated during earthworks, so that they do not pose a risk to users of the site and will not damage vegetation within the waterway protection area.
Reason for condition
To ensure the risk to life and property from landslides is minimised and to ensure the development does not have an unnecessary impact upon natural values
ENV s2
An approved construction management plan for the stormwater works within the waterway protection area must be implemented.
A construction management plan for the stormwater works within the waterway protection area, prepared by a suitably qualified person, must be submitted and approved prior the commencement of works and prior to the granting of building consent.
The construction management plan must: · detail all proposed works within the waterway protection area, including ground disturbance and vegetation disturbance; · include a brief description of the work methodology;
· minimise ground disturbance and impact on vegetation, particularly native vegetation; · minimise impacts on habitat features; · minimise the risk of pollution of the Rivulet, including from fuel spills; · include soil and water management measures to minimise the risk of erosion and sediment transfer to the Rivulet; and · include rehabilitation measures for disturbed areas.
Reason for condition
To ensure the development does not have an unacceptable impact on natural values
SURV 1
The applicant must submit to the Council a copy of the surveyor’s survey notes at the time of lodging the final plan.
Reason for condition
To enable the Council to accurately update cadastral layers on the corporate Geographic Information System.
SURV 2
The final plan and schedule of easements must be submitted and approved in accordance with section 89 of the Local Government (Building & Miscellaneous Provisions) Act 1993.
Reason for condition
To ensure that the subdivision/boundary adjustment is carried out in accordance with the Council's requirements under the provisions of Part 3 of the Local Government (Building & Miscellaneous Provisions) Act 1993.
SURV 3
The final plan and schedule of easements must be submitted and approved under section 89 of the Local Government (Building & Miscellaneous Provisions) Act 1993.
The final plan and schedule of easements must provide easements to the satisfaction of the Council:
1. Over any proposed sewer mains passing through the lots on the final plan, in favour of TasWater (minimum width of 2.5 m). 2. Over any existing or proposed private rights of way, drainage and/or service easements in favour of the lots they are required to serve. 3. Over any existing road embankment easements in favour of the Hobart City Council. 4. Over the stormwater headwall and scour protection in favour of Hobart City Council if it is located within the boundaries of Lot 2.
Reason for condition
To ensure that there are no impediments to the provision of public and private services and access to the lots.
SURV 9
Any lots on the final plan created from the addition of sub minimal lots on the plan of subdivision are to be notated on the final plan.
The final plan must include notations in accordance with section 111 of the Local Government (Building and Miscellaneous Provisions) Act 1993, in relation to lot 1 to satisfy the above requirement.
Reason for condition
To ensure compliance with statutory provisions.
SURV 12
Lot 1 on the final plan is to be notated in accordance with the provisions of section 83(5)(a)(ii) of the Local Government (Building & Miscellaneous Provisions) Act 1993, to the effect that the Hobart City Council cannot provide a means of gravity reticulated stormwater disposal (Select from the whole of lot1.
The final plan must be submitted for approval by the Council. The final plan must be notated to the satisfaction of the Council.
Reason for condition
To ensure that the restriction in the Council’s ability to provide a means of gravity reticulated stormwater disposal is noted on the final plan.
SURV 13
The final plan is to be notated in accordance with the provisions of section 83(7) (b) of the Local Government (Building & Miscellaneous Provisions) Act 1993 to the effect that the Tasmanian Water and Sewerage Corporation cannot provide a means of gravity reticulated sewerage disposal from lot 2 below a specified reduced level.
The final plan must be submitted for approval by the Council. The final plan must be notated to the satisfaction of the Council.
The specified reduced level that may be required is to be provided by the owner’s Registered Land Surveyor who must supply the invert level (on State Datum) of the sewer connection constructed to serve Lot 2.
Reason for condition
To ensure that the limitation in TasWater’s ability to provide a means of gravity reticulated sewerage disposal from Lot 2 is noted on the final plan.
ENG 16
Prior to the sealing of the final plan, private sewer, stormwater (including surface drainage) and water services/connections are to be entirely separate to each lot and contained wholly within the lots served.
Reason for condition
To ensure that each lot is services separately.
ENG 17
Prior to the sealing of the final plan, the developer must verify compliance with condition ENG 16 by supplying the Council with an asinstalled services plan clearly indicating the location and details of all relevant services (entirely contained within their respective lots or appropriate easements). The as installed services plan must be accompanied by certification from a suitably qualified person that all engineering work required by this permit has been completed.
Advice:
Any final plan submitted for sealing will not be processed unless it is accompanied by documentation by a suitably qualified person that clearly certifies that this condition has been satisfied and that all the work required by this condition has been completed. A 'suitably qualified person' must be a professional engineer or professional surveyor or other persons acceptable to the Council.
Reason for condition
To ensure that the developer provides the Council with clear written confirmation that the separation of services is complete.
SUB s1
The existing drainage easement 2.50 m wide through Lots 1 and 2 is to be deleted by means of a section 103 amendment to Sealed Plan 159808 under the provisions of section 103 of the Local Government (Building and Miscellaneous Provisions) Act 1993 prior to the sealing of the final plan. Alternatively the section 103 amendment to delete the drainage easement is to be lodged concurrently at the Land Titles Office with the sealed final plan for the boundary adjustment.
Reason for condition
To ensure that a redundant easement is not brought forward to burden the lots on the final plan.
ADVICE – protection of historic track
If, the new stormwater connection to Sandy Bay Rivulet crosses remains of the historic track found on the site then the Applicant is encouraged to minimise disturbance to the track and reinstate the track to the state that it was prior to the works commencing.
ADVICE
The following advice is provided to you to assist in the implementation of the planning permit that has been issued subject to the conditions above. The advice is not exhaustive and you must inform yourself of any other legislation, bylaws, regulations, codes or standards that will apply to your development under which you may need to obtain an approval. Visit the Council's website for further information.
Prior to any commencement of work on the site or commencement of use the following additional permits/approval may be required from the Hobart City Council.
CONDITION ENDORSEMENT ENGINEERING
All engineering drawings required to be submitted and approved by this planning permit must be submitted to the City of Hobart as a CEP (Condition Endorsement) via the City’s Online Service Development Portal. When lodging a CEP, please reference the PLN number of the associated Planning Application. Each CEP must also include an estimation of the cost of works shown on the submitted engineering drawings. Once that estimation has been confirmed by the City’s Engineer, the following fees are payable for each CEP submitted and must be paid prior to the City of Hobart commencing assessment of the engineering drawings in each CEP:
Value of Building Works Approved by Planning Permit Fee: Up to $20,000: $150 per application. Over $20,000: 2% of the value of the works as assessed by the City's Engineer per assessment.
These fees are additional to building and plumbing fees charged under the Building and Plumbing Regulations.
Once the CEP is lodged via the Online Service Development Portal, if the value of building works approved by your planning permit is over $20,000, please contact the City’s Development Engineer on 6238 2715 to confirm the estimation of the cost of works shown on the submitted engineering drawings has been accepted.
Once confirmed, pleased call one of the City’s Customer Service Officers on 6238 2190 to make payment, quoting the reference number (ie. CEP number) of the Condition Endorsement you have lodged. Once payment is made, your engineering drawings will be assessed.
BUILDING PERMIT
You may need building approval in accordance with the Building Act 2016. Click here for more information.
This is a Discretionary Planning Permit issued in accordance with section 57 of the Land Use Planning and Approvals Act 1993.
PLUMBING PERMIT
You may need plumbing approval in accordance with the Building Act 2016, Building Regulations 2016 and the National Construction Code. Click here for more information.
OCCUPATION OF THE PUBLIC HIGHWAY
You may require a permit for the occupation of the public highway for construction or special event (e.g. placement of skip bin, crane, scissor lift etc). Click here for more information.
You may require an occupational license for structures in the Hobart City Council highway reservation, in accordance with conditions to be established by the Council. Click here for more information.
You may require a road closure permit for construction or special event. Click here for more information.
You may require a Permit to Open Up and Temporarily Occupy a Highway (for work in the road reserve). Click here for more information.
DRIVEWAY SURFACING OVER HIGHWAY RESERVATION
If a coloured or textured surface is used for the driveway access within the Highway Reservation, the Council or other service provider will not match this on any reinstatement of the driveway access within the Highway Reservation required in the future.
ACCESS
Designed in accordance with LGAT IPWEA – Tasmanian standard drawings. Click here for more information.
CROSS OVER CONSTRUCTION
The construction of the crossover can be undertaken by the Council or by a private contractor, subject to Council approval of the design. Click here for more information.
COUNCIL RESERVES
This permit does not authorise any works on the adjoining Council land. Any act that causes, or is likely to cause, damage to Council’s land may be in breach of Council’s Public Spaces Bylaw and penalties may apply. A permit is required for works on Council land. The bylaw is available here.
WORKS ABOVE HOBART RIVULET PARK
Your property is located above the Hobart Rivulet Park. In this area there have been a number of recent incidents of large rocks and other debris rolling down into the Park, as a direct result of construction activity above the Park. This presents a serious risk to Park visitors. Please implement appropriate measures to contain within your property boundary any debris resulting from your construction activity.
WORK PLACE HEALTH AND SAFETY
Appropriate occupational health and safety measures must be employed during the works to minimise direct human exposure to potentiallycontaminated soil, water, dust and vapours. Click here for more information.
NOISE REGULATIONS
Click here for information with respect to noise nuisances in residential areas.
WASTE DISPOSAL
It is recommended that the developer liaise with the Council’s Cleansing and Solid Waste Unit regarding reducing, reusing and recycling materials associated with demolition on the site to minimise solid waste being directed to landfill.
Further information regarding waste disposal can also be found on the Council’s website.
FEES AND CHARGES
Click here for information on the Council's fees and charges.
DIAL BEFORE YOU DIG
Click here for dial before you dig information.
|
||||||||||
PART B
That a traffic and parking management plan for Romilly Street, South Hobart be considered by the City Infrastructure Committee.
|
||||||||||
a Millard Ziegler - Deputation Supporting Information - 32 Romilly
Street ⇨ b Sam Stark / Felicity Spaulding - Deputation Supporting Information
- 32 Romilly Street ⇨ c Peter Blackwell - Deputation Supporting Information - 32 Romilly
Street ⇨ |
Delegation: Part A Council
Part B Committee
The Chairman adjourned the meeting at 6.54 pm for a comfort break.
The meeting was reconvened at 6.58 pm.
Item 7.1.4 was then taken.
There being no further business the meeting closed at 7.49 pm.
TAKEN AS READ AND SIGNED AS A CORRECT RECORD
THIS
14th DAY OF DECEMBER 2020.
CHAIRMAN